Louisiana Industrial Coatings, Inc. v. Boh Bros. Construction Co. (In Re Louisiana Industrial Coatings, Inc.)

53 B.R. 464
CourtDistrict Court, E.D. Louisiana
DecidedAugust 12, 1985
DocketCiv. A. 82-309
StatusPublished
Cited by14 cases

This text of 53 B.R. 464 (Louisiana Industrial Coatings, Inc. v. Boh Bros. Construction Co. (In Re Louisiana Industrial Coatings, Inc.)) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Louisiana Industrial Coatings, Inc. v. Boh Bros. Construction Co. (In Re Louisiana Industrial Coatings, Inc.), 53 B.R. 464 (E.D. La. 1985).

Opinion

MEMORANDUM OPINION AND ORDER

CASSIBRY, Senior District Judge:

Louisiana Industrial Coatings, Inc. (“LIC”) appeals from the judgment of the United States Bankruptcy Court for the Eastern District of Louisiana. The case originates from a dispute over the unpaid balances on thirteen industrial painting subcontracts between LIC, the subcontractor, and Boh Bros. Construction Company, Inc. (“Boh”), the prime contractor. The bankruptcy court denied the claims of LIC and its purported assignee, the Bank of St. Charles and Trust Company (“Bank”), and allowed the counterclaim of Boh in the amount of $92,345 as an unsecured nonpri-ority claim in bankruptcy. Having reviewed the entire record in this case and the applicable law, I amend the judgment in one respect and affirm in all others.

I.

On September 4, 1980, LIC filed a voluntary petition for relief under chapter 11 of the Bankruptcy Code. LIC, as debtor in possession, then filed thirteen separate actions in the bankruptcy court to recover payments from Boh for work performed pursuant to thirteen subcontracts. The Bank joined the litigation asserting its claim as assignee of LIC’s accounts receivable. Boh denied that any funds were due either LIC or the Bank and filed a counterclaim for amounts expended to complete four of the subcontracts.

The facts of this case are largely undisputed. At the time the bankruptcy petition was filed, LIC had completed eight of the thirteen subcontracts. In late August, 1980, just prior to the filing of the petition, LIC stopped work on the remaining five subcontracts. LIC admits that it breached four of these subcontracts, but denies having breached the fifth, entitled the LOOP-Clovelly Electrial Substation subcontract, claiming that Boh breached in the first instance. The bulk of the testimony at trial centered on the LOOP-Clovelly subcontract, the sole factual dispute in this case.

As the prime contractor, Boh was required to complete the five unfinished subcontracts. Boh could complete one of the subcontracts for an amount equal to the outstanding contract price. However, each of the other four subcontracts could only be completed at a cost which exceeded the outstanding contract price for a total loss to Boh of $163,229. This amount was stipulated as were the amounts billed and unpaid to LIC for work completed on the thirteen subcontracts.

Finding that LIC had substantially breached the five uncompleted subcontracts, including the LOOP-Clovelly subcontract, the bankruptcy court held that Boh owed LIC nothing on these subcontracts. Furthermore, the court interpreted the thirteen identical subcontracts as permitting Boh to recoup its losses on the uncompleted subcontracts from funds which would otherwise be due LIC on the completed subcontracts. Because Boh’s losses exceeded the unpaid balances on the completed subcontracts, the court concluded that no debt was owed LIC and dismissed LIC’s claims for payment as well as the Bank’s. 1 Finally, the court granted *467 Boh’s counterclaim for its total excess loss on the uncompleted subcontracts minus the unpaid balances on the completed subcontracts plus the one subcontract completed by Boh without a loss.

On appeal, LIC asserts that the bankruptcy court erred in two respects: (1) the court failed to construe the subcontracts properly; and (2) the court failed to consider the effect of section 553 of the Bankruptcy Code on Boh’s ability to recoup its losses. 2 Based on these alleged errors, LIC requests that the decision of the bankruptcy court be reversed and judgment entered in its favor and against Boh for $70,-884 plus costs. The sum of $70,884 represents the unpaid balances on the completed subcontracts and on the one uncompleted subcontract which Boh finished without a loss.

II.

The first question presented on appeal is the proper standard of review to be applied to the findings of the bankruptcy court. LIC contends that the court’s decision is not entitled to the deference afforded by the clearly erroneous standard of review, but rather should be treated merely as the argument of counsel. LIC’s contention is based on the court’s verbatim adoption of Boh’s proposed findings of fact and conclusions of law.

LIC’s argument on this score has been settled recently by the United States Supreme Court. See Anderson v. City of Bessemer City, — U.S. -, 105 S.Ct. 1504, 84 L.Ed.2d 518 (1985). In Anderson, the Supreme Court held that the findings of a trial judge may be reversed only if clearly erroneous even if the judge adopts proposed findings of the prevailing party verbatim. 105 S.Ct. at 1511. Although the Court was interpreting Rule 52 of the Federal Rules of Civil Procedure, its conclusion applies equally here. Rule 8013 of the Bankruptcy Rules of Practice and Procedure mandates the application of the clearly erroneous standard of review to a bankruptcy court’s findings. The rule tracks the language of Rule 52, and clearly accords the same deference and weight to the factual findings of a bankruptcy judge as that accorded to those of a district judge. See Bank.R.Prac. & P. 8013 advisory committee note (West 1984).

III.

Having determined the appropriate standard of review, I turn to LIC’s argument that the bankruptcy court failed to construe properly the subcontracts at issue in this case. The bankruptcy court held that under paragraph ten of each of the identical subcontracts, Boh was entitled to apply its losses on the uncompleted subcontracts against the unpaid balances on the completed subcontracts. Paragraph ten provides as follows:

Should Subcontractor at any time refuse or neglect to supply a sufficient number of properly qualified workmen or a sufficient quantity of materials of proper quality, or abandon the work or fail in any respect to prosecute the work covered by this contract with promptness and diligence, or fail in the performance of any of the agreements herein contained, Contractor may, at its option, after forty-eight (48) hours notice to Subcontractor, provide any such labor and materials and deduct the cost thereof from any money then due or thereafter to become due to Subcontractor under this contract or otherwise; or Contractor may, at its option, terminate this contract and, for the purposes of completing the work covered by this contract, Contractor shall have the right to take possession of all the materials, tools and appliances belonging to Subcontractor at the site of the work, and Contractor may either complete said work itself or may employ, or contract *468

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Staggs v. Forrester (In Re Staggs)
177 B.R. 92 (N.D. Indiana, 1995)
Boyer v. Baker & Schultz, Inc. (In re Smith)
123 B.R. 605 (N.D. Indiana, 1991)
Matter of Smith
123 B.R. 605 (N.D. Indiana, 1991)
Atkins v. Lowin (In Re Monetary Group)
91 B.R. 138 (M.D. Florida, 1988)
Warsco v. Weaver (In Re Weaver)
93 B.R. 172 (N.D. Indiana, 1988)
Warsco v. Graves (In Re Graves)
70 B.R. 535 (N.D. Indiana, 1987)
Matter of Busick
65 B.R. 630 (N.D. Indiana, 1986)
Matter of Grieshop
63 B.R. 657 (N.D. Indiana, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
53 B.R. 464, Counsel Stack Legal Research, https://law.counselstack.com/opinion/louisiana-industrial-coatings-inc-v-boh-bros-construction-co-in-re-laed-1985.