Luckyland (N.Y.), LLC v. Core Continental Construction, LLC

83 A.D.3d 1073, 921 N.Y.S.2d 537
CourtAppellate Division of the Supreme Court of the State of New York
DecidedApril 26, 2011
StatusPublished
Cited by6 cases

This text of 83 A.D.3d 1073 (Luckyland (N.Y.), LLC v. Core Continental Construction, LLC) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Luckyland (N.Y.), LLC v. Core Continental Construction, LLC, 83 A.D.3d 1073, 921 N.Y.S.2d 537 (N.Y. Ct. App. 2011).

Opinion

In a proceeding pursuant to Lien Law § 19 (6) to summarily [1074]*1074discharge two mechanic’s liens, Core Continental Construction, LLC, appeals, as limited by its brief, from so much of an order of the Supreme Court, Kings County (Bayne, J.), dated October 22, 2010, as granted that branch of the petition which was to summarily discharge its mechanic’s lien.

Ordered that the order is reversed insofar as appealed from, on the law, with costs, and that branch of the petition which was to summarily discharge the appellant’s mechanic’s lien is denied.

A court has no inherent power to vacate or discharge a mechanic’s lien except as authorized under Lien Law § 19 (6) (see Matter of Gold Dev. & Mgt., LLC v P.J. Contr. Corp., 74 AD3d 1340, 1341 [2010]; Matter of Northside Tower Realty, LLC v Klin Constr. Group, Inc., 73 AD3d 1072 [2010]; Matter of Retek v City of New York, 14 AD3d 708, 709 [2005]). “Lien Law § 19 provides the grounds for the discharge of a mechanic’s lien for private improvement” (Coppola Gen. Contr. Corp. v Noble House Constr. of N.Y., 224 AD2d 856, 857 [1996]).

In this case, that branch of the petition which was to summarily discharge the appellant’s mechanic’s lien was based upon the assertions that, inter alia, the appellant, the general contractor for the subject construction project, did not fulfill its contractual obligations and complete the work because of a stop work order which resulted from its improper work and which it failed to remove. However, since the petitioner sought summary discharge pursuant to Lien Law § 19 (6), and the notice of lien was not invalid on its face, the lien was not subject to summary discharge. Accordingly, since there was no defect upon the face of the notice of lien, any dispute regarding the validity of the lien must await trial thereof by foreclosure (see Matter of Northside Tower Realty, LLC v Klin Constr. Group, Inc., 73 AD3d at 1072-1073; Matter of Lowe, 4 AD3d 476 [2004]; Dember Constr. Corp. v P & R Elec. Corp., 76 AD2d 540, 544 [1980]).

The petitioner’s remaining contentions are without merit.

Accordingly, the Supreme Court erred in directing summary discharge of the mechanic’s lien. Covello, J.P., Eng, Hall and Roman, JJ., concur.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Matter of Old Post Rd. Assoc., LLC v. LRC Constr., LLC
2019 NY Slip Op 7930 (Appellate Division of the Supreme Court of New York, 2019)
Robert K. Futterman & Associates, LLC v. Boerum Commercial, LLC
134 A.D.3d 690 (Appellate Division of the Supreme Court of New York, 2015)
Rivera v. Department of Hous. Preserv. & Dev. of City of New York
130 A.D.3d 802 (Appellate Division of the Supreme Court of New York, 2015)
Lane Construction Co. v. Chayat
117 A.D.3d 992 (Appellate Division of the Supreme Court of New York, 2014)
Construction for Commerce, Inc. v. 1325 48th St., LLC
90 A.D.3d 975 (Appellate Division of the Supreme Court of New York, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
83 A.D.3d 1073, 921 N.Y.S.2d 537, Counsel Stack Legal Research, https://law.counselstack.com/opinion/luckyland-ny-llc-v-core-continental-construction-llc-nyappdiv-2011.