LUCIUS HILL & Another v. CONSERVATION COMMISSION OF FALMOUTH.

Massachusetts Appeals Court·Decided August 2, 2023·No. 22-P-0581·Unpublished

Opinion

NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).

COMMONWEALTH OF MASSACHUSETTS

APPEALS COURT

22-P-581

LUCIUS HILL & another 1

vs.

CONSERVATION COMMISSION OF FALMOUTH.

MEMORANDUM AND ORDER PURSUANT TO RULE 23.0

The plaintiffs, Lucius and Wendy Hill, appeal from the

judgment of a Superior Court judge upholding the decision of the

conservation commission of Falmouth (commission) denying an

application for an order of conditions for construction of a new

walkway leading to an existing dock in West Falmouth harbor. We

affirm.

In addition to the Wetlands Protection Act, G. L. c. 131,

§ 40 (WPA), the town of Falmouth regulates wetlands through a

local wetlands protection bylaw, chapter 235 of the town's code

(wetlands bylaw), and the commission's Falmouth wetland

regulations (FWR). The plaintiffs submitted a notice of intent

under the WPA, wetlands bylaw, and the FWR, seeking permission

1 Wendy Hill.

to construct an elevated walkway to reach their existing licensed concrete ramp and float. 2 Section 10.16 (h) of the FWR provides "general requirements" and "prohibitions" applicable to all docks and piers. Section 10.16 (h) (1) provides that:

"No new docks or piers or extension of an existing dock or pier may be constructed in any portion of [a] FEMA designated velocity zone (V-Zone) unless the applicant demonstrates that there will be public benefit from the project. The Commission shall weigh the potential likelihood of damage and harm that any such dock or pier would cause during a storm event with the public benefit demonstrated by the applicant in determining whether the project should be allowed."

While the record does not reveal a specific finding, the commission and the parties have all treated the location of the proposed walkway as being in a velocity zone, and the plaintiffs do not suggest otherwise on appeal.

After providing proper notice, the commission conducted a public hearing over several days. At one of the first hearing dates, some of the members inquired about revegetating the existing walking path after the elevated walkway is installed. The plaintiffs responded with a letter from a landscape design company recommending the planting of 200 salt marsh plugs to facilitate restoration. At the next hearing, the plaintiffs' representative informed the commission that the plaintiffs would

2 According to the commission's meeting minutes, currently there is a grass path leading to a solid stone and concrete dock, which is surrounded by knee-high water at times.

install salt marsh material as recommended by the landscape design company. Before the commission voted, it was noted that the plan proposed an expansion of a dock in a velocity zone and that planting plugs was recommended to enhance the salt marsh after construction of the walkway. Indeed, one of the members of the commission noted prior to the vote that "[i]t will be a better environment because the salt marsh will fill in. It's better for Falmouth to have the project than not to have it." Another member commented, however, that "[t]here is value of the salt marsh and the value of the velocity zone. The structure should be prohibited because of the damage that will be done when the structure is ripped out in a storm and does harm to the resources."

On February 24, 2021, a motion was made to grant the order of conditions. The commission voted, but the vote failed to carry a majority of the commission, and therefore, the application was considered denied. On February 26, 2021, the commission issued a written decision signed by a majority explaining its reasons for denying the application. The decision set forth the commission's finding that the proposed walkway is an "extension" of the existing dock and explained that no extension of a dock is allowed in the velocity zone unless the applicant demonstrates a public benefit, and the

plaintiffs did not demonstrate how there will be a public benefit from the proposed project.

The plaintiffs filed a certiorari appeal pursuant to G. L.

c. 249, § 4, in the Superior Court. On cross motions for judgment on the pleadings, the judge granted the commission's motion, affirming the commission's decision and dismissing the appeal. This appeal followed.

Discussion. "In a review under certiorari, the court is limited to correcting 'substantial errors of law apparent on the record adversely affecting material rights'" (citation omitted). FIC Homes of Blackstone, Inc. v. Conservation Comm'n of Blackstone, 41 Mass. App. Ct. 681, 684 (1996). We review a decision allowing a motion for judgment on the pleadings de novo. Delapa v. Conservation Comm'n of Falmouth, 93 Mass. App. Ct. 729, 733 (2018). "In an action in the nature of certiorari challenging a wetlands permit decision made by a conservation commission pursuant to a local by-law, our review is limited at most to whether the commission's decision is supported by substantial evidence in the administrative record, whether the commission's action was arbitrary and capricious, and whether the commission committed an abuse of discretion or other error of law." Id. at 733-734. With these principles in mind, we address the plaintiffs' arguments.

1. Sufficiency of the vote. The plaintiffs first argue that when the commission's vote to grant the order of conditions did not pass, the commission erred in treating it as a vote to deny the order of conditions, and that the proper procedure would have been to conduct a second vote specifically on the question whether to deny the order of conditions. They point to several sections of the wetlands bylaw and the FWR, none of which require two votes in the circumstances presented. Cf. McElderry v. Planning Bd. of Nantucket, 431 Mass. 722, 722, 727 (2000) (in absence of affirmative vote by majority of quorum, plan disapproved).

First, the plaintiffs point to § 10.05 (9) (b) of the FWR, which discusses "substantive denials" and provides that the commission "may deny permission for any activity within areas under its jurisdiction if, in its judgment, such denial is necessary to protect the Resource area values identified in the Bylaw." It further provides that "[t]he written decision will include the reasons for the denial, citing Resource area values protected, and relevant regulations. The written decision will be signed by a majority of the Commission." Contrary to the plaintiffs' contention, all of these requirements were met, as reflected in the written decision.

In addition, the plaintiffs point to § 235-7 (B) of the wetlands bylaw, which requires that in denying a request for a

permit, "[d]ue consideration shall be given to any demonstrated hardship on the applicant by reason of denial, as presented at the public hearing," and argue that because there was no second vote, the commission did not consider any "hardship" that the plaintiffs would suffer if their application were denied. The FWR defines "hardship" specifically:

Free access — add to your briefcase to read the full text and ask questions with AI

LUCIUS HILL & Another v. CONSERVATION COMMISSION OF FALMOUTH., (Mass. Ct. App. 2023).

LUCIUS HILL & Another v. CONSERVATION COMMISSION OF FALMOUTH. (LUCIUS HILL & Another v. CONSERVATION COMMISSION OF FALMOUTH.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

McElderry v. Planning Board
431 Mass. 722 (Massachusetts Supreme Judicial Court, 2000)
Oyster Creek Preservation, Inc. v. Conservation Commission
449 Mass. 859 (Massachusetts Supreme Judicial Court, 2007)
Croteau v. Planning Board
663 N.E.2d 583 (Massachusetts Appeals Court, 1996)
FIC Homes of Blackstone, Inc. v. Conservation Commission
673 N.E.2d 61 (Massachusetts Appeals Court, 1996)
Chace v. Curran
881 N.E.2d 792 (Massachusetts Appeals Court, 2008)
Wine v. Planning Board
908 N.E.2d 806 (Massachusetts Appeals Court, 2009)
Delapa v. Conservation Comm'n of Falmouth
108 N.E.3d 474 (Massachusetts Appeals Court, 2018)