Love v. Meyer & Najem Construction, LLC

950 N.E.2d 7
CourtIndiana Court of Appeals
DecidedJune 15, 2011
Docket32A01-1006-CR-317
StatusPublished
Cited by2 cases

This text of 950 N.E.2d 7 (Love v. Meyer & Najem Construction, LLC) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Love v. Meyer & Najem Construction, LLC, 950 N.E.2d 7 (Ind. Ct. App. 2011).

Opinion

OPINION

FRIEDLANDER, Judge.

James and Diana Love appeal from the trial court’s grant of partial summary judgment in favor of Meyer & Najem Construction, LLC (Meyer Najem). The Loves present one issue for review: Did the trial court properly grant Meyer Na-jem’s motion for partial summary judgment upon determining that Meyer Najem did not owe a duty to James?

We reverse.

This case arises out of injuries that James Love sustained on May 13, 2008 while working for General Interiors, Inc. at the Brownsburg High School Classroom Renovation and Addition project (the Project). The Project included the addition of several choir and band practice rooms. Meyer Najem contracted with Brownsburg Community School Corporation (the Owner) to serve as the construction manager for the Project. 1 Likewise, General Interiors directly contracted with the Owner to install acoustical panel ceilings, acoustical wall panels, and acoustical curtains in the choir and band practice rooms. There was no contract between Meyer Najem and General Interiors.

To fulfill its responsibilities, Meyer Na-jem employed Andrew Slye to serve as a fulltime, on-site superintendent for the Project. James served as the person in charge and responsible for safety procedures for General Interior’s crew working on the Project.

In May 2008, the Project was nearing completion. On the day James sustained his injuries, he and another employee of General Interiors were hanging two acoustical curtains in a show choir classroom. The curtain track to which the curtains attached was approximately sixteen to twenty feet off of the floor above a narrow *9 horizontal window. The day before, Slye told James that they could not use a scissor lift to install the curtains because Slye was concerned that the scissor lift would damage the newly installed flooring. To accomplish the task of hanging the curtains, James and his co-worker decided to use thirty-foot extension ladders that had rubber cushions on the bottom. James and his co-worker positioned their ladders and hung the first set of curtains. While setting up the ladders to hang the second set of curtains, Slye directed James to put something under the feet of the ladders so that they would not scratch or otherwise damage the floor. James explained to Slye that they had already installed a curtain using the ladders and that the ladders caused no damage to the flooring. Nevertheless, Slye again told James to put something under his ladder to protect the flooring.

According to James, Slye picked up a piece of carpeting and instructed James and his co-worker to put it under their ladders. James maintains that Slye actually helped position the carpet remnant, nap-side down, under the ladders. In contrast to James’s recollection of events, Slye stated in his deposition that James looked around and located the carpeting remnant and asked if it was suitable to use under the ladders. Slye indicated that the carpet, if used nap-side down, would protect the flooring and that he conditioned James’s choice of carpet as a barrier between the ladders and the floor by stating “as long as it doesn’t slide.” Appellants’ Appendix at 118. Slye then left the room. A few minutes later, Slye heard a commotion in the choir room. While working from the ladder to install the second curtain at a height of fifteen to sixteen feet, the carpeting under the ladder slid causing both James and the ladder to fall. James suffered permanent injury.

The Loves filed their complaint against Meyer Najem on February 5, 2009, alleging among other things that Meyer Najem “assumed a duty of safety by contract and its conduct at the SCHOOL construction site.” Id. at 16. Meyer Najem filed its answer on March 27, 2009. A year later, on March 30, 2010, Meyer Najem moved for summary judgment, arguing that it owed no duty to Love by contract and that it did not assume a duty by conduct.

The Loves filed a response in opposition to Meyer Najem’s motion for summary judgment as well as a request for partial summary judgment in their favor. In their motion, the Loves clarified that their theory of the case was not that Meyer Najem assumed a duty for project-wide safety by contract or by its conduct on the jobsite. Rather, the Loves maintained that their theory of the case was that Meyer Najem assumed a duty to use reasonable care when it asserted control over the means and methods by which General Interior’s employees (i.e., Love and his coworker) could perform their work on the day in question.

On May 26, 2010, the trial court held a hearing on the cross-motions for summary judgment. The trial court entered an order on June 16, 2010, granting Meyer Na-jem’s motion for summary judgment and denying the Loves’ cross-motion for summary judgment. The. trial court found that “[a]s a matter of law, [Meyer Najem] did not assume, by contract or by conduct, a duty for project-wide safety at the construction site at issue in this cause, and therefore owed no duty to [James Love].” 2 Id. at 9. The Loves now appeal.

*10 Our standard of review for summary judgment is the same as that used in the trial court: summary judgment is appropriate only where the evidence shows there is no genuine issue of material fact and the moving party is entitled to judgment as a matter of law. Ind. Trial Rule 56(C); Bd. of Sch. Comm’rs of City of Indianapolis v. Pettigrew, 851 N.E.2d 326 (Ind.Ct.App.2006), trans. denied. All facts and reasonable inferences drawn from those facts are construed in favor of the non-moving party. Bd. of Sch. Comm’rs of City of Indianapolis v. Pettigrew, 851 N.E.2d 326. Review of a summary judgment motion is limited to those materials designated to the trial court. Id. Our standard of review is not altered by the fact that the parties have filed cross-motions for summary judgment. Alexander v. Marion County Sheriff, 891 N.E.2d 87 (Ind.Ct.App.2008), trans. denied.

To premise a recovery on a theory of negligence, a plaintiff must establish three elements: (1) a duty on the part of the defendant to conform his conduct to a standard of care arising from his relationship with the plaintiff, (2) a failure of the defendant to conform his conduct to the requisite standard of care required by the relationship, and (3) an injury to the plaintiff proximately caused by the breach. Webb v. Jarvis, 575 N.E.2d 992 (Ind.1991). Here, the trial court determined that Meyer Najem did not owe a duty to James.

“ ‘Duty’ has been defined as ‘an obligation, to which the law will give recognition and effect, to conform to a particular standard of conduct toward another.’ ” Blake v. Calumet Constr. Corp., 674 N.E.2d 167, 170 (Ind.1996) (quoting W.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
950 N.E.2d 7, Counsel Stack Legal Research, https://law.counselstack.com/opinion/love-v-meyer-najem-construction-llc-indctapp-2011.