Lundy v. Illinois Department of Transportation

53 Ill. Ct. Cl. 181, 2001 Ill. Ct. Cl. LEXIS 15
CourtCourt of Claims of Illinois
DecidedMarch 26, 2001
DocketNo. 95-CC-3948
StatusPublished

This text of 53 Ill. Ct. Cl. 181 (Lundy v. Illinois Department of Transportation) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lundy v. Illinois Department of Transportation, 53 Ill. Ct. Cl. 181, 2001 Ill. Ct. Cl. LEXIS 15 (Ill. Super. Ct. 2001).

Opinion

OPINION

Epstein, J.

This is a swale case. This contract claim against the Respondent’s Department of Transportation (“IDOT”) for improper excavation/construction of an agreed swale is before us for final decision after trial to Commissioner James E. Shadid. We have the case on the pleadings, the trial record, which includes extensive technical testimony and exhibits, the report of the Commissioner and the parties’ post-trial briefs. Although the Respondent’s post-trial brief was unconscionably late, and was filed without leave of court, we allow the Respondent’s brief in the interest of assisting the Court through this large complex record, which we have reviewed in detail.

Nature of the Claim

This claim is brought as a breach of contract action. Claimant seeks contract damages for injury or loss of farming use of a portion of an 80-acre tract of farmland owned by Claimant Helen Lundy, and actively farmed by her tenant farmer, Claimant Jack Barnes, in Douglas County. (The subject property lies approximately one-half mile south of Areola, Illinois.) Claimants allege that IDOT breached — by improper performance — a written contract between Lundy and IDOT that provided for IDOT to excavate and regrade a portion of the Lundy land to improve and/or restore drainage for the adjacent State highway (Route 45) and, seemingly and perhaps incidentally, for the adjacent land area as well.

Claimant alleged that IDOT breached the specific terms of a letter agreement between Lundy and IDOT, dated December 11, 1991 (Complaint, Exhibit A) (executed by Lundy on January 8, 1992), that provided for IDOT to cut and restore a swale through the Lundy property for drainage purposes in accordance with a specific agreed plan that was reduced to drawings — particularly a “typical cross-section” of the proposed swale with specific dimensions — based on a current survey of the property. A second IDOT letter, dated March 31, 1992, and accepted by Lundy’s letter to IDOT of April 2, 1992 (Exhibit No. 17) modified the terms of the agreed excavation project somewhat.

Claimants alleged that IDOT’s excavation work, which was done in the Fall of 1992 and the Spring of 1993, and the resulting swale on the Lundy land, did not conform to the agreed specifications and resulted in the loss — i.e., the loss of its use for farming — of more than four acres of the Lundy farmland and the consequent loss of farm income to Claimant Barnes.

Claimants also complain, inter alia, that the resulting swale “is so deep that it has effectively split the farm into two halves so that farm equipment, machinery and vehicles cannot cross [the swale]” (Complaint, par. 7, 8), which Claimants maintain is contrary to representations that were made by IDOT officials to Claimant Barnes during the discussions of the swale project with Mrs. Lundy’s attorney. Claimants also complain that the swale causes water “to flow onto the farm and to remain standing rather than draining away, causing a permanent bog” (Complaint, par. 8), thus reducing usable farm acreage. Finally, Claimants assert some oral agreements and representations as to the process of the IDOT excavation work, including the giving of notice to Mr. Barnes and an opportunity for him to be present during the work, doing the work only when the ground was dry, and disposing of the excavation debris by distribution on the remainder of the Lundy land.

Claimants seek $100,000 compensatory damages, which they do not allocate between themselves in their complaint.

Nature of the Defense

IDOT has defended this claim on the bases: (1) that it did not breach, or did not materially breach, the agreement as to the specified dimensions of the swale; (2) that the “representations” allegedly made to the Claimants were not part of any of the letter agreements between the parties and are not actionable in this contract case, as they were not pleaded; (3) that Claimant Jack Barnes is not a party to the Lundy-IDOT agreements and cannot claim contract rights or contractual inducement by IDOT “misrepresentations”; (4) that IDOT did not agree or represent to Mrs. Lundy that farm operations would be unaffected and unreduced by the swale, and (5) that it was clear and was understood that part of the swale project was to restore a prior drainage swale through the Lundy lands that had silted up due to silt deposits carried by water flow to obstruction(s) located on the Lundy land, as well as from farming activities above and below obstruction^) on the property, and that Mrs. Lundy and Mr. Barnes knew or should have known that removal of the siltage would reduce the farmable acreage that Mr. Barnes had been farming on the siltage built up in the prior swale area.

The Trial Record

Claimant Barnes was the sole occurrence witness for the Claimants, who also presented one expert witness, John C. Guillou, an engineer. Respondent presented the testimony of Jerry Wilhoit, a field maintenance official of IDOT, Kevin Knoepfel, a bridge and hydraulic engineer, Leon Gobel, also of IDOT, who was Respondents sole occurrence witness, and Jack Barnes as an adverse witness.

The parties introduced numerous exhibits, relating to the parties’ negotiations and agreements, relating to the engineering and construction of the swale, and relating to the drainage characteristics of the Lundy property and adjacent areas.

The Evidence

We summarize the evidence by adopting the trial summary report of our Commissioner, here excerpted:

“The contract, when finally approved, was by way of letter of December 11,1991 and March 31,1992 from the Illinois Department of Transportation to Mrs. Lundy. A survey had been completed that time and decisions had been made based upon the survey. The drawing showed a proposed typical cross-section of a swale with a 70-foot tip width and 10-foot bottom width, 10:1 side slope and a 3-foot nominal depth. Ms. Lundy accepted IDOT’s by sending a letter in return on April 2,1992. (Exhibit 17.)
Exhibit 18 was one last IDOT memo to the file, dated April 2, 1992. It memorialized a meeting between Gobel, Mrs. Lundy, Mr. Barnes, and Bum-pus (Exhibit 18). Mr. Barnes made certain requests which are noted in the memo, including that he be notified prior to the start of any work at his specific telephone number. It was after this meeting, and obtaining IDOT’s agreement to Mr. Barnes’ request, that Mrs. Lundy signed and returned the proposal letter. (Exhibit 18.)”

The actual excavation began in the Fall of 1992 and was completed in the Spring of 1993.

During this trial, there was often complicated and complex testimony about waterflow through the property and location of field tiles as well as siltation buildup.

Plaintiffs expert, John C. Guillou, testified that he was an engineer with degrees from the University of Southern California and University of Illinois. Exhibit 22 was a copy of his curriculum vitae. In preparation for his testimony, Guillou had reviewed various documents and physically visited the land in question on August 4, 1995, September 12, 1995, December 1, 1995, December 30, 1995 (actually 1996; T. 121), and January 21, 1998. Group Exhibit 30 is a series of 25 photographs he took on September 12,1995.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
53 Ill. Ct. Cl. 181, 2001 Ill. Ct. Cl. LEXIS 15, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lundy-v-illinois-department-of-transportation-ilclaimsct-2001.