Luckenbach Steamship Co. v. United States

64 Ct. Cl. 59, 1927 U.S. Ct. Cl. LEXIS 344, 1927 WL 2877
CourtUnited States Court of Claims
DecidedFebruary 14, 1927
DocketNo. C-934
StatusPublished
Cited by2 cases

This text of 64 Ct. Cl. 59 (Luckenbach Steamship Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Luckenbach Steamship Co. v. United States, 64 Ct. Cl. 59, 1927 U.S. Ct. Cl. LEXIS 344, 1927 WL 2877 (cc 1927).

Opinion

Booth, Judge,

delivered the opinion of the court:

This is one of a group of cases wherein the plaintiffs sue for just compensation for the expropriation of ship construction contracts. The cases were argued and submitted at the same time. The plaintiffs rests the right of recovery on the Brooks-Scanlon case, 265 U. S. 106. The claim is for an award of $23,093,448.65. The defendant, in addition to the defense raised in the Brooks-Scanlon case now before the court on remand, interposes herein a defense predicated upon a contention that under the facts in this case the plaintiffs’ contracts were not expropriated, and even so, they were without value.

The plaintiff steamship company is a Delaware corporation. Its shipping interests are large. On October 2, 1916, it entered into two written contracts with the Sun Shipbuilding Company, of Philadelphia, Pa., to construct for it two twin-screw steel cargo steamships identified as Numbers 5 and 6 of an estimated gross tonnage of ten thousand tons each, at a cost of $1,390,000 for each vessel. On February 20, 1917, the contracts were modified so as to cover changes made in the original design, and the costs of the two vessels increased, comprehending in the end a final outlay of $2,808,-554 for the vessels. Payments were to be made by the owner to the contractor in installments as the work on the vessels progressed. The vessels were to be completed on or before March 1,1918, and in the event of a default in this respect a liquidated damage clause imposed upon the contractor the payment of $1,000 for each day of delay, provided that in case the delay exceeded 10 days beyond the contract period the sum of $10,000 would be remitted from any demurrage claimed, and in the event of a performance of the contract prior to the completion date fixed therein, the contractor was.to receive a premium of $1,000 per day for each day the work was so advanced. The contract among other important provisions contained the following stipulations:

“Builder agrees to deliver said steamships complete and ready for ocean service to the Owner at Chester, Pennsyl[75]*75vania, on or before March first, 1918, unless actually prevented by strikes, fire, flood, war in, by, or with the United States of America, or commandeering thereby, or acts of God, or by delay or failure in delivery to Builder of Turbines or Boiler's complete. * * *
“ It is hereby convenanted and agreed that the vessels and all materials, fittings, etc., delivered, bought, or ordered for the said vessels, shall forthwith as the work progresses, become the sole property of the Owner, to extent of payments made, and subject to Builder’s Lien (common Jaw and statutory) for the unpaid purchase money, and also subject to the right of Builder as against the vessels, materials, fittings, etc., and not merely personally as against Owner, to full indemnification against any loss resulting from default by Owner in carrying out the conditions of its part of this contract.”

On December 21,1916, the plaintiffs again contracted with the Sun Shipbuilding Company to construct two additional vessels of substantially the same design and under similar contractual terms and conditions, identified as vessels Nos. 9 and 10. The contract price in this instance, including changes made, was $2,888,114 for the two vessels. Payments were to be made in installments, and the date of delivery was contingent upon the completion of prior contract work then in course of performance in the company’s plant.

On August 8, 1917, the Emergency Fleet Corporation transmitted to the Sun Shipbuilding Company the telegram set out in Finding IY. This was followed by the Fleet Corporation’s letter of the same date, as appears in the same finding. Subsequently the letter1 to Mr. G. R. McDermott, set out in Finding VII, reached the Shipbuilding Company, and thereafter ensued an extensive correspondence between the Shipbuilding Company and the Fleet Corporation. The Shipbuilding Company, disavowing reluctance to aid the Government in time of war, was exceedingly loathe to give its unqualified assent to the proceedings. It steadfastly insisted upon an express indemnification against liability to the owner of the contracts requisitioned and at no time yielded to the -propositions embraced in the orders of the Fleet Corporation as originally formulated. On the contrary, negotiations were carried on be[76]*76tween the company and the Fleet Corporation until a date when the Fleet Corporation directed the company to proceed with construction of the vessels and payments would be made in accord with the cost of materials, labor, and reasonable overhead. This the company did until finally, on November 12, 1918, a written agreement was executed by the parties, wherein the Fleet Corporation agreed to pay for the vessels cost plus $15 per dead-weight ton. As a result of the attitude of the Shipbuilding Company and the Fleet Corporation the four vessels covered by the contracts cost the Government $6,636,832.47 more than the original contract price. The vessels were completed in the following order: No. 5, March 7, 1919; No. 6, May 21, 1919; No. 9, July 18, 1919; and No. 10, July 7, 1919. Completion of the vessels on the dates mentioned was accomplished by the employment of overtime and holiday labor at an enhanced cost; No. 5 was completed as a cargo vessel in substantial accord with the original contract to build the same; Nos. 6, 9, and 10 were diverted from the original design to combined cargo and transport vessels.

On the date of requisition, August 3, 1917, the plaintiffs had paid to the Shipbuilding Company the comparatively small sum of $339,600, so that their title to and interest in assembled materials were not extensive. Nothing whatever so far as actual structural work was concerned had been done. Plans and specifications for construction work were in process and near completion. The keel of none of the vessels had been laid and the most that can be said for the conditions- obtaining is' that a comparatively insignificant quantity of material was on hand. Orders had been placed for’ more, but not a nail had been driven or material placed to bring into being the vessels contracted for. All that had been done was the usual and customary preliminaries to actual construction work. The Fleet Corporation, as before observed, succeeded in finishing the vessels a little over a year after the contract period by the employment of large forces of labor in daily, overtime, and holiday work, at a tremendously increased price over the one specified .in the contract.

[77]*77The defendant, in view of these facts, first insists that because of the unwillingness of the Shipbuilding Company to agree to the terms and conditions of the Fleet Corporation’s letter of August 22, 1917, an independent agreement arose between the parties as to the construction of the vessels, and the contract between the plaintiffs and the Shipbuilding Company was ignored. No advantage was taken of its existence; no benefit accrued to the Government because of its terms; and the plans and specifications of the owners were not followed in constructing the vessels. However, when compared with the facts in the Brooks-Scanlon case and the opinion of the Supreme Court in that case it is difficult to discover any variance sufficiently vital to take this case out of the principles announced in that case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Virginia Engineering Co. v. United States
89 Ct. Cl. 457 (Court of Claims, 1939)
Smith v. United States
67 Ct. Cl. 182 (Court of Claims, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
64 Ct. Cl. 59, 1927 U.S. Ct. Cl. LEXIS 344, 1927 WL 2877, Counsel Stack Legal Research, https://law.counselstack.com/opinion/luckenbach-steamship-co-v-united-states-cc-1927.