Opinion
DiPENTIMA, J.
The plaintiff, Seniel Lucien, appeals from the judgment of the trial court denying her application to discharge the mechanic’s lien filed by the defendant, McCormick Construction, LLC. On appeal, the plaintiff claims that the court improperly concluded that the defendant satisfied its burden of establishing that the plaintiff asserted violations of the Home Improvement Act (act), General Statutes § 20-418 et seq., in bad faith. We reverse the judgment of the trial court.
The parties stipulated to the following facts. In late 2005, the parties commenced negotiations on a contract for the defendant to renovate a residence in Chester that the plaintiff later purchased. On December 13,2005, the defendant sent a proposed contract to the plaintiffs representative, Arlene Boop, an attorney based in New York. The two sides negotiated the terms of the contract, and, on March 20, 2006, the defendant sent Boop a copy of the contract and other related documents, including a “ ‘notice of cancellation.’ ” The plaintiff, however, never signed the contract or any document acknowledging receipt of the notice of cancellation.
The defendant began work on the plaintiffs residence in early May, 2006. From May, 2006, through May, 2007, the defendant sent invoices totaling $323,917.99 to the plaintiff. Of this total, $207,453 represented the original contract price, and the $116,464.99 balance was the
result of change orders. The plaintiff has paid the defendant a total of $211,781.28, and the defendant claims that the plaintiff owes it a balance of $82,698.36.
From at least March, 2007, the plaintiff has communicated to the defendant that she disputes the amount the defendant claims that she owes, the change orders and whether the contract was properly or fully performed by the defendant. Additionally, the plaintiff has maintained that the defendant was responsible for delays in performance under the contract, though the defendant contends that the plaintiff was to blame for any delays.
On or about May 16, 2008, the defendant filed a mechanic’s lien with the town of Chester claiming a lien in the principal amount of $99,824.85 against the plaintiffs residence.
On or about September 10, 2008, the plaintiff made an application to the Superior Court, pursuant to General Statutes § 49-35a,
alleging that there was not probable cause to sustain the validity of the lien and seeking an order for the discharge of the lien pursuant to General Statutes § 49-35b.
In seeking
to discharge the mechanic’s hen, the plaintiff alleged that the construction contract failed to comply with the act. The court held a hearing regarding the application on September 29, 2008, and issued its memorandum of decision on February 5, 2009.
In its memorandum, the court noted that, based on the stipulated facts, it was unquestionable that the contract violated the act because it was not signed in violation of General Statutes § 20-429 (a) (2), a notice of cancellation was not attached to the contract in violation of General Statutes § 42-135a (2) and the contract failed to provide notice of the homeowner’s right to cancellation in violation of § 42-135a (1). Thus, the dis-positive issue was “whether noncompliance with the act is excused because [the] plaintiff has asserted this defense in bad faith.” After reviewing the facts, the court concluded that “under these circumstances, the defendant has satisfied [its] burden of proving that the plaintiff has acted in bad faith in asserting . . . violations [of the act]. While it is true that [the] plaintiff did make substantial payments on the contract, it is notable that she did not dispute any moneys owed, or the defendant’s performance, until shortly before the final balance was rendered in May, 2007. There is no record evidence to suggest that from the commencement of the construction process in March, 2006, until March, 2007, she registered any complaints about the invoice amounts, delays in performance or the quality of [the] defendant’s work. Further, it is undisputed that although the contract failed to comply with the [act]
in a number of material respects, no mention of noncompliance was raised until almost eighteen months after work on the project commenced. [The] [p]laintiff correctly points out that it would be unusual for a party to a contract to recognize whether it complies with the [act], and therefore the late assertion of that defense should not be the basis of a finding of bad faith. Typically, [the] plaintiffs argument would be persuasive. In this case, however, [the] plaintiff was represented throughout the negotiation process by counsel. If defects in the contract were an issue, they could have, and should have, been timely raised. The assertion of this defense, at the eleventh hour, to defeat a significant claim of nonpayment is not consistent with good faith obligations imposed on both parties to a contract.” The court denied the plaintiffs application to discharge the mechanic’s lien, and this appeal followed.
On appeal, the plaintiff claims that the defendant failed to satisfy its burden of establishing that she asserted violations of the act in bad faith. Specifically, she argues that the bases supporting the court’s finding of bad faith—her failure to raise the violations of the act until after the completion of the project and that she was represented by counsel during negotiations— are not, without more, evidence of bad faith. We agree.
Prior to evaluating the plaintiffs claim, we must first articulate the relevant standard of review. “Because the parties have stipulated to the relevant facts, our review is plenary and we must determine whether the trial court’s conclusions of law are legally and logically correct and find support in the stipulated facts.” (Internal quotation marks omitted.)
Ace Equipment Sales, Inc.
v.
H.O. Penn Machinery Co.,
88 Conn. App. 687, 690, 871 A.2d 402, cert. denied, 274 Conn. 909, 876 A.2d 1200 (2005).
“The principles governing the . . . claim of bad faith are well established. In
Barrett Builders
v.
Miller,
[215
Conn. 316, 328, 576 A.2d 455 (1990)], our Supreme Court stated, in dictum, that a homeowner could not avail himself of the protection afforded to him by § 20-429 if he invoked the statute in bad faith. Our Supreme Court subsequently applied the bad faith exception in
Habetz
v.
Condon,
224 Conn. 231, 618 A.2d 501 (1992), in which it upheld a trial court’s factual finding of bad faith. The central element giving rise to this exception is the recognition that to allow the homeowner who acted in bad faith to repudiate the contract and hide behind the act would be to allow him to benefit from his own wrong, and indeed encourage him to act thusly.
Free access — add to your briefcase to read the full text and ask questions with AI
Opinion
DiPENTIMA, J.
The plaintiff, Seniel Lucien, appeals from the judgment of the trial court denying her application to discharge the mechanic’s lien filed by the defendant, McCormick Construction, LLC. On appeal, the plaintiff claims that the court improperly concluded that the defendant satisfied its burden of establishing that the plaintiff asserted violations of the Home Improvement Act (act), General Statutes § 20-418 et seq., in bad faith. We reverse the judgment of the trial court.
The parties stipulated to the following facts. In late 2005, the parties commenced negotiations on a contract for the defendant to renovate a residence in Chester that the plaintiff later purchased. On December 13,2005, the defendant sent a proposed contract to the plaintiffs representative, Arlene Boop, an attorney based in New York. The two sides negotiated the terms of the contract, and, on March 20, 2006, the defendant sent Boop a copy of the contract and other related documents, including a “ ‘notice of cancellation.’ ” The plaintiff, however, never signed the contract or any document acknowledging receipt of the notice of cancellation.
The defendant began work on the plaintiffs residence in early May, 2006. From May, 2006, through May, 2007, the defendant sent invoices totaling $323,917.99 to the plaintiff. Of this total, $207,453 represented the original contract price, and the $116,464.99 balance was the
result of change orders. The plaintiff has paid the defendant a total of $211,781.28, and the defendant claims that the plaintiff owes it a balance of $82,698.36.
From at least March, 2007, the plaintiff has communicated to the defendant that she disputes the amount the defendant claims that she owes, the change orders and whether the contract was properly or fully performed by the defendant. Additionally, the plaintiff has maintained that the defendant was responsible for delays in performance under the contract, though the defendant contends that the plaintiff was to blame for any delays.
On or about May 16, 2008, the defendant filed a mechanic’s lien with the town of Chester claiming a lien in the principal amount of $99,824.85 against the plaintiffs residence.
On or about September 10, 2008, the plaintiff made an application to the Superior Court, pursuant to General Statutes § 49-35a,
alleging that there was not probable cause to sustain the validity of the lien and seeking an order for the discharge of the lien pursuant to General Statutes § 49-35b.
In seeking
to discharge the mechanic’s hen, the plaintiff alleged that the construction contract failed to comply with the act. The court held a hearing regarding the application on September 29, 2008, and issued its memorandum of decision on February 5, 2009.
In its memorandum, the court noted that, based on the stipulated facts, it was unquestionable that the contract violated the act because it was not signed in violation of General Statutes § 20-429 (a) (2), a notice of cancellation was not attached to the contract in violation of General Statutes § 42-135a (2) and the contract failed to provide notice of the homeowner’s right to cancellation in violation of § 42-135a (1). Thus, the dis-positive issue was “whether noncompliance with the act is excused because [the] plaintiff has asserted this defense in bad faith.” After reviewing the facts, the court concluded that “under these circumstances, the defendant has satisfied [its] burden of proving that the plaintiff has acted in bad faith in asserting . . . violations [of the act]. While it is true that [the] plaintiff did make substantial payments on the contract, it is notable that she did not dispute any moneys owed, or the defendant’s performance, until shortly before the final balance was rendered in May, 2007. There is no record evidence to suggest that from the commencement of the construction process in March, 2006, until March, 2007, she registered any complaints about the invoice amounts, delays in performance or the quality of [the] defendant’s work. Further, it is undisputed that although the contract failed to comply with the [act]
in a number of material respects, no mention of noncompliance was raised until almost eighteen months after work on the project commenced. [The] [p]laintiff correctly points out that it would be unusual for a party to a contract to recognize whether it complies with the [act], and therefore the late assertion of that defense should not be the basis of a finding of bad faith. Typically, [the] plaintiffs argument would be persuasive. In this case, however, [the] plaintiff was represented throughout the negotiation process by counsel. If defects in the contract were an issue, they could have, and should have, been timely raised. The assertion of this defense, at the eleventh hour, to defeat a significant claim of nonpayment is not consistent with good faith obligations imposed on both parties to a contract.” The court denied the plaintiffs application to discharge the mechanic’s lien, and this appeal followed.
On appeal, the plaintiff claims that the defendant failed to satisfy its burden of establishing that she asserted violations of the act in bad faith. Specifically, she argues that the bases supporting the court’s finding of bad faith—her failure to raise the violations of the act until after the completion of the project and that she was represented by counsel during negotiations— are not, without more, evidence of bad faith. We agree.
Prior to evaluating the plaintiffs claim, we must first articulate the relevant standard of review. “Because the parties have stipulated to the relevant facts, our review is plenary and we must determine whether the trial court’s conclusions of law are legally and logically correct and find support in the stipulated facts.” (Internal quotation marks omitted.)
Ace Equipment Sales, Inc.
v.
H.O. Penn Machinery Co.,
88 Conn. App. 687, 690, 871 A.2d 402, cert. denied, 274 Conn. 909, 876 A.2d 1200 (2005).
“The principles governing the . . . claim of bad faith are well established. In
Barrett Builders
v.
Miller,
[215
Conn. 316, 328, 576 A.2d 455 (1990)], our Supreme Court stated, in dictum, that a homeowner could not avail himself of the protection afforded to him by § 20-429 if he invoked the statute in bad faith. Our Supreme Court subsequently applied the bad faith exception in
Habetz
v.
Condon,
224 Conn. 231, 618 A.2d 501 (1992), in which it upheld a trial court’s factual finding of bad faith. The central element giving rise to this exception is the recognition that to allow the homeowner who acted in bad faith to repudiate the contract and hide behind the act would be to allow him to benefit from his own wrong, and indeed encourage him to act thusly. Proof of bad faith therefore serves to preclude the homeowner from hiding behind the protection of the act. . . .
Habetz
made it clear, however, that mere disagreement about contract performance does not suffice to establish bad faith.
Habetz
defined bad faith as involving actual or constructive fraud, or a design to mislead or deceive another, or a neglect or refusal to fulfill some duty or some contractual obligation, not prompted by an honest mistake as to one’s rights or duties, but by some interested or sinister motive. . . . Bad faith means more than mere negligence; it involves a dishonest purpose.” (Citation omitted; internal quotation marks omitted.)
New England Custom Concrete, LLC
v.
Carbone,
102 Conn. App. 652, 660-61, 927 A.2d 333 (2007). “It is the burden of the party asserting the lack of good faith to establish its existence and whether that burden has been satisfied in a particular case is a question of fact.”
Habetz
v.
Condon,
supra, 237 n.11.
As it was the defendant that alleged bad faith on the part of the plaintiff, it had the burden of establishing its existence. The court concluded that the defendant had met its burden, reasoning that the plaintiffs representation by counsel throughout the negotiation process and her failure to raise the noncompliance with the act until the defendant raised a claim of nonpayment established bad faith. Our Supreme Court, however, has held that neither of the grounds the court relied on in reaching its conclusion that the defendant had established bad faith on the part of the plaintiff, without additional evidence, rises to the level of bad faith.
In
Wadia Enterprises, Inc.
v.
Hirschfeld,
224 Conn. 240, 618 A.2d 506 (1992), our Supreme Court considered a similar claim of bad faith on the part of the defendant homeowners in an action brought by the plaintiff to foreclose a mechanic’s lien. As evidence of bad faith, the plaintiff noted that the defendants “prepared the underlying defective contract through their New York attorneys and architect and then relied on the same contract as a defense to its enforcement . . . .’’Id., 248. In rejecting the allegation of bad faith, the court noted that “[t]he fact that the defendants had their architect and New York attorneys draft the contract
does not in and of itself indicate bad faith on the part of the defendants. There is no allegation or proof that the attorneys intentionally omitted [the] requirement [that the contract contain notice of the right of cancellation] in order to have an escape hatch. At most, the New York attorneys were negligent in failing to consult Connecticut law and to include the required clause in the contract. An honest mistake does not rise to the level of bad faith.” Id., 248-49. Similarly, in this case there is nothing in the stipulated facts that supports the conclusion that the plaintiff or Boop acted with bad faith in failing to ensure that the contract in this case complied with the act.
In the absence of such proof, we cannot conclude that the plaintiff acted in bad faith on this basis.
The court also concluded that the plaintiff acted in bad faith on the basis that she waited until “the eleventh hour” to raise the violations of the act, which the court viewed as “[inconsistent] with good faith obligations imposed on both parties to a contract.” “[initially enforcing the contract and subsequently asserting the contract’s invalidity . . . does not, by itself, present a claim of bad faith. There is nothing dishonest or sinister about homeowners proceeding on the assumption that there is a valid contract, enforcing its provisions, and later . . . upon learning that the contract is invalid, then exercising their right to repudiate it.”
Wadia Enterprises, Inc.
v.
Hirschfeld,
supra, 224 Conn. 249. The facts stipulated to by the parties do not state that the plaintiff knew of the violation earlier, or that she purposely drafted the contract in violation of the act in order to later avoid her obligation to pay. There simply
is nothing in the stipulated facts that can legally and logically support the court’s conclusion that the plaintiff acted with a dishonest purpose in claiming that the defendant violated the act.
We therefore conclude that the court improperly denied the plaintiffs application to discharge the mechanic’s lien.
The judgment is reversed and the case is remanded with direction to grant the plaintiffs application to discharge the defendant’s mechanic’s lien.
In this opinion the other judges concurred.