Lucien v. McCormick Construction, LLC

998 A.2d 250, 122 Conn. App. 295, 2010 Conn. App. LEXIS 295
CourtConnecticut Appellate Court
DecidedJuly 6, 2010
DocketAC 30800
StatusPublished
Cited by6 cases

This text of 998 A.2d 250 (Lucien v. McCormick Construction, LLC) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lucien v. McCormick Construction, LLC, 998 A.2d 250, 122 Conn. App. 295, 2010 Conn. App. LEXIS 295 (Colo. Ct. App. 2010).

Opinion

Opinion

DiPENTIMA, J.

The plaintiff, Seniel Lucien, appeals from the judgment of the trial court denying her application to discharge the mechanic’s lien filed by the defendant, McCormick Construction, LLC. On appeal, the plaintiff claims that the court improperly concluded that the defendant satisfied its burden of establishing that the plaintiff asserted violations of the Home Improvement Act (act), General Statutes § 20-418 et seq., in bad faith. We reverse the judgment of the trial court.

The parties stipulated to the following facts. In late 2005, the parties commenced negotiations on a contract for the defendant to renovate a residence in Chester that the plaintiff later purchased. On December 13,2005, the defendant sent a proposed contract to the plaintiffs representative, Arlene Boop, an attorney based in New York. The two sides negotiated the terms of the contract, and, on March 20, 2006, the defendant sent Boop a copy of the contract and other related documents, including a “ ‘notice of cancellation.’ ” The plaintiff, however, never signed the contract or any document acknowledging receipt of the notice of cancellation.

The defendant began work on the plaintiffs residence in early May, 2006. From May, 2006, through May, 2007, the defendant sent invoices totaling $323,917.99 to the plaintiff. Of this total, $207,453 represented the original contract price, and the $116,464.99 balance was the *297 result of change orders. The plaintiff has paid the defendant a total of $211,781.28, and the defendant claims that the plaintiff owes it a balance of $82,698.36.

From at least March, 2007, the plaintiff has communicated to the defendant that she disputes the amount the defendant claims that she owes, the change orders and whether the contract was properly or fully performed by the defendant. Additionally, the plaintiff has maintained that the defendant was responsible for delays in performance under the contract, though the defendant contends that the plaintiff was to blame for any delays.

On or about May 16, 2008, the defendant filed a mechanic’s lien with the town of Chester claiming a lien in the principal amount of $99,824.85 against the plaintiffs residence. 1 On or about September 10, 2008, the plaintiff made an application to the Superior Court, pursuant to General Statutes § 49-35a, 2 alleging that there was not probable cause to sustain the validity of the lien and seeking an order for the discharge of the lien pursuant to General Statutes § 49-35b. 3 In seeking *298 to discharge the mechanic’s hen, the plaintiff alleged that the construction contract failed to comply with the act. The court held a hearing regarding the application on September 29, 2008, and issued its memorandum of decision on February 5, 2009.

In its memorandum, the court noted that, based on the stipulated facts, it was unquestionable that the contract violated the act because it was not signed in violation of General Statutes § 20-429 (a) (2), a notice of cancellation was not attached to the contract in violation of General Statutes § 42-135a (2) and the contract failed to provide notice of the homeowner’s right to cancellation in violation of § 42-135a (1). Thus, the dis-positive issue was “whether noncompliance with the act is excused because [the] plaintiff has asserted this defense in bad faith.” After reviewing the facts, the court concluded that “under these circumstances, the defendant has satisfied [its] burden of proving that the plaintiff has acted in bad faith in asserting . . . violations [of the act]. While it is true that [the] plaintiff did make substantial payments on the contract, it is notable that she did not dispute any moneys owed, or the defendant’s performance, until shortly before the final balance was rendered in May, 2007. There is no record evidence to suggest that from the commencement of the construction process in March, 2006, until March, 2007, she registered any complaints about the invoice amounts, delays in performance or the quality of [the] defendant’s work. Further, it is undisputed that although the contract failed to comply with the [act] *299 in a number of material respects, no mention of noncompliance was raised until almost eighteen months after work on the project commenced. [The] [p]laintiff correctly points out that it would be unusual for a party to a contract to recognize whether it complies with the [act], and therefore the late assertion of that defense should not be the basis of a finding of bad faith. Typically, [the] plaintiffs argument would be persuasive. In this case, however, [the] plaintiff was represented throughout the negotiation process by counsel. If defects in the contract were an issue, they could have, and should have, been timely raised. The assertion of this defense, at the eleventh hour, to defeat a significant claim of nonpayment is not consistent with good faith obligations imposed on both parties to a contract.” The court denied the plaintiffs application to discharge the mechanic’s lien, and this appeal followed.

On appeal, the plaintiff claims that the defendant failed to satisfy its burden of establishing that she asserted violations of the act in bad faith. Specifically, she argues that the bases supporting the court’s finding of bad faith—her failure to raise the violations of the act until after the completion of the project and that she was represented by counsel during negotiations— are not, without more, evidence of bad faith. We agree.

Prior to evaluating the plaintiffs claim, we must first articulate the relevant standard of review. “Because the parties have stipulated to the relevant facts, our review is plenary and we must determine whether the trial court’s conclusions of law are legally and logically correct and find support in the stipulated facts.” (Internal quotation marks omitted.) Ace Equipment Sales, Inc. v. H.O. Penn Machinery Co., 88 Conn. App. 687, 690, 871 A.2d 402, cert. denied, 274 Conn. 909, 876 A.2d 1200 (2005).

“The principles governing the . . . claim of bad faith are well established. In Barrett Builders v. Miller, [215 *300 Conn. 316, 328, 576 A.2d 455 (1990)], our Supreme Court stated, in dictum, that a homeowner could not avail himself of the protection afforded to him by § 20-429 if he invoked the statute in bad faith. Our Supreme Court subsequently applied the bad faith exception in Habetz v. Condon, 224 Conn. 231, 618 A.2d 501 (1992), in which it upheld a trial court’s factual finding of bad faith. The central element giving rise to this exception is the recognition that to allow the homeowner who acted in bad faith to repudiate the contract and hide behind the act would be to allow him to benefit from his own wrong, and indeed encourage him to act thusly.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Burns v. Adler
Supreme Court of Connecticut, 2017
Burns v. Adler
Connecticut Appellate Court, 2015
Shipman v. Roberts
23 A.3d 764 (Connecticut Appellate Court, 2011)
Walpole Woodworkers, Inc. v. Manning
11 A.3d 165 (Connecticut Appellate Court, 2011)
ANDY'S OIL SERVICE, INC. v. Hobbs
9 A.3d 433 (Connecticut Appellate Court, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
998 A.2d 250, 122 Conn. App. 295, 2010 Conn. App. LEXIS 295, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lucien-v-mccormick-construction-llc-connappct-2010.