Lowry v. Law

150 P. 660, 27 Cal. App. 483, 1915 Cal. App. LEXIS 45
CourtCalifornia Court of Appeal
DecidedMay 26, 1915
DocketCiv. No. 1365.
StatusPublished
Cited by1 cases

This text of 150 P. 660 (Lowry v. Law) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lowry v. Law, 150 P. 660, 27 Cal. App. 483, 1915 Cal. App. LEXIS 45 (Cal. Ct. App. 1915).

Opinion

CHIPMAN, P. J.

Plaintiff brought the action as assignee of the American National Bank of San Francisco, hereinafter referred to as the bank, and as assignee of the American-Hawaiian Engineering & Construction Company, hereinafter referred to as the construction company. There were several causes of action stated.

*484 In the first count is alleged an account stated, in the sum of $46,033.50, between the bank and defendant which was assigned to plaintiff.

The second count is for the value of certain extras furnished in the construction of the Monadnock Building in the city of San Francisco, aggregating $2,892.19.

The third count is for additional extras based upon their reasonable value, to wit: the sum of $5,225.53.

The fourth count is for the sum of $3,597.50 as a balance due upon an open account for moneys paid and expended for the use and benefit of defendant.

The causes of action set out in the second, third, and fourth counts were assigned to plaintiff by the construction company.

In his answer the defendant denied the existence of any account stated; admitted the doing of certain extra work but denied that it was of greater value than $939.99, exclusive of the set-off and counterclaim set forth in the answer. The answer to the third count is a denial, but admits certain amounts to be due which it is alleged, however, were offset by the counterclaim ; the fourth count was denied.

As a special defense to the several causes of action alleged in the complaint and by way of counterclaim, defendant alleged the ■ existence of a bulding contract between the construction company, plaintiff’s assignor, and the defendant, in which the price for the erection of said building was fixed at the sum of $482,200.00 to be paid by defendant, the owner, to the said contractor in installments, subject, however, to additions and deductions on account of alterations and omissions, respectively ; that by agreement a large amount of work was omitted from the construction of the building, and that the total reasonable value of the amount of work so omitted was $12,657.10, which defendant claimed as a set-off by deduction from the conceded claims and demands of plaintiff.

The cause was tried by the court without a jury and upon the issues thus raised the court found: That there was no account stated; that the value of the extra work referred to in the second cause of action amounted to the sum of $200.00 and no more, in addition to the sum of $1,147.12 admitted to be due by the answer, subject, however, to the set-off and counterclaim of defendant, amounting, as elsewhere ■ found, to $10,055.64; as to the third cause of action the court found that the value of the extra work amounted to $787.96, which *485 was subject to said counterclaim. The total value of the extra work included in the second and third counts, admitted and found, was $2,356.99; as to the fourth cause of action the court found that, except as stated in the findings, it was not true that there was a balance due upon an open book account for moneys paid out and expended by said construction company the sum of $3,572.50, as alleged, but that of said sum there had been paid out and expended the sum of $672.50 and no more. The court further found the amount of the oif-set as heretofore stated, to wit: $10,055.64.

As conclusion of law the court found that plaintiff was not entitled to any judgment and that defendant was entitled to his costs and judgment was entered accordingly. Plaintiff’s motion for a new trial was denied and he appeals from the order.

Plaintiff contends 1. That the evidence established an account stated; 2. That the value of the extra work, fixed at $2,359.99, should be increased by the sum of $3,225.00, being the alleged value of certain extra work in constructing certain pilasters of the reasonable value of said last named amount; and, 3. That there is no evidence to sustain the finding that the reasonable value of the omitted work, claimed in defendant’s offset, was $10,055.64.

The alleged account stated first demands attention. To establish plaintiff’s contention, he was called upon to show by clear proof that an agreement existed between the bank and defendant that the twenty-five per cent of the contract price should be and was held by defendant for a period of 35 days after the completion of the contract, for the sole use and benefit of the bank and not to meet the claims of possible lienors which, as it turned out, aggregated about $78,000.00. These claims were settled by defendant, as the law and the building contract required, so far as the retained twenty-five per cent, to wit: $46,033.50, would go.

On January 16, 1905, defendant entered into a contract with the construction company by which it agreed to construct a portion of the building known as the Monadnock, in San Francisco. The contract provided that the building should be constructed in two sections, the first one to be completed before the second was commenced. Section 1 was completed in March, 1907, and the money paid to the contractor and its creditors. The present controversy connects itself with the *486 construction of section 2 on which work began about May 1, 1907, and was completed about March 8,1909. Upon the completion of this section it was found that, exclusive of omitted work and extra work, there was due the contractor, its creditors or assigns, the sum of $46,033.50 which, as we understand the evidence, was the retained twenty-five per cent of the amount due for work on section 2. The contract was duly recorded and no question arises as to defendant’s right as well as duty to withhold payment of this twenty-five per cent for 35 days after the completion of the contract. The only question is, Did defendant put himself in such position as required him to pay this money to lienors and also a like amount to the bank, i. e., to pay it twice ?

The contract is a very elaborate document and seems to have been drawn to meet every possible contingency likely to arise. Among other things it provided that progressive payments were to be made monthly of amounts approximating seventy-five per cent of the value of the work and materials to be estimated by the architect and approved in writing by the owner, expressly providing that no more than seventy-five per cent of the contract price should be paid at the completion of the building and that twenty-five per cent of the whole contract price should be paid thirty-five days after completion of the contract and acceptance of the work, as to which latter and the amounts due certificates in writing should be given by the architect, countersigned by the owner. It was also provided that monthly estimates of the architect should be subject to correction by him in any, subsequent monthly or final estimates, and the monthly estimates, by the terms of the contract, were “presumed to be only approximate.” No oversight in superintendence by the architect and no certificates should relieve the contractor from full performance and the architect was authorized to reject defective or deficient work or require it to be done over and no payment was to be made unless the work had been done to the satisfaction of the architect.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

C. F. Bolster Co. v. J. C. Boespflug Construction Co.
334 P.2d 247 (California Court of Appeal, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
150 P. 660, 27 Cal. App. 483, 1915 Cal. App. LEXIS 45, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lowry-v-law-calctapp-1915.