Lump v. Best Door and Window, Unpublished Decision (3-27-2002)

CourtOhio Court of Appeals
DecidedMarch 27, 2002
DocketCase No. 8-01-09.
StatusUnpublished

This text of Lump v. Best Door and Window, Unpublished Decision (3-27-2002) (Lump v. Best Door and Window, Unpublished Decision (3-27-2002)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lump v. Best Door and Window, Unpublished Decision (3-27-2002), (Ohio Ct. App. 2002).

Opinions

OPINION
Appellant's, Mike and Amy Lump, appeal the June 6, 2001 judgment entry of the Logan County Court of Common Pleas, granting partial summary judgment in favor of the appellee, Best Door Window, Inc., as to the claims involving alleged violations of the Ohio Consumer Sales Practices Act, Case No. 8-01-09. In addition, the Lumps appeal the June 8, 2001 judgment entry of the Logan County Court of Common Pleas, granting partial summary judgment in favor of the appellee, Modern Builders Supply, Inc., as to the claims involving alleged violations of the Ohio Consumer Sales Practices Act, Case No. 8-01-10. Pursuant to this Court's journal entry, dated August 1, 2001, and filed on August 2, 2001, these two appeals were consolidated.

Many of the facts of this case are in dispute. However, the general chronology of events leading to this litigation is as follows. The Lumps decided to build a home and hired builder, Wayne Lumbatis, as the general contractor for this project sometime in 1999. In an effort to save money, the Lumps agreed to paint and stain the interior of the home and to do the trim work, themselves. However, Mr. Lump wanted to have the labor that he was to do completed by February 2000, because of his schedule at work.

In the summer of 1999, Mr. Lump contacted Kevin Boone, president and general manager of Appellee Best Door Window, Inc. (hereinafter "Best"), about ordering windows for the home that Lumbatis was building for the Lumps. The parties discussed the ordering of windows several times over the next few months, and Boone eventually placed the order for windows, as well as related items, for the Lumps with co-appellee, Modern Builder Supply, Inc. (hereinafter "Modern"), in late November of 1999. The order form sent to Modern contained the sizes for the various windows. On November 29, 1999, Boone received a letter from Modern that confirmed Modern's receipt of the order.

After placing the order, Boone met with Lumbatis at the construction site, and the two discussed the sizes of the various windows. Lumbatis recorded each window's size on the blueprints for the home according to the dimensions provided to him by Boone. The reason for doing so was that Lumbatis needed to know what size to make the rough openings in the house for the windows. Lumbatis also informed the parties that the windows needed to meet the applicable egress codes in order to pass the building inspection.

The Lumps maintain that prior to ordering the windows, Mr. Lump expressed to Boone the need for the windows to arrive quickly so that he could do the work that he was supposed to do inside of the house. According to Mr. Lump, Boone told him that the windows would arrive by December 13, 1999. However, this date was not written on the order form placed with Modern by Boone. Boone, while not admitting to providing a firm delivery date to Mr. Lump, did admit that this date coincided with the normal delivery time for such an order.

When none of the windows or related items arrived on December 13, 1999, Mr. Lump contacted Boone, who could not provide an explanation for the delay at that time. Mr. Lump called Boone approximately one week later to once again inquire about the delay, and again, Boone did not provide an explanation for the delay. At the end of December 1999, Mr. Lump called Boone a third time, and Boone relayed that he had talked to Modern but had no more details. Boone did not reveal to Mr. Lump that Modern's factory would be closed for two weeks during the holiday season although he knew this to be true.

At this point, Mr. Lump requested that Boone provide him with a contact number for Modern. Thereafter, Mr. Lump contacted Ron Keplinger, a representative of Modern, on several occasions to discuss the delivery delay, as well as an expected delivery date. However, Keplinger did not provide an explanation. Mr. Lump then spoke with the manager, Mike Schweigert, on at least two occasions. Sometime during his conversations with representatives of Modern and Best, Mr. Lump did discover that Modern had not promptly processed the order upon receiving it from Best.

The windows did not arrive at the construction site until the middle of January 2000, and two of the ordered windows were missing. Mr. Lump once again contacted Keplinger, this time to investigate where the other two windows were. Mr. Lump maintains that Keplinger told him that these two windows were placed on a separate order for some unknown reason but that they would arrive within the week. When they did not arrive within the week, Mr. Lump contacted Keplinger and was given another delivery date. He then contacted Schweigert and Keplinger. Throughout the course of these conversations, Mr. Lump received approximately four different delivery dates for the two missing windows. At some point, Mr. Lump told Schweigert about the financial problems being caused by not having the windows and requested that Modern do something to make the situation "right" or else Modern could take the windows back. Mr. Lump contends that Schweigert told him that Modern would do whatever it took to rectify the situation. The missing windows arrived in early February of 2000. However, by this time, Mr. Lump claims that he could not perform the work inside the house that he had agreed to do because his work schedule prevented him from doing so.

Moreover, while attempting to install the windows that were delivered, Lumbatis discovered that several of the windows did not fit the rough openings. As a result, he had to adjust the size of the rough openings to accommodate the windows. Also, one of the windows that was to be mulled together by the manufacturer came in two separate pieces, and the window frame had to be changed to accommodate this style of window. A further problem with the windows was that the bedroom windows did not meet the applicable egress codes, and the window above the Jacuzzi tub was not made of tempered glass as it should have been for safety purposes. In addition, the Lumps discovered that the windows did not work properly in that someone had to go outside to shut the windows in order for them to latch. This discovery was not made until a few months after the windows were installed.

The Lumps filed suit against Best and Modern on May 12, 2001. The complaint against Best contained two counts of breach of contract, two counts of violations of the CSPA, two counts of violating express and implied warranties, and one count of fraud. The complaint against Modern contained two counts of violations of the CSPA, two counts of violating express and implied warranties, and one count of fraud. Best filed its answer to the complaint on June 14, 2000, and counterclaimed against the Lumps for failing to pay for the windows that they received. Modern filed its answer to the complaint on July 14, 2000.

On March 1, 2001, Best filed its motion for summary judgment as to all counts of the complaint against it, as well as on its counterclaim against the Lumps. On that same date, Modern filed a motion for summary judgment as to all counts of the complaint against it. On June 6, 2001, the trial court granted summary judgment in favor of Best as to the Ohio Consumer Sales Practices Act (hereinafter "CSPA") claims and as to the claim alleging fraud. Also, in its June 6, 2001, judgment entry, the trial court denied the motion for summary judgment as to the breach of contract claims, the breach of express/implied warranty claims, and as to the counterclaim. On June 8, 2001, the trial court granted summary judgment in favor of Modern as to the CSPA claims and as to the claim alleging fraud.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kraft, Inc. v. Federal Trade Commission
970 F.2d 311 (Seventh Circuit, 1992)
State Ex Rel. Fisher v. Rose Chevrolet, Inc.
612 N.E.2d 782 (Ohio Court of Appeals, 1992)
Charlie's Dodge, Inc. v. Celebrezze
596 N.E.2d 486 (Ohio Court of Appeals, 1991)
Funk v. Montgomery amc/jeep/renault
586 N.E.2d 1113 (Ohio Court of Appeals, 1990)
Renner v. Derin Acquisition Corp.
676 N.E.2d 151 (Ohio Court of Appeals, 1996)
Thomas v. Sun Furniture & Appliance Co.
399 N.E.2d 567 (Ohio Court of Appeals, 1978)
Lorain National Bank v. Saratoga Apartments
572 N.E.2d 198 (Ohio Court of Appeals, 1989)
Richards v. Beecumont Volvo
711 N.E.2d 1088 (Ohio Court of Appeals, 1998)
Garner v. Borcherding Buick, Inc.
616 N.E.2d 283 (Ohio Court of Appeals, 1992)
Frey v. Vin Devers, Inc.
608 N.E.2d 796 (Ohio Court of Appeals, 1992)
Crye v. Smolak
674 N.E.2d 779 (Ohio Court of Appeals, 1996)
Smaldino v. Larsick
630 N.E.2d 408 (Ohio Court of Appeals, 1993)
Einhorn v. Ford Motor Co.
548 N.E.2d 933 (Ohio Supreme Court, 1990)
Murphy v. City of Reynoldsburg
604 N.E.2d 138 (Ohio Supreme Court, 1992)
Brown v. Lyons
332 N.E.2d 380 (Court of Common Pleas of Ohio, Hamilton County, 1974)
Daniels v. True
547 N.E.2d 425 (Hamilton County Municipal Court, 1988)
Maricle v. United States
479 U.S. 829 (Supreme Court, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
Lump v. Best Door and Window, Unpublished Decision (3-27-2002), Counsel Stack Legal Research, https://law.counselstack.com/opinion/lump-v-best-door-and-window-unpublished-decision-3-27-2002-ohioctapp-2002.