Lund v. Washoe County

31 Nev. 227
CourtNevada Supreme Court
DecidedApril 15, 1909
DocketNo. 1767
StatusPublished

This text of 31 Nev. 227 (Lund v. Washoe County) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lund v. Washoe County, 31 Nev. 227 (Neb. 1909).

Opinion

By the Court,

Talbot, J.:

This appeal is from a judgment, and is based on the judgment roll. The only contention of the appellant is that the complaint, which contains the following allegations, does not state a cause of action:

" (2) On or about the 14th day of August, 1907, the parties, plaintiff and defendant, made and entered into a valid written contract, whereby, for a valuable consideration therein named, the plaintiff undertook and agreed to erect, build, and finish certain piers and abutments on a certain public bridge in the said county known as Mayberry bridge, and to do similar work on a certain other public bridge, also situate in said county, known as Verdi bridge; both of said bridges being erected over and across the Truckee River, and intended for the use of public travel. That it was provided in said contract that the work should be ' conformable to the plans and specifications of the said work on file in the office of the county clerk of said Washoe County,’ to which plans and [232]*232specifications and said agreement on file in said county clerk’s office the plaintiff hereby refers.

" (3) And in and by said contract it was further provided that the work should be done to the satisfaction, and under the direction, of F. R. Nicholas, to be testified by his writing or certificate; and plaintiff avers that he undertook and performed all of the matters and things in and by the said contract to be by him done, performed, and kept, and that the said F. R. Nicholas gave the certificate approving the work of the plaintiff as required.

" (4) That in the performance of the said contract by the plaintiff certain extra xvork, not provided for in the same, and not shown, or in any wise indicated, by the plans and specifications aforesaid, consisting of excavations for the foundations of said piers, was ordered by the said F. R. Nicholas, the engineer in charge, for and on behalf of the said defendant, and was necessary to be done and performed. That under the direction of the said engineer the plaintiff thereupon did and performed the same. That the cubic measurement of such excavation is shown by tire schedule hereto annexed and made a part hereof, and to which reference is hereby made. That the price charged therefor, namely, the sum of $1.50 per cubic yard, is a fair and reasonable rate or charge, and is the reasonable value of the extra work so done and performed.

" (5) That the total value of said excavation work was the sum of $167.55, and that the balance of said extra-work, entirely without the said contract and the plans and specifications aforesaid, and ordered by the said engineer to be done as necessary extra work, and so accordingly done, performed, and furnished by the plaintiff, consisted in the removal of rock wall at said Mayberry bridge for which the plaintiff has charged the sum of $70; also rock wall removed at Verdi bridge, for which the plaintiff has charged the sum of $75. That such charges are the fair and reasonable value of the said extra works, and that the same are set out in the schedule hereinbefore referred to, and to which reference again is hereby made.

" (6) That the total cost and value of all of the said extra [233]*233work so clone, furnished, and performed by the plaintiff for the said defendant is the sum of $312.55, and the claims therefor have been duly made by the plaintiff to the board of county commissioners of said defendant, and the same have not been allowed.”

Section 2111 of the Compiled Laws gives boards of county commissioners power to control and manage public roads and bridges within their respective counties, and to make such orders as may be necessary to carry this control and management into effect. It is further provided as follows:

Section 448, approved March 9, 1866: "All work hereafter done upon highways, streets or alleys, whether in opening, improving or keeping the same in repair, shall, when the public cost of such contemplated work shall exceed one hundred dollars, be done by contracts let to the lowest responsible bidder, and public notice of at least five days shall be given, describing the work to be done, the time and place that bids will be received, and the means of paying for such work. Such bids shall be sealed, may all be rejected, and if any are accepted, it shall be that of the lowest bidder who is responsible, or will give satisfactory security. In all cases of emergency, it shall be discretionary with the board of county commissioners to let contracts for repairs without giving the five days’ notice, as is contemplated in this section.”

Section 437, approved February 21, 1877: "No bridge, the cost of the construction or repair of which will exceed the sum of one hundred dollars, must be constructed or repaired except on an order of the board of county commissioners. When ordered to be constructed or repaired, the contract therefor must be let out to the lowest bidder, after reasonable notice given by the board of county commissioners, by publication at least two weeks in a county newspaper, and if none, then by three posted notices—one at the court-house, one at the point to be bridged, and one at some other neighboring place. The bids to be sealed, opened and contract awarded at the time specified in the notice. The contract and bond to perform it must be entered into to the approval of the board of county commissioners.”

No officer excepting the board of county commissioners is [234]*234given any authority to obligate the county for bridges, or.for work upon public highways, and it is clear from the language of the statute that the board is not authorized to let contracts in excess of $100 for the construction or repair of bridges or roads, except to the lowest bidder, after giving notice, or in cases of emergency.

On behalf of the appellant it is claimed that the board, composed of the elective officers of the people, could not delegate to the engineer, or to any one else, their discretionary power to contract for or order work done, and could not authorize the extra work itself, without advertising for bids, as it amounted to over $100. These propositions do not come directly within the facts stated in the complaint, for it fails to show that the board without advertising, or in any other way, ordered the extra work, recovery for the value of which is sought, or attempted to authorize the engineer to order it done. Paragraph 2 of the complaint indicates that the plaintiff had contracted to build and finish certain abutments and piers for the bridges named, in accordance with the plans and specifications on file in the clerk’s office, paragraph 3 that this work should be done to the satisfaction and under the direction of the engineer, and paragraph 4 that certain extra and necessary work, not provided for in the contract or in the plans or specifications, consisting of excavations ordered by the engineer, was done under his direction. As there is no statute vesting the engineer with any power to create a liability against the county, and it does not appear from the complaint or contract that the board attempted to confer upon him any authority to order additional work to be done, or- to do more than to supervise, direct, and report upon the work provided for in the contract, there is a failure to state a cause of action. This would be true even in the absence of the prohibitory language quoted from the statute.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Zottman v. City & County of San Francisco
20 Cal. 96 (California Supreme Court, 1862)
Sadler v. Board of County Commissioners
15 Nev. 39 (Nevada Supreme Court, 1880)
Jos. Schlitz Brewing Co. v. Grimmon
28 Nev. 235 (Nevada Supreme Court, 1905)
Travers v. Barrett
30 Nev. 402 (Nevada Supreme Court, 1908)
Springfield Milling Co. v. Lane County
5 Or. 265 (Oregon Supreme Court, 1874)
Brady v. Mayor of New York
2 Bosw. 173 (The Superior Court of New York City, 1867)
Pacific Bridge Co. v. Clackamas County
45 F. 217 (U.S. Circuit Court for the District of Oregon, 1891)

Cite This Page — Counsel Stack

Bluebook (online)
31 Nev. 227, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lund-v-washoe-county-nev-1909.