Louisville & Nashville Railroad v. O'Flynn

281 S.W. 174, 213 Ky. 346, 1926 Ky. LEXIS 514
CourtCourt of Appeals of Kentucky (pre-1976)
DecidedMarch 2, 1926
StatusPublished
Cited by1 cases

This text of 281 S.W. 174 (Louisville & Nashville Railroad v. O'Flynn) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky (pre-1976) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Louisville & Nashville Railroad v. O'Flynn, 281 S.W. 174, 213 Ky. 346, 1926 Ky. LEXIS 514 (Ky. 1926).

Opinion

Opinion of the Court by

Judge Sampson

Affirming.

Appellee, 0’Flynn, sued appellant, railroad company, for damages resulting to his lands and growing crops from water cast thereon by drainless embankments of the railroad, and recovered a verdict.

The petition as first drafted sounded in both contract and tort, and appellant company moved for an election, and this motion was sustained along with one to strike certain averments of the petition sounding in tort. Some years ago a similar contention arose between appellant and appellee and others, and to settle the matter all parties entered into a written contract reading:

“Received of the Louisville and Nashville Railroad Company the sum of two hundred dollars ($200.00) which, with said company’s agreement herein contained, is accepted in full settlement, satisfaction and compromise of all claims in my favor asserted by me in a suit now pending in the Daviess circuit court, wherein I am plaintiff and said company is defendant, being common law action No......., on account of alleged injury to my land and crops by the alleged negligent construction and maintenance of said company’s roadbed and ditches at a point in Daviess county lying between Utica station and the county ditch north of said station, and of all claims and demands of every character whatsoever which I may have had, have or may hereafter have against said company, its officers, agents or employes, on account of any water overflowing' or standing upon any part of my land described in the petition in said action, which is situated in Daviess county, Kentucky, between Útica and, Brown Valley, *348 and adjoining the lands of Sue Talbott, J. M. Clark and Joe Birkhead, by reason of said company’s constructing or maintaining any ditches, or changing the natural course of Big Bun creek at said point, or by reason of the damming up, obstructing, impeding or confining of any water by said company’s railroad bed or embankment, or because of the filling up or damming of any ditches, or because of any or all the conditions heretofore or now existing at or near my said land, and on every other account whatsoever.
“The said company hereby agrees, as part of the consideration of this settlement, to construct and maintain ditches on both sides of its track at said point as follows': The ditch on the west side of said track is to begin at the county ditch and to be twelve (12) feet wide at top, four (4) feet deep and six (6) feet wide at bottom, the depth from level of land, south to corner of Joe Birkhead’s land; thence south with his land eleven (11) feet wide at top, four (4) feet deep and five (5) feet wide at bottom, half of dirt to be put on Birkhead’s side; thence south ten (10) feet wide at top, four (4) feet deep and four (4) feet wide at bottom to railroad culvert in Utica, half of dirt to be thrown on each side and each bank of ditch to have a gradual slope from top to bottom. The ditch on the east side of said track at said point is to begin at culvert near county ditch eight (8) feet wide at top, three and a half (3%) feet find four (4) feet wide at bottom to Joe Birkhead’s land; thence south seven (7) feet wide at top, three and a half (3%) feet deep and three and a half (3%) feet wide at bottom to E. 0’Flynn’s corner; thence south six (6) feet wide at top, three and a half (3%) feet deep and three (3) feet wide at bottom to E. 0’Flynn’s southern corner. It is understood that these ditches are to be seventeen (17) feet from the outside of the rail, and that the water from the east side ditch is to be carried through the culvert referred to above under railroad track to the west side ditch.
“In consideration of the construction and maintenance of said ditches, and the said sum paid to me, I further agree and bind myself, my vendees, heirs and assigns, that I, and they, will not make any claim or claims, or bring any suit or action at law, against said company,- its successors or assigns, on *349 account of any damage that may have been or may be done to said land, on any part thereof, by water overflowing or standing thereon or damaging said land in any way, whether occasioned by the failure of said company to have a culvert, pipe, waterway, or other drainage whatsoever through or under said railroad embankment or roadbed or right of way, or on account of said railroad embankment now or as it may be hereafter constructed as a roadbed, or for any other reason.
“It is further understood and agreed by and between the parties hereto that the obligation on any part to hold said company harmless against any claims, demands or litigation on account of any' damage to said land, as aforesaid, shall be a covenant running with the land and binding upon me, my heirs and assigns forever. The said action is to be dismissed settled at the cost of the defendant.”

The petition in substance alleged O’Flynn to be the owner of about twenty acres of fine bottom land near the railroad embankment on which land water was caused to flow by reason of the railroad embankment, and because the railroad company failed to construct and maintain the ditches along its right of way which it contracted to build and maintain and that by reason thereof the water destroyed a crop of com and grass belonging to appellee in the year 1917, and another crop of corn and a crop of grass in 1920, and a third one in 1921, to the damage of appellee in named sums aggregating in all $1,000.00. The plaintiff also filed an amended petition averring the failure of the railroad company to build the ditches in accordance with the contract. The answer of the company traversed the averments in the petition of loss and damage to the plaintiff for each of the years. By a second paragraph it was affirmatively pleaded that the ditches were constructed in accordance with the term's of the contract, and further that the appellee, O’Flynn, participated and assisted in the construction of the ditches and accepted them when completed as a full compliance with the terms of the contract, and is now estopped to assert that the ditches did not comply with the terms of the contract. The third paragraph of the answer pleaded contributory negligence.

Appellant, O’Flynn, offered and was permitted to prove by himself and several witnesses that his land was *350 overflowed by water backing np from the railroad embankment; that the culverts were not large enough to allow the water to pass; that the ditches called for in the contract were not properly constructed, at least in part, and that they had not been properly maintained, but on the contrary had been allowed to cave in and to fill up and thus cause the water to flow upon and stand upon appellee’s lands; that in the year 1917 he lost growing crops of corn and a growing crop of grass to his damage in the sum of about $300.00, and for the years 1920 and 1921 he lost growing crops upon his land by floods caused in the same manner, to his damage in named sums.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hellier Graded School District v. Pike County Board of Education
24 S.W.2d 934 (Court of Appeals of Kentucky (pre-1976), 1930)

Cite This Page — Counsel Stack

Bluebook (online)
281 S.W. 174, 213 Ky. 346, 1926 Ky. LEXIS 514, Counsel Stack Legal Research, https://law.counselstack.com/opinion/louisville-nashville-railroad-v-oflynn-kyctapphigh-1926.