Louisiana Environmental Society, Inc. v. William T. Coleman, Secretary, Department of Transportation

524 F.2d 930, 6 Envtl. L. Rep. (Envtl. Law Inst.) 20093, 1975 U.S. App. LEXIS 11728
CourtCourt of Appeals for the Fifth Circuit
DecidedNovember 28, 1975
Docket74-3087
StatusPublished
Cited by12 cases

This text of 524 F.2d 930 (Louisiana Environmental Society, Inc. v. William T. Coleman, Secretary, Department of Transportation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Louisiana Environmental Society, Inc. v. William T. Coleman, Secretary, Department of Transportation, 524 F.2d 930, 6 Envtl. L. Rep. (Envtl. Law Inst.) 20093, 1975 U.S. App. LEXIS 11728 (5th Cir. 1975).

Opinion

CLARK, Circuit Judge:

The Louisiana Environmental Society (LES) appeals from the denial of preliminary injunctive relief to halt the construction of the Interstate 220 bypass highway around Shreveport, Louisiana. Based upon a full opinion dealing with every issue raised, the district court denied the motion for preliminary injunction after determining that LES had failed to demonstrate a substantial likelihood it would prevail on the merits. 1 The court’s ruling that the Secretary of Transportation had correctly complied with § 4(f) of the Department of Transportation Act 2 raises a serious question which we pretermit here because the record establishes that LES failed to carry its burden of proving irreparable injury would occur absent injunctive relief. The denial of the preliminary injunction is affirmed.

Before this court can determine that the denial of a preliminary injunction amounts to an abuse of the trial court’s discretion, it must be determined that the proponent of such relief has met the high threshold burden of proving “(1) a substantial likelihood that [he] will prevail on the merits, (2) a substantial threat that [he] will suffer irreparable injury if the injunction is not granted, (3) that the threatened injury to [him] outweighs the threatened harm the injunction may do to the defendant, and (4) that granting the preliminary injunction will not disserve the public interest.” Canal Authority v. Callaway, 489 F.2d 567, 572 (5th Cir. 1974).

The planned bypass highway at the center of this controversy is a 17.6-mile segment of a four-lane, limited-access interstate roadway designed to alleviate traffic congestion in the Shreveport area. The route adopted by the Secretary requires a 10,225-foot bridge over Cross Lake. This lake serves as the main water supply for the City of Shreveport and also constitutes a valuable public recreational area. •

LES mounted a four-pronged environmental attack on the 1-220 bridging of Cross Lake. First, the proposed construction of the highway violates section 4(f) of the Department of Transportation Act because Secretary Brinegar could not reasonably have found that there were no prudent, feasible alternatives or that all possible planning had been done to minimize harm, and his determinations that both prerequisites existed were arbitrary and capricious. Second, the construction of the highway does not comply with the National Environmental Policy Act 3 because full disclosure was not made and the environmental impact statement was insufficient. Third, 23 U.S.C. § 128(a) and recent administrative *932 regulations require additional public hearings before construction on this highway may proceed. Finally, the highway violates 23 U.S.C. § 134 since it is not based on a continuing comprehensive transportation planning process.

Without intending to intimate any view as to the last three issues raised, we conclude that the significance of the first issue to the future history of this litigation warrants discussion now. Under section 4(f) the Secretary of Transportation is required not to approve a highway project which uses a recreational area unless (1) there is no “feasible and prudent alternative,” and then only if (2) the project “includes all possible planning to minimize harm.” 4

The administrative record before the Secretary at the time of his decision was the most pertinent material before the district court. That record discloses that west of the Red River five alternatives to the chosen route were considered. The Secretary rejected all of these alternatives, finding them to be feasible but not prudent.

The bypass location around Cross Lake which LES claims should not have been rejected was alternative “C.” The final 4(f) statement considered by Secretary Brinegar noted the following adverse effects in rejecting alternative route “C”: It would present a visual obstruction to numerous inhabitants along the eastern perimeter of the Lake. It would require traversing two small pockets of the Lake (this intrusion was found to have negligible impact on the function and uses of the Lake). Approximately 160 family and individual household units, 24 businesses, and 1 nonprofit organization would be displaced. Right-of-way costs were estimated at approximately 18,000,-000 dollars. 5 The route traverses land which would be available for development. 6

On the positive side, the final statement found that alternative “C” would be less damaging to wildlife than the route chosen, and that part of its path would be through an oil field and through low lands subject to occasional flooding, having less potential for future development than some of the property to be taken by the route selected. Adequate replacement housing would be available in the project area. The cost of this route was estimated to be 33,600,-000 dollars as compared to an estimated cost for the route adopted of 36,110,000 dollars.

The statement concludes that property damages, displacements and resulting high right-of-way costs indicated the alternative was not prudent. The Secretary did not mention that he has studied the feasibility of utilizing for alternate “C” the Red River bridge as it is now planned and a substantial portion of the right-of-way already acquired on the west side of the Red River, nor has he studied means of minimizing residential displacements along the east end of Cross Lake by moving the alignment south and east of the line proposed after crossing City Pocket and by rejoining the approved route north of Jefferson-Page Road. Both alterations appear to offer maximum use of already acquired right-of-way and minimum displacements.

In Citizens to Preserve Overton Park, Inc. v. Volpe, 401 U.S. 402, 91 S.Ct. 814, 28 L.Ed.2d 136 (1971), the Supreme Court has fixed the meaning of the pivotal term “prudent” for purposes of judicial review of the Secretary’s action.

*933 Congress clearly did not intend that costs and disruption of the community were to be ignored by the Secretary. But the very existence of the statutes indicates that protection of parkland was to be given paramount importance. The few green havens that are public parks were not to be lost unless there were truly unusual factors present in a particular case or the cost of community disruption resulting from alternative routes reached extraordinary magnitudes. If the statutes are to have any meaning, the Secretary cannot approve the destruction of parkland unless he finds the alternative routes present unique problems.

401 U.S. at 412, 413, 91 S.Ct. at 821, 822 (emphasis added). 7

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
524 F.2d 930, 6 Envtl. L. Rep. (Envtl. Law Inst.) 20093, 1975 U.S. App. LEXIS 11728, Counsel Stack Legal Research, https://law.counselstack.com/opinion/louisiana-environmental-society-inc-v-william-t-coleman-secretary-ca5-1975.