Lundberg v. Corporation of Catholic Archbishop

346 P.2d 164, 55 Wash. 2d 77, 1959 Wash. LEXIS 489
CourtWashington Supreme Court
DecidedNovember 12, 1959
DocketNo. 34978
StatusPublished
Cited by7 cases

This text of 346 P.2d 164 (Lundberg v. Corporation of Catholic Archbishop) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lundberg v. Corporation of Catholic Archbishop, 346 P.2d 164, 55 Wash. 2d 77, 1959 Wash. LEXIS 489 (Wash. 1959).

Opinion

Ott, J.

The Corporation of Catholic Archbishop of Seattle, hereinafter referred to as the owner, employed Johnston-Campanella, hereinafter referred to as the architects, to prepare plans and specifications for the construction of a church, convent, school, and rectory near Kirkland. The architects employed Ruskin Fisher & Associates, hereinafter referred to as the engineer, to perform the necessary engineering work, as well as to establish elevations and grades for a gravity-flow sewer system from the buildings, when constructed, to connect with a designated trunk line of the Kirkland sewer system. The elevations and grades furnished by the engineer were shown on the plans and specifications which were given to contractors for their preparation of bids.

The owner contracted with various contractors separately for the construction of the buildings, the plumbing, and the sewer system. There was to be no general contractor in charge of the overall construction work. Because of the owner’s method of accomplishing its building program, the contracts provided that each contractor was to co-ordinate his work with that of the others. The architects had general supervision, inspection, and approval of the work of the various contractors.

During the construction of the rectory, referred to as Unit D, it became necessary to lower the elevation of the building below that shown in the architect’s plans. This change necessitated lowering the elevation of the outfall from Unit D to the sewer accordingly. The structural change was completed and in place prior to the date of letting the contract for the construction of the gravity-flow sewer system.

[79]*79When the owner asked for bids for the construction of the sewer system, it furnished the prospective bidders with a copy of the engineer’s original plans, which indicated the higher elevation for Unit D as originally designed, and did not indicate the lower elevation as Unit D was then actually constructed. The Lundberg Construction Company, hereinafter referred to as the contractor, was the successful bidder.

The sewer construction contract provided, inter alia, that the contractor was to construct the main line in the street and connect the units to the main line at the owner’s property line, and that the main line was to connect with the city of Kirkland’s trunk-line system. The locations of the feeder lines from the buildings were to be shown by stakes on the property line at the end of each side sewer. In this regard, the contract provided:

“Special Conditions . . . Article 13. Side Sewers. The Contractor shall connect all side sewers into the sewer main. The location of the side sewers shall be shown by a stake on the property line at the end of the side sewers.”

The contract further provided:

“Art. 35. Separate Contracts.—The Owner reserves the right to let other contracts in connection with this work. The Contractor shall afford other contractors reasonable opportunity for the introduction and storage of their materials and the execution of their work, and shall properly connect and coordinate his work with theirs.
“If any part of the Contractor’s work depends for proper execution or results upon the work of any other contractor, the Contractor shall inspect and promptly report to the Architect any defects in such work that render it unsuitable for such proper execution and results. His failure so to inspect and report shall constitute an acceptance of the other contractor’s work as fit and proper for the reception of his work, except as to defects which may develop in the other contractor’s work after the execution of his work.
“To insure the proper execution of his subsequent work the Contractor shall measure work already in place and shall at once report to the Architect any discrepancy between the executed work and the drawings .” (Italics ours.)

[80]*80One of the special conditions of the contract provided that the grade elevations shown in the plans were to be followed:

“2. Excavation
“A. General
“The Contractor shall do all excavation of whatever substances encountered to depth shown on drawings. Excavated materials not required for fill or backfill shall be removed from site as directed by the Engineer and disposed of by the Contractor.
“Excavation for manholes and other accessories to have 12-inch minimum and 24-inch maximum clearance on all sides.
“Excavation shall not be carried below the required level.
“Excess excavation below required level shall be back-filled at the Contractor’s expense with earth, sand, gravel, or concrete, as directed by the Engineer, and thoroughly tamped.” (Italics ours.)

A further special condition relating to the surveys and grade elevations was as follows:

“Article 1. Surveys, Lines, and Grades
“The Contractor will make his own surveys and establish his own grades after the Engineer furnishes the basic bench marks.”

May 31, 1957, the contractor called the architects to determine the location of the line for the main sewer and was advised by them that it would be necessary for him to determine the proper location and grade for the gravity-flow sewer (article 1, supra). The contractor told the architects that he was not aware that his contract with the owner required him to provide placement or grade elevations, and that he had not included any engineering costs in his bid. Because of the contractor’s oversight in this regard, the owner contributed ninety dollars toward the contractor’s engineering expense.

Thereafter, the contractor employed the same engineer that the owner had previously employed for the preparation of the original plans to give him the proper location and grade stakes for the sewer line. Although the outfall from Unit D had been lowered and was then in place; this structural change was apparently disregarded.

[81]*81By June 17th, the contractor had constructed the main sewer line from the Kirkland trunk line to the street intersection of 120th avenue N. E., which was adjacent to the newly constructed buildings, and which street was to contain the vital main sewer line to which the laterals from the building units, including Unit D, were to be attached. The contractor observed that there were no location stakes at the property line, as required by article 13. He contacted the persons in charge of the construction of the various units to ascertain the sewer locations and outfall elevations. When he contacted the person in charge of Unit D, he was advised that the outfall elevation then in place was “pretty deep.” The record indicates that it would have required approximately one hour’s work for the contractor to have ascertained precisely how deep “pretty deep” was. However, he did not “measure work already in place,” but, instead, constructed the main sewer line pursuant to the elevations and grades as shown on the owner’s original plans and drawings.

On June 19th, when putting the feeder line connections in place, the contractor discovered that he had constructed the main line too high for gravity flow from Unit D.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gross v. City of Lynnwood
583 P.2d 1197 (Washington Supreme Court, 1978)
Bassan v. Investment Exchange Corp.
524 P.2d 233 (Washington Supreme Court, 1974)
Shell Oil Co. v. Livingston Fertilizer & Chemical Co.
513 P.2d 861 (Court of Appeals of Washington, 1973)
Dobias v. Western Farmers Ass'n
491 P.2d 1346 (Court of Appeals of Washington, 1971)
Stratton v. U. S. Bulk Carriers, Inc.
478 P.2d 253 (Court of Appeals of Washington, 1970)
Lundberg v. CORP. OF CATH. ARCHBISHOP OF SEATTLE
346 P.2d 164 (Washington Supreme Court, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
346 P.2d 164, 55 Wash. 2d 77, 1959 Wash. LEXIS 489, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lundberg-v-corporation-of-catholic-archbishop-wash-1959.