Ludvik Electric Company v. Vanderlande Industries, Inc.

CourtDistrict Court, D. Utah
DecidedMarch 9, 2026
Docket2:21-cv-00462
StatusUnknown

This text of Ludvik Electric Company v. Vanderlande Industries, Inc. (Ludvik Electric Company v. Vanderlande Industries, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ludvik Electric Company v. Vanderlande Industries, Inc., (D. Utah 2026).

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF UTAH

LUDVIK ELECTRIC COMPANY, MEMORANDUM DECISION AND ORDER GRANTING [105] Plaintiff, DEFENDANT’S MOTION FOR PARTIAL SUMMARY JUDGMENT v. Case No. 2:21-cv-00462-DBB-CMR VANDERLANDE INDUSTRIES, INC, District Judge David Barlow Defendant.

Before the court is Defendant Vanderlande Industries, Inc.’s (“Vanderlande”) Motion for Partial Summary Judgment (the “Motion”)1 on the issue of damages against Plaintiff Ludvik Electric Company (“Ludvik”). BACKGROUND This case is about a construction dispute arising out of renovations on the Salt Lake City International Airport.2 HDJV, the general contractor for that project, subcontracted with Vanderlande to install the airport’s new baggage handling system.3 Vanderlande then sub- subcontracted with Ludvik for electrical and mechanical work relating to the baggage handling system.4 The court allowed the parties to bifurcate their discovery and dispositive motions to separately focus on two issues, liability and damages.5 On December 19, 2023, the court entered an order granting in part and denying in part Defendant’s motion for partial summary judgment

1 Motion for Partial Summary Judgment (“MSJ Damages”), ECF No. 105, filed Sep. 26, 2025. 2 Id. at 5. 3 Id. 4 Id. 5 See Ninth Amended Scheduling Order, ECF No. 104, entered June 18, 2025. on the issue of liability.6 Pursuant to that order, all of Plaintiff’s causes of action were dismissed

except its claim for negligent misrepresentation.7 Following an additional discovery period and numerous extensions of time, Vanderlande now moves for summary judgment on the issue of damages for the negligent misrepresentation claim.8 The court laid out much of the relevant background for this case in its previous order granting in part Defendant’s motion for partial summary judgment on the issue of liability.9 Only some of that extensive factual background will be repeated here. Pass-Through Claims In January 2019, Ludvik notified Vanderlande of certain “pass-through claims” that it wished to assert against HDJV through Vanderlande.10 These claims arose because of project delays that were caused by the project Owner or HDJV.11 Ludvik contends that, because of these

delays, its schedule was compressed without any corresponding extension, and it incurred unanticipated inefficiency costs of around $9.4 million.12 In July 2019, Vanderlande signed Change Order 22 with HDJV, which stated: “It is agreed and understood that all costs for changes initiated prior to January 1, 2019 have been received by HDJV and that no additional cost for change initiated during 2018 will be accepted.”13 Prior to signing, Vanderlande confirmed with HDJV that Change Order 22 would not waive Ludvik’s still-developing pass-

6 See Memorandum Decision and Order Granting in Part and Denying in Part Defendant’s Partial Motion for Summary Judgment (“Summ. J. Order Liability”), ECF No. 80, entered Dec. 19, 2023. 7 Id. 8 See MSJ Damages. 9 See Summ. J. Order Liability 1–7. 10 Id. at 2; Aff. of Douglas C. Alewelt (“Alewelt Aff.) ¶ 7, ECF No. 65-5, filed Apr. 17, 2023. 11 Alewelt Aff. ¶ 7. 12 Id.; Aperture Report 32–33, ECF No. 110-9, filed Nov. 21, 2025. 13 Summ. J. Order Liability 3; see also Change Order 22, ECF No. 65-6, filed Apr. 17, 2023. through claims.14 Shortly after Change Order 22 was signed, Ludvik submitted its pass-through

claim to Vanderlande, and Vanderlande submitted it to HDJV on August 15, 2019.15 HDJV rejected Ludvik’s pass-through claim in a letter to Vanderlande on October 1, 2019.16 One of the reasons for this rejection is that the claim was not preserved by Change Order 22 and was “time barred.”17 On December 6, 2019, Vanderlande signed Change Order 26, which contained similar language to Change Order 22, purporting to waive any claims initiated prior to June 1, 2019, and not included on the attached change order log.18 Vanderlande informed Ludvik that the claim had been rejected but did not forward the October 1 letter to Ludvik until December 12, 2019.19 Ludvik did not ask for clarification about whether its claims were time-barred, and the parties continued to discuss the denied pass-through claims.20 During these discussions, Vanderlande acted as if the claims were rejected due to form

and content inadequacies rather than any sort of waiver or time bar.21 Ludvik and Vanderlande ultimately executed a Settlement Agreement in August 2020.22 In that agreement, Ludvik released all of its claims against Vanderlande relating to the subcontract or the project except for its pass-through claims against HDJV.23 Vanderlande’s potential liability on those claims was limited to any amount paid by HDJV, and Vanderlande promised to cooperate with Ludvik in pursuing its pass-through claims.24

14 Summ. J. Order Liability 3; Alewelt Aff. ¶ 15. 15 Summ. J. Order Liability 3. 16 Id. 17 Id. at 3–4; Oct. 1, 2019, Letter, ECF No. 110-3, filed Nov. 21, 2025. 18 Change Order 26, ECF No. 110–12, filed Nov. 21, 2025. 19 Summ. J. Order Liability 4. 20 Id. at 4–5. 21 Id. 22 VI/LE Settlement Agreement, ECF No. 110-15, filed Nov. 21, 2025. 23 Id. § 5. 24 Id. §§ 5(a), 6(b). Ludvik later attended a mediation involving it, Vanderlande, HDJV, and the project owner.25 Ludvik states that during the mediation, it learned for the first time that its pass-through claims were not on the Change Order 22 or Change Order 26 logs and that HDJV considered that omission to be an affirmative waiver by Vanderlande of Ludvik’s pass-through claims.26 Ludvik asserts that, as a result of the waived pass-through claims, it was forced to accept a less-favorable settlement with HDJV.27 It ultimately settled and released all its claims against HDJV, including its pass-through claims.28 Ludvik / Vanderlande Agreements Vanderlande and Ludvik’s obligations and rights in this project are governed by a 2017 Project Subcontract Agreement (“PSA”),29 which also incorporates the terms of a prior Installation Service Agreement (“ISA”).30 Under § 11.2 of the ISA, if Ludvik has a claim against

HDJV, Vanderlande: may submit [Ludvik’s] claims to [HDJV] provided that (a) [Ludvik] has submitted notices and claim documents in the form required by the Main Contract and in sufficient time for [Vanderlande] to comply with the deadlines provided in the Main Contract; and (b) [Ludvik] shall accept [Vanderlande’s] prosecution of such claims at [Ludvik’s] expense and [Vanderlande’s] payment to [Ludvik] of any money that [Vanderlande] may receive from [HDJV] upon [Ludvik’s] claims, in full and complete satisfaction and liquidation of [Vanderlande’s] obligation to [Ludvik], it being understood and agreed that [Vanderlande] shall not have any other liability or responsibility to [Ludvik] by reason of Claims attributable to [HDJV].31

25 Declaration of James Ludvik (“Ludvik Decl.”) ¶ 14, ECF No. 110-7, filed Nov. 21, 2025. 26 Id. ¶ 15. 27 Id. ¶ 18. 28 HDJV/LE Settlement Agreement, ECF No. 105-8, filed Nov. 21, 2025. 29 VI/LE Subcontract (“PSA”), ECF No. 110-3, filed Nov. 21, 2025. 30 Id. at 1 (Expressly incorporating the Installation Agreement Standard Terms and Conditions); Installation Agreement (“ISA”), ECF No. 110-18, filed Nov. 21, 2025. 31 Id. § 11.2. A claim under this section is considered a “pass-through claim.” The ISA clarifies that Ludvik’s “entitlement to compensation” in a pass-through claim against HDJV via Vanderlande “is expressly contingent upon [Vanderlande’s] receipt of payment for [Ludvik’s] claim from [HDJV].32 The ISA also limits Vanderlande’s liability for damages arising out of inefficiencies or delays in § 4.3: [Ludvik] shall not be entitled to payment, damages, monies, or compensation from [Vanderlande] of any kind for direct, indirect or impact damages arising because of hindrance, inefficiency or delay from any cause whatsoever, whether reasonable or unreasonable, foreseeable or unforeseeable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Adler v. Wal-Mart Stores, Inc.
144 F.3d 664 (Tenth Circuit, 1998)
Stump v. Gates
211 F.3d 527 (Tenth Circuit, 2000)
United States v. Gordon
710 F.3d 1124 (Tenth Circuit, 2013)
Gadd v. Olson
685 P.2d 1041 (Utah Supreme Court, 1984)
WebBank v. American General Annuity Service Corp.
2002 UT 88 (Utah Supreme Court, 2002)
Green River Canal Co. v. Thayn
2003 UT 50 (Utah Supreme Court, 2003)
Zia Shadows, L.L.C. v. City of Las Cruces
829 F.3d 1232 (Tenth Circuit, 2016)
Gutierrez v. Luna County
841 F.3d 895 (Tenth Circuit, 2016)
Utah Power & Light Co. v. Federal Insurance
983 F.2d 1549 (Tenth Circuit, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
Ludvik Electric Company v. Vanderlande Industries, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/ludvik-electric-company-v-vanderlande-industries-inc-utd-2026.