Lund-Ross Constructors v. Vecino Natural Bridge, LLC

District Court, D. Nebraska·Decided August 30, 2023·No. 8:19-cv-00550·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEBRASKA

LUND-ROSS CONSTRUCTORS, INC.,

Plaintiff/Counter- 8:19CV550 Defendant,

v. MEMORANDUM AND ORDER VECINO NATURAL BRIDGE, LLC,

Defendant/Counter- Plaintiff.

This matter is before the Court on defendant/counter-plaintiff Vecino Natural Bridge, LLC’s (“Vecino”) Second Motion for Partial Summary Judgment (Filing No. 76), Vecino’s Motion in Limine (Filing No. 80), and plaintiff/counter-defendant Lund-Ross Constructors, Inc.’s (“Lund-Ross”) combined Motion for Partial Summary Judgment and Motion in Limine (Filing No. 84). For the reasons stated below, Vecino’s motion in limine is granted; its motion for partial summary judgment is granted in part and denied in part. Lund-Ross’s combined motion is denied in its entirety. I. BACKGROUND A. Facts This construction-contract dispute is back before the Court after several months of discovery and a failed attempt at settlement. See Lund-Ross Constructors, Inc. v. Vecino Nat. Bridge, LLC, No. 8:19CV550, 2021 WL 6202667, at *7 (D. Neb. Nov. 3, 2021) (granting Vecino’s motion for partial summary judgment in part). Both parties agree that trial will be necessary in this diversity case and that certain issues should be decided by the court as a matter of Nebraska law. See Erie R. Co. v. Tompkins, 304 U.S. 64, 78 (1938); Crain v. Crain, 72 F.4th 269, 279 (8th Cir. 2023) (describing the agreed application of state substantive law in a diversity case under 28 U.S.C. § 1332(a)(1)). Unfortunately, they do not agree as to what those issues are. Still, many of the underlying facts are uncontested. Lund-Ross is a general contractor that constructs projects across the Midwest. Vecino is a real-estate developer that owns real property near the campus of Creighton University in Omaha, Nebraska. On October 4, 2017, Lund-Ross and Vecino entered into a standard-form contract (the “contract”) for the construction of a two-building apartment complex for student housing on Vecino’s property (the “project”) with a Guaranteed Maximum Price of $24,114,417.00 at execution. Section 11.5.2 of the contract included non-standard provisions regarding project timing and completion and liquidated damages for breach (the “liquidated-damages provision”). In particular, the contract provided Lund- Ross would incur liquidated damages if the project was not complete by May 31, 2019, for any reason. The contract identified three categories of liquidated damages: (1) daily/monthly damages, (2) hotel costs and per diem, and (3) lost leases. About two years after the contract was executed, with construction ongoing, Vecino notified Lund-Ross it intended to terminate the contract for cause effective October 14, 2019. Vecino asserted Lund-Ross repeatedly failed to supply sufficient skilled labor for the project and failed to complete it on time. Vecino eventually hired a replacement contractor, Ideal Construction (“Ideal”), which completed a punch list on the project on October 16, 2020, though some minor work remains. Vecino seeks “at least” $1,100,878.58 in liquidated damages and other “mitigation” damages as a result of Lund- Ross’s breach of contract. Attributing some of the delay in completing the project to Vecino, Lund-Ross seeks to recover amounts it says it is owed for the work it did under the contract before termination. In Lund-Ross’s view, even if the liquidated-damages provision is valid under Nebraska law, Vecino waived its rights to enforce it. Lund-Ross also disputes Vecino’s damage calculations and questions whether the terms of Vecino’s agreement with Ideal and their post-termination practices unfairly left Lund-Ross on the hook for additional liquidated and consequential damages. B. Procedural History On October 17, 2019, Lund-Ross sued Vecino and others in the District Court of Douglas County, Nebraska (Filing No. 1-2), seeking to enforce its construction lien on the project under Neb. Rev. Stat. § 52-155 and alleging breach of contract, quantum meruit, and unjust enrichment. On December 16, 2019, Vecino removed the case to this Court with the consent of Springfield First Community Bank (“Springfield”), the only other defendant remaining at that point (Filing No. 1).1 Vecino then filed an answer and asserted counterclaims against Lund-Ross for breach of contract, wrongful recording of a lien pursuant to Neb. Rev. Stat. § 52-157, declaratory judgment, and unjust enrichment (Filing Nos. 8 and 24). Lund-Ross responded to the counterclaims (Filing No. 23) and later dismissed Springfield as a party (Filing Nos. 25 and 26). As the case moved forward, the parties advised the magistrate judge assigned to the case that a motion for summary judgment on an issue of contract interpretation might allow them to streamline this case and avoid unnecessary discovery (Filing No. 37). On August 20, 2021, Vecino moved for partial summary judgment (Filing No. 38), asking the Court to find as a matter of law that (1) § 11.5.2 of the contract included a “Final Completion Date of May 31, 2019,” that “was not extendable under the [contract],” (2) the liquidated-damages provision in § 11.5.2 was enforceable, and (3) Vecino was entitled to recover liquidated damages from Lund-Ross. The Court granted the motion in part and denied it in part. See Lund-Ross, 2021 WL 6202667, at *7. The Court found that § 11.5.2 set a fixed completion date of May 31,

1In removing the case, Vecino requested a jury trial. The parties’ briefs also frequently argue in terms of how the jury will view the evidence and decide the issues. In contrast, the parties’ joint Report of the Parties’ Planning Conference (Filing No. 14) indicates that neither “party has timely demanded a jury trial.” Based on that statement, the magistrate judge set this case for a non-jury trial. The Court has accounted for that in its analysis. 2019, and that the liquidated-damages provision was not an unenforceable penalty under Nebraska law. See id. But the Court concluded “open questions regarding waiver and other damage issues preclude[d] any assessment of damages at [that] time.” See id. Over the next several months, the parties conducted extensive discovery and participated in a settlement conference with the magistrate judge. When those efforts at settlement proved unsuccessful, the parties filed the pending cross-motions for partial summary judgment and cross-motions in limine. A bench trial is currently set for February 12, 2024. II. DISCUSSION A. Motions in Limine 1. Standard of Review Lund-Ross and Vecino have each filed a motion in limine. Such motions generally allow a party to seek “to exclude evidence before it is offered” at trial or another proceeding. United States v. Roenigk, 810 F.2d 809, 815 (8th Cir. 1987); see also Luce v. United States, 469 U.S. 38, 40 n.4 (1984) (“Although the Federal Rules of Evidence do not explicitly authorize in limine rulings, the practice has developed pursuant to the district court’s inherent authority to manage the course of trials.”). As with all evidentiary rulings, the Court has considerable discretion in deciding a motion in limine. See United States v. Daniels, 932 F.3d 1120, 1123 (8th Cir. 2019); Spencer v. Young, 495 F.3d 945, 949 (8th Cir. 2007). 2.

Free access — add to your briefcase to read the full text and ask questions with AI

Lund-Ross Constructors v. Vecino Natural Bridge, LLC, (D. Neb. 2023).

Lund-Ross Constructors v. Vecino Natural Bridge, LLC (Lund-Ross Constructors v. Vecino Natural Bridge, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Luce v. United States
469 U.S. 38 (Supreme Court, 1984)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Daubert v. Merrell Dow Pharmaceuticals, Inc.
509 U.S. 579 (Supreme Court, 1993)
United States v. Wayne Roenigk
810 F.2d 809 (Eighth Circuit, 1987)
United States v. James C. Dunkel
927 F.2d 955 (Seventh Circuit, 1991)
United States v. Jimmy Lee Stuckey, Jr.
255 F.3d 528 (Eighth Circuit, 2001)
Dallas v. American General Life & Accident Insurance
709 F.3d 734 (Eighth Circuit, 2013)
Mann v. Yarnell
497 F.3d 822 (Eighth Circuit, 2007)
Spencer v. Young
495 F.3d 945 (Eighth Circuit, 2007)
Ciomber v. Cooperative Plus, Inc.
527 F.3d 635 (Seventh Circuit, 2008)
Davenport Ltd. v. 75th & Dodge I
780 N.W.2d 416 (Nebraska Supreme Court, 2010)
Abel Construction Co. v. School District of Seward
195 N.W.2d 744 (Nebraska Supreme Court, 1972)
Parsons Construction Co. v. Metropolitan Utilities District
104 N.W.2d 272 (Nebraska Supreme Court, 1960)
Kozlik v. Emelco, Inc.
483 N.W.2d 114 (Nebraska Supreme Court, 1992)