Ludlow Valve Manufacturing Co. v. City of Chicago

181 Ill. App. 388, 1913 Ill. App. LEXIS 265
CourtAppellate Court of Illinois
DecidedJune 12, 1913
DocketGen. No. 18,244
StatusPublished
Cited by1 cases

This text of 181 Ill. App. 388 (Ludlow Valve Manufacturing Co. v. City of Chicago) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ludlow Valve Manufacturing Co. v. City of Chicago, 181 Ill. App. 388, 1913 Ill. App. LEXIS 265 (Ill. Ct. App. 1913).

Opinion

Mr. Justice Fitch

delivered the opinion of the court.

Appellee recovered a judgment against the city of Chicago for $1,000, alleged to be the balance due upon á contract for furnishing several hundred gate valves for use in connection with the city’s water supply system. The contract is dated August 21, 1906, and provides that gate valves of the number and sizes described in the specifications attached to the contract are to be furnished by appellee and delivered at the places named in the specifications, that such delivery shall “be commenced as provided in paragraph 21 of attached specifications, to progress * * * as provided in the specifications * * * and to be finished and fully completed as provided in paragraph 21 of attached specifications, the time of commencement, rate of progress and time of completion being essential conditions of this contract.” Paragraph 21 thus referred to provides that “the work shall be commenced immediately upon the acceptance of the bond filed with the contract, and the delivery of valves shall commence not later than thirty days from the date of said acceptance. * * * One-third of the whole number of valves shall be delivered within sixty days from the date of above acceptance, one-third in ninety days from said date, and the remaining one-third within four months from said date.” Paragraph 22 of the specifications is as follows: “It is distinctly understood and agreed by the parties hereto that the valves hereinabove mentioned shall be delivered within the times severally fixed for their delivery. Inasmuch as the failure to deliver said valves within the time herein fixed will work an injury to the city, and as the damages arising from such failure cannot be calculated with any degree of certainty, it is hereby agreed that if said valves are not fully delivered within the times fixed hereby, then there shall be deducted from the contract price and retained by said city as its ascertained and liquidated damages, the sum of $10 for each and every day passing after the date so fixed for such delivery until said valves are delivered. ’ ’ It was admitted upon the trial that all the valves specified in the contract were delivered to and received by the city in accordance with the contract, except as to the time of delivery. It appears also, from the evidence, that the bond required by the contract to be filed was approved by the Commissioner of Public Works on August 28, 1906. While there is some evidence tending to show that the contract was not signed by the city comptroller until September 18, 1906, we think the evidence to that effect is insufficient to overcome the express provision of the contract fixing the date of “the acceptance of the bond” as the date from which to compute the time of delivery. Under that provision the first one-third of the whole number of valves was required to be delivered before October 28, 1906; the second one-third before November 28, 1906, and the remainder to be delivered before December 28,1906. The evidence apparently shows that the first one-third of the valves were not fully delivered until November 25, 1906; the second one-third, until January 12, 1907, and the remainder, until January 24, 1907. Upon this basis, the total delay amounted to one hundred days time. On February 19, 1907, a final voucher and warrant were issued to appellee, showing that the total amount of the contract was $23,636.65, from which $10 a day was deducted as liquidated damages for the hundred days delay above mentioned, and the remainder was paid to appellee. On March 25, 1907, the Commissioner of Public Works wrote a letter to the finance committee of the city council, referring to appellee’s contract and stating: “I beg to submit the attached report of Engineer Shaw, in which he states that the City of Chicago received the valves as fast as needed and occasioned no damages. Under the circumstances, I respectfully recommend that the contract be extended to January 15, 1907, and that no deductions be made for forfeiture by reason of making such extensions. ’ ’ Acting upon this letter, the finance committee made a report, and on its recommendation, the city council passed an order, on May 6, 1907, and to correct a clerical error in that order, passed a second order on May 13, 1907, authorizing the Commissioner of Public Works to “extend the time” for completing the contract to January 15,1907, which that officer, by letter dated May 25, 1907, attempted to do. A further order was passed on November 24, 1907, purporting to “extend the time” for the final completion of the contract to January 28, 1907. It will be noticed that all of these orders were passed after the valves had all been delivered, after the deduction of $1,000 had been made, as above stated, and after a warrant had been issued and paid to appellee for the balance due by the terms of the contract. Appellee wrote into its receipt for the amount of the final voucher the words: “Without prejudice to our claim for the amount of penalty deducted.” No further payment was made, however, in pursuance of the council orders, and in December, 1910, appellee brought suit to recover the $1,000 deducted from the contract price of the valves.

Two questions are presented for our consideration: First, whether the provision authorizing the city to deduct $10 a day for delays in furnishing the material is to be construed as a provision for liquidated damages or merely as a penalty; second, whether the city council had the power, after all the materials had been delivered to the city, to waive the benefit of that provision, or (what amounts to the same thing) to “extend the time for performance” after the materials had all been delivered and nothing remained to he done but the payment of the price agreed upon.

It is often a difficult matter to determine whether a contract provision like the one here involved shall be construed as a provision for liquidated damages or only as a penalty. The primary and most essential principle of construction is to ascertain the meaning and intent of the parties, by reference to the contract itself, the subject-matter thereof, the terms used to express the intent, and the circumstances under which the contract was made. The fact that parties fix a sum to be paid in case of a breach of the contract and call that sum “liquidated damages” is not conclusive, but is one of the circumstances tending to prove the actual intent of the parties. Hennessy v. Metzger, 152 Ill. 505; Gobble v. Linder, 76 Ill. 157. In the latter ease it is said: “It will be inferred the partiés intended the sum named as liquidated damages where the damages arising from the breach are uncertain, and are not capable of being ascertained by any satisfactory and known rule, or where, from the nature of the case and the tenor of the agreement, it is apparent the damages have already been the subject of actual and fair calculation and adjustment.” In 1 Sedgwick on Damages (8th Ed.) sec. 396, it is said: “The subject-matter of the contract, and the intention of the parties are the controlling guides. If, from the nature of the agreement, it is clear that any attempt to get at the actual damage would be difficult, if not vain, then the courts will incline to give the relief which the parties have agreed on. But if, on the other hand the contract is such that the strict construction of the phraseology would work absurdity or oppression, the use of the term ‘liquidated damages’ will not prevent the courts from inquiring into the actual injury sustained, and doing justice between the parties. ’ ’

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lu-Mi-Nus Signs, Inc. v. Jefferson Shoe Stores, Inc.
257 Ill. App. 150 (Appellate Court of Illinois, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
181 Ill. App. 388, 1913 Ill. App. LEXIS 265, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ludlow-valve-manufacturing-co-v-city-of-chicago-illappct-1913.