Lumber Mart Co. v. Buchanan

419 P.2d 1002, 69 Wash. 2d 658, 1966 Wash. LEXIS 993
CourtWashington Supreme Court
DecidedNovember 3, 1966
Docket38325
StatusPublished
Cited by18 cases

This text of 419 P.2d 1002 (Lumber Mart Co. v. Buchanan) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lumber Mart Co. v. Buchanan, 419 P.2d 1002, 69 Wash. 2d 658, 1966 Wash. LEXIS 993 (Wash. 1966).

Opinion

*659 Langenbach, J.

This is an action by respondent to obtain a judgment for materials furnished in construction of a building and to foreclose a materialman’s lien. Appellants denied the allegations and cross-claimed for wages paid. From a judgment of foreclosure, appellants have appealed.

In July, 1962, appellants leased certain premises, containing a dance hall, for a 3-year term to one McFerran for recreational-business purposes. In September, 1962, McFerran contemplated building, at his own expense, an ice arena by remodeling and adding to the dance hall. The appellants acquiesced in this project. McFerran contracted with one Geffe for the materials and used them to construct forms in which he poured cement for the foundation. He also used some of these materials to do some remodeling on the present building.

McFerran, however, became financially unable to complete the contemplated structure. Consequently, on December 4, 1962, appellant Buchanan, and Geffe, on behalf of respondent, contracted for the erection of the new building suggested by McFerran. Buchanan testified he did not know he had contracted with respondent. The contract, however, mentioned Lumber Mart. The confusion in names was caused by Geffe selling his business about this time to respondent as a newly-formed corporation. Under this contract, respondent agreed to furnish all the materials for a completed structure for the sum of $17,628. This contract was silent as to the furnishing of any labor except that of Geffe, who was to supervise the installation of the steel-span girders at his own expense.

Throughout the construction of the proposed ice arena, McFerran ordered the materials and generally supervised the construction. As to his capacity, however, the evidence was in sharp conflict. McFerran testified Buchanan hired him at $100 a week to supervise the construction. In the meantime, his lease had been terminated and he went into *660 bankruptcy. After the building was erected, McFerran released the premises.

Buchanan testified he merely loaned this $100 a week to McFerran for living expenses and McFerran was not acting as his agent but as lessee. The court found that McFerran was a general agent to oversee the construction. The court did not make any findings as to McFerran as lessee or as to the trustee in bankruptcy.

In addition to the materials covered by the written contract, the respondent made six deliveries of extra materials; apparently McFerran ordered them. McFerran used some of the extra materials to construct a paint shop for his father, as a part of the ice arena. Buchanan knew that Mc-Ferran had thus constructed the paint shop. The evidence was in conflict as to whether respondent had such knowledge at the time of such deliveries. The court found that it did not have such knowledge. The rest of the extras were used in and about the ice arena premises.

In using this extra material, wages were incurred in the amount of $1,225. The laborers complained of nonpayment to the State Department of Labor and Industries. After a conference with a representative of this department, appellants paid said wages. This was the basis for the cross-claim in this action. It was the contention of appellants that respondent’s manager agreed to make reimbursement, which was not done.

When appellants refused to pay for the extra materials, respondent filed its notice of claim of lien on April 24, 1963. Later this action was instituted.

During the trial, appellants made a demand for a jury trial and deposited the jury fee. The court refused to allow a jury trial at that stage of the case.

Respondent did not offer its lien until during its rebuttal. Appellants objected, among other grounds, that the description was defective. The lien described three tracts of land adjacent to the one on which the building had been erected and the materials used. The trial court, pursuant to RCW 60.04.060, allowed an amendment to the description to include the property on which the building had been con *661 structed and ruled that third party interests were not prejudiced.

On appeal, appellants argued the trial court erred in not holding (1) their nonliability for the extra materials; (2) the invalidity of the lien on several grounds; (3) appellants were entitled to a jury trial; and (4) liability of respondent for the $1,225 wages paid to the laborers.

There was a decided conflict in the evidence concerning the liability for the extra materials. Appellants asserted McFerran was not their agent, or if he was, he acted outside the scope of his authority in ordering extra materials; at least, those used in connection with the paint shop.

As appellants argued, the rule is that agency cannot be proven by declarations of the alleged agent. See, Ford v. United Brotherhood of Carpenters & Joiners of America, 50 Wn.2d 832, 315 P.2d 299 (1957). Other evidence, however, substantiated the trial court’s finding that McFerran was general agent to oversee the construction of the ice arena. Buchanan visited the building site on several occasions and knew what McFerran was doing. He made no complaint about his actions.

As to the extra materials, the court found in findings of fact No. 6, that “All of these materials were ordered by McFerron, were, in fact, installed in the building and were reasonably necessary to the completion of the building for its intended use as an ice arena.” The evidence sustained this finding.

As to those materials used in construction of the paint shop, the court found

[T]hat this extra work was specifically ordered by Mr. McFerron and though Buchanan may have understood that it was being done for McFerrons own benefit it clearly was not so understood by Geffe or the plaintiff [Lumber Mart] and it is again clear that the plaintiff [Lumber Mart] supplied the additional materials for the storage area at McFerrons request with no knowledge of any lack of his authority to order the additional work or materials. Finding of fact No. 8.

Appellants argued that respondent failed to *662 sustain its burden of proving agency. With this we do not agree.

It is a general rule, . . . that a corporation may be bound by the contracts or agreements of its agent if within the apparent scope of the agent’s authority, although the contract may be beyond the scope of his actual authority. [Citing cases.]
It is also the well-established rule that the apparent or ostensible authority of an agent can be inferred only from acts and conduct of the principal. [Citing cases.] Lamb v. General Associates, Inc., 60 Wn.2d 623, 627, 374 P2d 677 (1962).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McCormick v. Lake Washington School Dist.
992 P.2d 511 (Court of Appeals of Washington, 2000)
Blake Sand & Gravel, Inc. v. Saxon
989 P.2d 1178 (Court of Appeals of Washington, 1999)
McCormick v. Lake Washington School District
992 P.2d 511 (Court of Appeals of Washington, 1999)
Westberg v. All-Purpose Structures, Inc.
936 P.2d 1175 (Court of Appeals of Washington, 1997)
United States v. Omdahl
104 F.3d 1143 (Ninth Circuit, 1997)
Costco Wholesale Corp. v. World Wide Licensing Corp.
898 P.2d 347 (Court of Appeals of Washington, 1995)
Smith v. Hansen, Hansen & Johnson, Inc.
818 P.2d 1127 (Court of Appeals of Washington, 1991)
American Seamount Corp. v. Science & Engineering Associates, Inc.
812 P.2d 505 (Court of Appeals of Washington, 1991)
Amtruck Factors v. International Forest Products
795 P.2d 742 (Court of Appeals of Washington, 1990)
Bergin v. Thomas
638 P.2d 621 (Court of Appeals of Washington, 1981)
Schoonover v. Carpet World, Inc.
588 P.2d 729 (Washington Supreme Court, 1978)
Kiniski v. Archway Motel, Inc.
586 P.2d 502 (Court of Appeals of Washington, 1978)
Barnes v. Treece
549 P.2d 1152 (Court of Appeals of Washington, 1976)
Oliphant v. Oliphant
435 P.2d 29 (Washington Supreme Court, 1967)
Lamm v. McTighe
434 P.2d 565 (Washington Supreme Court, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
419 P.2d 1002, 69 Wash. 2d 658, 1966 Wash. LEXIS 993, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lumber-mart-co-v-buchanan-wash-1966.