Loverde v. Building Management, Inc.

71 Va. Cir. 204
CourtFairfax County Circuit Court
DecidedJune 27, 2006
DocketCase No. (Law) 2005-1097
StatusPublished

This text of 71 Va. Cir. 204 (Loverde v. Building Management, Inc.) is published on Counsel Stack Legal Research, covering Fairfax County Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Loverde v. Building Management, Inc., 71 Va. Cir. 204 (Va. Super. Ct. 2006).

Opinion

By Judge Kathleen H. MacKay

On Friday, May 4,2006, this matter came before the Court on Fourth-Party Defendant Chamberlain Construction Corporation’s Demurrers. Specifically, Chamberlain Construction Corporation demurred to Goughnour Engineering, P.C., and Steven Goughnour’s Fourth-Party Motion for Judgment and to Plaintiff Bishop Paul Loverde’s Counterclaim. Although [205]*205initially it appeared that Chamberlain Construction Corporation was also demurring to Building Management, Inc.’s Cross-claim against Chamberlain Construction Corporation, in its Reply to Opposition Briefs Chamberlain Construction Corporation states that Building Management, Inc., should not be included in any argument. After the hearing, the Court took the matter under advisement and requested that each side submit a list of contractual provisions supporting their respective arguments regarding the issue of property insurance. Since the hearing date, the Court has had the opportunity to review these lists and again review the briefs in light of oral arguments made, and I am now prepared to rule.

I. Factual and Procedural History

On or about December 5, 2001, Plaintiff Bishop Loverde contracted with Chamberlain Construction Corporation for the construction of the St. Joseph’s Parish School Addition/Renovation Project. On or about February 19, 2002, Chamberlain Construction Corporation entered into a subcontract with Building Management, Inc., and subsequently Building Management, Inc., subcontracted with Goughnour Engineering, P.C., to provide certain professional engineering services for the Project.

On or about February 18, 2003, a portion of the roof of the Project collapsed.

On February 23, 2005, Plaintiff Bishop Loverde filed the original Motion for Judgment against Defendant Building Management, Inc., for breach of contract, negligence, breach of implied warranty of merchantability, and breach of implied warranty of fitness for a particular purpose. Plaintiff Bishop Loverde alleged that the cause of the collapse was that the light gauge steel trusses were incorrectly designed, engineered, manufactured, and/or installed. Plaintiff Bishop Loverde claims damage to the subject property and to adjacent property.

On August 22, 2005, Building Management, Inc., filed a Third-Party Motion for Judgment against Goughnour Engineering and Steven David Goughnour. Building Management, Inc., argues that, if it is held liable to Plaintiff Loverde, it is entitled to contribution or indemnity from Goughnour Engineering and Steven David Goughnour.

Similarly, onNovember 30,2005, Goughnour Engineering and Steven David Goughnour filed a Fourth-Party Motion for Judgment against Chamberlain Construction Corporation and Calvert-Jones. Goughnour Engineering, P.C., and Steven David Goughnour argue that if they are held [206]*206liable to Building Management, Inc., then they are entitled to contribution and indemnification from Chamberlain Construction Corporation and Calvert-Jones.

On January 24, 2006, Chamberlain Construction Corporation filed a Cross-claim against Plaintiff Bishop Loverde and Defendant Building Management, Inc.

On February 16, 2006, Plaintiff Bishop Loverde filed a Counterclaim against Chamberlain Construction Corporation, alleging breach of contract, negligence, and breach of express warranties. On the same day, Building Management, Inc., filed a Cross-claim against Chamberlain Construction Corporation, and Building Management, Inc., and amended their Third-Party Motion for Judgment against Goughnour Engineering and Steven David Goughnour.

II. Legal Analysis

A demurrer tests the legal sufficiency of the claims stated in the challenged pleading. Dray v. New Market Poultry Products, Inc., 258 Va. 187, 189, 518 S.E.2d 312 (1999). The sole question to be decided by the court is whether the facts pleaded, implied, and fairly and justly inferred are legally sufficient to state a cause of action against Defendants. Thompson v. Skate America, Inc., 261 Va. 121, 128, 540 S.E.2d 123 (2001).

Demurrer to Plaintiff Loverde’s Counterclaim and Demurrer to Fourth-Party Motion for Judgment for Contribution and Indemnification

Plaintiff Loverde seeks damages for breach of contract, negligence, and breach of express warranties. Fourth-Party Plaintiff Goughnour Engineering, P.C., and Steven David Goughnour argue that, if they are held liable to Building Management, Inc., then they are entitled to contribution and indemnification from Chamberlain Construction Corporation and Calvert-Jones.

The odd way in which this suit was initiated, that is by Loverde suing Building Management, Inc., rather than its prime contractor Chamberlain Construction Corporation has, arguably, required every subcontractor to sue every other subcontractor in order for everyone’s obligations to get sorted out. Overall, however, the Court agrees with the various pleadings filed by the various subcontractors that Plaintiff Loverde has a viable contract claim against its contractor and a viable negligence claim only as to damage inflicted on the adj acent property.

[207]*2071. Breach of Contract

As to the breach of contract claim, Chamberlain Construction Corporation demurs arguing that the contractual provision of insurance bars recovery of damages. Section 11.3.1 of the Conditions of the Contract required the Owner, Plaintiff Loverde, to purchase and maintain Builders’ Risk Insurance. The entire contract should have been attached as Exhibit A to the original Motion for Judgment. See letter dated May 10, 2006, from Attorney Sanford A. Friedman to this Court. The explicit purpose of this insurance was to protect “interests of the Owner, the Contractor, Subcontractors, and Sub-subcontractors in the Work.”

The Supreme Court of Virginia has held, where “a plaintiff has contracted to protect the defendant from a loss by procuring insurance, the plaintiff (or his subrogee) may not recover for that loss from the defendant even if the loss is caused by the defendant’s negligence.” Walker v. Vanderpool, 225 Va. 266, 271, 302 S.E.2d 669 (1983). Accordingly, the breach of contract claim is barred from recovery by the contractual provision of Builders’ Risk Insurance.

Plaintiff Loverde highlights that the waiver of subrogation provision in the Contract was struck by the parties. Plaintiff Loverde argues that, by striking this waiver, the parties agreed that the right of subrogation existed hereby giving Plaintiff Loverde the right to recover from Chamberlain Construction Corporation. Even if the parties agreed to strike the waiver of subrogation clause in the contract, this does not change the effect of Walker. Id.

Plaintiff contracted to protect the Owner, Contractor, Subcontractors, and Sub-subcontractors by procuring insurance; therefore, it is the Court’s belief that the deletion of the waiver of subrogation provision has no effect on the issue of insurance and the Plaintiff may not recover for losses that would be covered by that insurance as to the work which is the subject of the Contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thompson Ex Rel. Thompson v. Skate America, Inc.
540 S.E.2d 123 (Supreme Court of Virginia, 2001)
Dray v. New Market Poultry Products, Inc.
518 S.E.2d 312 (Supreme Court of Virginia, 1999)
Sensenbrenner v. Rust, Orling & Neale, Architects, Inc.
374 S.E.2d 55 (Supreme Court of Virginia, 1988)
Walker v. Vanderpool
302 S.E.2d 669 (Supreme Court of Virginia, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
71 Va. Cir. 204, Counsel Stack Legal Research, https://law.counselstack.com/opinion/loverde-v-building-management-inc-vaccfairfax-2006.