Lozoya Construction, Inc. v. H&E Equipment Services, Inc.

CourtCourt of Appeals of Texas
DecidedMarch 26, 2020
Docket11-19-00287-CV
StatusPublished

This text of Lozoya Construction, Inc. v. H&E Equipment Services, Inc. (Lozoya Construction, Inc. v. H&E Equipment Services, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lozoya Construction, Inc. v. H&E Equipment Services, Inc., (Tex. Ct. App. 2020).

Opinion

Opinion filed March 26, 2020

In The

Eleventh Court of Appeals __________

No. 11-19-00287-CV __________

LOZOYA CONSTRUCTION, INC., Appellant V. H&E EQUIPMENT SERVICES, INC., Appellee

On Appeal from the 441st District Court Midland County, Texas Trial Court Cause No. CV55629

MEMORANDUM OPINION Pursuant to a written contract, Lozoya Construction, Inc. agreed to perform certain work at H&E Equipment Services, Inc.’s facility in Midland. H&E was dissatisfied with the work and sued Lozoya for breach of contract, breach of implied warranty of good and workmanlike manner, negligence, negligent misrepresentation, and fraud.1 Lozoya moved to dismiss these claims pursuant to

1 H&E also asserted claims against Lozoya for suit on a sworn account, breach of contract, and quantum meruit based on Lozoya’s failure to pay the rental charges for certain equipment. Lozoya did not move to dismiss those claims. the Texas Citizens Participation Act, TEX. CIV. PRAC. & REM. CODE ANN. §§ 27.001–.011 (West 2015) (the TCPA).2 The trial court denied Lozoya’s motion to dismiss, determined that the motion was frivolous and intended to delay, and awarded H&E attorney’s fees. In eight issues, Lozoya contends that the trial court erred when it considered the factual allegations in H&E’s response and conclusory allegations in H&E’s response and pleadings as evidence, determined that the TCPA did not apply to H&E’s claims and that H&E established by clear and specific evidence a prima facie case for each essential element of its claims, found that the commercial speech exemption in the statute applies to H&E’s claims, awarded H&E attorney’s fees, and failed to award Lozoya attorney’s fees and sanctions. We hold that the trial court did not err when it (1) denied the motion to dismiss based on the commercial speech exemption and (2) found that H&E was entitled to recover the attorney’s fees that it incurred to respond to the motion. Because the evidence is insufficient to support the amount of attorney’s fees awarded by the trial court, we reverse the trial court’s award of attorney’s fees in the amount of $9,360 and remand the issue of the amount of attorney’s fees to be awarded to H&E to the trial court for further proceedings. We affirm the trial court’s order in all other respects. Background Pursuant to a written contract, Lozoya agreed to perform site work and concrete installation at H&E’s facility in Midland. Among other work, Lozoya was required to install an 8,250 square foot concrete slab and approximately 28,196

2 The Texas legislature amended the TCPA effective September 1, 2019. See Act of May 17, 2019, 86th Leg., R.S., ch. 378, §§ 1–9, 12 (H.B. 2730) (codified at TEX. CIV. PRAC. & REM. CODE ANN. §§ 27.001, .003, .005–.007, .0075, .009–.010 (West Supp. 2019)). Because the underlying lawsuit was filed prior to September 1, 2019, the law in effect before September 1 applies. See id. §§ 11–12. For convenience, all citations to the TCPA in this opinion are to the version of the statute prior to September 1, 2019. See Act of May 21, 2011, 82d Leg., R.S., ch. 341, § 2, 2011 Tex. Gen. Laws 961–64, amended by Act of May 24, 2013, 83d Leg., R.S., ch. 1042, 2013 Tex. Gen. Laws 2499–2500. 2 square feet of three-inch asphalt. The contract specified that the concrete was to be “8 [inch] 4000 psi concrete with fiber.” H&E agreed to pay Lozoya $296,078.68 for all the work under the contract, with half of the money to be paid before Lozoya started the work and the other half to be paid “upon completion and final walkthrough.” H&E and Lozoya signed a second contract that required Lozoya to “[s]ervice blade” and lay caliche over 4.78 acres of the property and to install twelve pipe bollards. H&E agreed to pay $81,870 for this work. Lozoya purchased concrete that contained micro reinforcement fiber from PB Materials, LLC to use on the project. It also purchased the asphalt for the project from APM Contractor Services, LLC. After Lozoya completed the work, H&E filed this suit. In its first amended petition, H&E alleged that the parties agreed that Lozoya would use macro reinforcement fiber in the concrete. H&E pleaded that, due to Lozoya’s use of micro reinforcement fiber, there had been “a considerable amount of cracking in the concrete slab that requires immediate removal and replacement.” H&E also alleged that the contract required Lozoya “to install the asphalt to be three inches thick through the entire concept.” H&E asserted that Lozoya “installed the asphalt in a manner that is inconsistent with the three-inch thickness” and that the asphalt “is of substandard strength and starting to crack.” As relevant to this appeal, H&E asserted claims against Lozoya for the following: (1) breach of contract based on Lozoya’s failure to provide concrete with the correct reinforcement fiber and to install the asphalt to the contracted-for thickness; (2) breach of the implied warranty of good and workmanlike manner based on Lozoya’s failure to ensure that its services were performed in a skillful and workmanlike manner; (3) negligence; (4) negligent misrepresentation; and (5) fraud. H&E specifically alleged that Lozoya made material misrepresentations about the

3 type of reinforcement fiber that would be included in the concrete mix and about the thickness of the asphalt. In its answer and counterclaim, Lozoya asserted that it supplied H&E with “certain goods or services” as shown by the two contracts and that H&E was required to pay for the goods or services. Lozoya stated that the prices that it charged to H&E were “usual, customary, or reasonable prices” and “were the same prices charged to any other customer for the same goods and service at that time in Midland County.” Lozoya pleaded that H&E failed to pay for the goods and services and sought to recover $229,909.34 based on a sworn account, breach of contract, quantum meruit, and the Texas Prompt Pay Act, TEX. PROP. CODE ANN. §§ 28.001–.010 (West 2014). Lozoya filed a TCPA motion to dismiss H&E’s claims. Lozoya asserted that H&E’s claims were based on, related to, or in response to Lozoya’s exercise of the right of free speech. Lozoya specifically alleged that the statements about “the materials and qualities of the concrete work it had completed” for H&E were made in connection with a matter of public concern. Lozoya further contended that H&E could not meet its burden to establish a prima facie case for each essential element of its claims. In conjunction with its motion to dismiss, Lozoya filed the affidavit of its CEO, Filiberto I. Lozoya, Jr. Filiberto stated that Lozoya and H&E entered into two contracts. As relevant here, the first contract required Lozoya to install approximately 28,196 square feet of three-inch asphalt and “8,250 square feet of 8- inch 4000 psi concrete with fiber.” The second contract required Lozoya to install a layer of caliche over 4.78 acres of the site and to install twelve pipe bollards. Filiberto attached both contracts to his affidavit. Filiberto confirmed that H&E agreed to pay Lozoya $296,078.68 for the work under the first contract and $81,870 for the work under the second contract. However, because of the development of cracks in the concrete, H&E paid only fifty 4 percent of the amount due on the first contract and none of the amount due on the second contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arthur Andersen & Co. v. Perry Equipment Corp.
945 S.W.2d 812 (Texas Supreme Court, 1997)
Downer v. Aquamarine Operators, Inc.
701 S.W.2d 238 (Texas Supreme Court, 1985)
State v. Paul Reed Harper
562 S.W.3d 1 (Texas Supreme Court, 2018)
El Apple I, Ltd. v. Olivas
370 S.W.3d 757 (Texas Supreme Court, 2012)
City of Laredo v. Montano
414 S.W.3d 731 (Texas Supreme Court, 2013)
Long v. Griffin
442 S.W.3d 253 (Texas Supreme Court, 2014)
In re Lipsky
460 S.W.3d 579 (Texas Supreme Court, 2015)
Sullivan v. Tex. Ethics Comm'n
551 S.W.3d 848 (Court of Appeals of Texas, 2018)
Toth v. Sears Home Improvement Prods., Inc.
557 S.W.3d 142 (Court of Appeals of Texas, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Lozoya Construction, Inc. v. H&E Equipment Services, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/lozoya-construction-inc-v-he-equipment-services-inc-texapp-2020.