LTL Acres Limited Partnership v. Butler Manufacturing Co.

136 A.3d 682, 89 U.C.C. Rep. Serv. 2d (West) 424, 2016 WL 1408148, 2016 Del. LEXIS 233
CourtSupreme Court of Delaware
DecidedApril 11, 2016
Docket468, 2015
StatusPublished
Cited by4 cases

This text of 136 A.3d 682 (LTL Acres Limited Partnership v. Butler Manufacturing Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
LTL Acres Limited Partnership v. Butler Manufacturing Co., 136 A.3d 682, 89 U.C.C. Rep. Serv. 2d (West) 424, 2016 WL 1408148, 2016 Del. LEXIS 233 (Del. 2016).

Opinion

VAUGHN, Justice:

I. INTRODUCTION

This litigation arises from the construction of a Johnny Janosik furniture store (the “Janosik Building”) in Laurel, Delaware. The Plaintiff-Below/Appellant LTL Acres Limited Partnership (“LTL”) is the owner of the Janosik Building. Defendant-Below/Appellee Butler Manufacturing Company (“Butler”) provided pre-engi-neered components which were used to build the roof and exterior walls. Defendant-Below/Appellee Dryvit Systems, Inc. (“Dryvit”) supplied a product used to protect and seal the Butler walls from the exterior environment. In other words, the Dryvit product was used for the exterior finish. The building was completed in 2006. LTL initiated this action in the *684 Superior Court on July 17, 2013. It alleged breach of warranty, breach of contract, and negligence claims against Butler; (and breach of warranty and breach of contract claims against Dryvit.

The Superior Court granted summary judgment to both Butler and Dryvit on the grounds that the actions against both were barred by the applicable statute of limitations. It held that the action against Butler was barred by 10 Del. C. § 8127, which is a six year statute of limitations relating to alleged defective construction of an improvement to real property. As discussed below, we have concluded that summary judgment in favor of Butler should be affirmed for the reasons assigned by the Superior Court in its order dated July 30, 2015.

The Superior Court ruled that LTL’s action against Dryvit was barred by the four year statute of limitations set forth in 6 Del. C. § 2-725. That statute provides, in part, that a “breach of warranty occurs when tender of delivery is made, except that where a warranty explicitly extends to future performance of the goods and discovery of the breach must await the time of such performance the cause of action accrues when the breach is or should have been discovered.” 1 Dryvit gave LTL a ten year express warranty. The Superior Court described the warranty as a “repair and replacement warranty” and reasoned that such a warranty cannot be one that extends to future performance. It therefore concluded that the statute of limitations for an action on the warranty expired not later than four years after the Dryvit product was tendered and applied to the building; that is, not later than four years after 2006.

For the reasons which follow, we have concluded that the Dryvit warranty was one explicitly extending to future performance under which discovery of the breach must await the time of such performance. LTL’s action accrued, therefore, when the breach was or should have been discovered, not when the product was tendered. Since the Superior Court found that any alleged breach of the Dryvit warranty occurred when the product was tendered, it made no factual findings as to when the breach was or should have been discovered. Therefore, the grant of summary judgment in favor of Dryvit must be reversed and the case remanded for further proceedings.

II. FACTS AND PROCEDURAL HISTORY

A. Facts

In 2004, LTL hired the Whayland Company, Inc. (“Whayland”) as construction manager for the Janosik Building project. Whayland, an authorized purchaser and installer of Butler building systems, requested that Butler generate a quote for the Janosik Building, which needed to be two stories tall and approximately 180,000 square feet. Because Butler’s building systems were custom tailored to the client’s specific needs and location, Whay-land also provided Butler with the architectural and design plans.

Butler provided a quote, which was accepted on September 20, 2004, and the building components were delivered between March and August 2005. Whayland hired Merit Builders to erect the Butler building system.

Once the building was erected, Advanced Wall Systems was hired to apply an exterior insulation and finish system (“EIFS”), which entailed coating the building’s exterior with a plastic, stucco-looking *685 cladding manufactured by Dryvit. The Dryvit cladding came with a ten year limited warranty which, in pertinent part, stated:

DRYVIT ... hereby warrants for a period of ten (10) years from the date of substantial completion of the project that the Exterior Insulation and, Finish System materials manufacture and sold by Dryvit, including the insulation board, adhesive, basecoat, mesh and finish shall be free from defects in the manufacture of the materials and will not, as a result of such defects, when installed in accordance with the current published Dryvit Specifications, within said period of 10 years, under normal weather conditions and excluding unusual air pollution, lose their bond, peel, flake or chip, and further that the finish will be fade resistant, except for specially produced colors, and will be water resistant so long as the surface integrity is retained....
The sole responsibility and liability of Dryvit under this warranty shall be to provide labor and materials necessary to repair or replace the Dryvit materials described herein shown to be defective during the warranty period, and only for the materials warranted hereunder. 2

The Janosik Building was completed in September 2006, and the retail store opened in late October 2006. Unfortunately, the building had issues with water infiltration from the beginning. By February 2012, the EIFS cladding began to crack and buckle. The water infiltration and delamination persisted through 2013 despite attempts to remedy the issues.

B. Procedural History

As mentioned, LTL filed suit against Butler and Dryvit on July 17, 2013. After conducting discovery, Butler and Dryvit filed motions for summary judgment in early September 2014. Butler argued that LTL’s claims were barred under the six year statute of limitations set forth in 10 Del. C. § 8127. 3 Dryvit argued that LTL’s claims were barred under the four year statute of limitations set forth in 6 Del. C. § 2-725, 4 which it contended began to run at the time the materials were delivered. 5

LTL filed a joint response in March 2015. LTL argued that § 8127 was inapplicable because Butler did not “furnish construction” of the Janosik Building but merely supplied the building materials. Alternatively, LTL argued Butler should be equitably estopped from relying on the six year statute of limitations. As to Dry-vit, LTL argued that the Dryvit warranty was one of future performance, and thus, LTL’s warranty claim did not accrue until the breach was, or should have been, discovered. 6 Dryvit and Butler filed replies on March 26, 2015.

*686 On July 30, 2015, the Superior Court issued a letter opinion granting both motions for summary judgment.

Related

Cite This Page — Counsel Stack

Bluebook (online)
136 A.3d 682, 89 U.C.C. Rep. Serv. 2d (West) 424, 2016 WL 1408148, 2016 Del. LEXIS 233, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ltl-acres-limited-partnership-v-butler-manufacturing-co-del-2016.