Louisiana Capital Partners, L.L.C. v. Thomson General Contractors, Inc.

103 So. 3d 414, 2012 WL 3025128, 2012 La. App. LEXIS 976
CourtLouisiana Court of Appeal
DecidedJuly 25, 2012
DocketNos. 47,178-CA, 47,179-CA
StatusPublished

This text of 103 So. 3d 414 (Louisiana Capital Partners, L.L.C. v. Thomson General Contractors, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Louisiana Capital Partners, L.L.C. v. Thomson General Contractors, Inc., 103 So. 3d 414, 2012 WL 3025128, 2012 La. App. LEXIS 976 (La. Ct. App. 2012).

Opinion

WILLIAMS, J.

_JjThe plaintiff, Louisiana Capital Partners, L.L.C., and third-party defendant, Mark Goff, appeal a judgment in favor of the defendant/plaintiff-in-reconvention, Thomson General Contractors, Inc. The trial court awarded the defendant damages of $99,816.06 and recognized a lien in favor of the defendant for the judgment amount. For the following reasons, we affirm.

FACTS

Louisiana Capital Partners, L.L.C. (“LCP”) is the owner of a building located at 6540 Line Avenue in Shreveport. LCP has two members with equal ownership interests, Mark Goff (“Goff’) and Walter Ledig (“Ledig”). In February 2007, LCP submitted a proposal to the federal government to lease the premises to the U.S. Department of Agriculture (“USDA”) for use as office space. Goff then discussed the project with John R. Thomson, Jr. (“Thomson”), a construction contractor and [416]*416owner of Thomson General Contractors, Inc. (“TGC”). In a letter dated October 4, 2007, Thomson wrote to Goff and Ledig that TGC offered to “furnish all material, labor, equipment, subcontractors, permits, insurance, supervision and construction management for bringing your project on Line Ave. to the shell stage for the sum of all cost (material, labor, ... overhead, etc.) plus a fee of 4%.” Under Thomson’s signature is the handwritten word “accepted” and the signature of Mark Goff.

A short time later, TGC began demolition of the interior of the building. This work included placing chutes outside of the windows and trash dumpsters in front of the building. On December 21, 2007, TGC ^submitted its first invoice to LCP in the amount of $84,361.07, which included the cost of demolition and the contractual contractor’s fee through that date. TGC issued a second invoice on March 24, 2008, in the amount of $47,909.74, for demolition and the contractor’s fee. That same month, Goff made a payment by check to TGC in the amount of $20,000, drawn on the escrow account of LCP’s counsel, James Bodenheimer. On September 10, 2008, TGC submitted a final invoice in the amount of $119,816.06, the total cost for all of the work performed at the site. When payment was not received, TGC filed a lien against the property that was recorded in the Caddo Parish mortgage records.

Subsequently, the plaintiff, LCP, filed a petition for damages against the defendant, TGC, alleging unauthorized demolition. LCP also filed a rule to cancel TGC’s lien filed against the property. TGC then filed a reconventional demand against LCP and a third party demand against Goff and Ledig, seeking recovery of $99,816.60, the net amount due after a credit for the prior payment, and enforcement of the lien. Ledig was later dismissed from the action.

After a trial, the court issued written reasons for judgment, finding that a valid contract existed and that the demolition work performed by TGC was authorized. The court noted the evidence showing that Goff and Ledig were aware of the demolition work being done, including the contemporaneous emails, field reports and the lack of written response to TGC’s invoices by the principals of LCP. The trial court rendered judgment ordering LCP and Goff, in solido, to pay damages of $99,816.06 for ^demolition work performed and recognizing the lien in favor of TGC. LCP and Goff filed a motion for new trial, which was denied. The appellants, LCP and Goff, appeal the judgment.

DISCUSSION

The appellants contend the trial court erred in awarding damages to the defendant for demolition work. Appellants argue that they do not owe payment because the defendant failed to show that they entered a contract with or authorized defendant to perform demolition in the building.

A contract is an agreement by two or more parties whereby obligations are created, modified or extinguished. LSA-C.C. art. 1906. A contract is formed by consent of the parties established through offer and acceptance, which may be made orally, in writing or by action or inaction that under the circumstances indicates consent. LSA-C.C. art. 1927. The determination of the existence of a contract is a finding of fact not to be disturbed unless clearly wrong. Dubois Construction Co. v. Moncla Construction Co., Inc., 39,794 (La.App.2d Cir.6/29/05), 907 So.2d 855.

In the present case, Goff testified that his occupation was “health care” and that he was an equal co-owner of LCP with Walter Ledig. Goff stated that LCP origi[417]*417nally bought the building on Line Avenue for use as a health care facility, but then that project was halted for lack of funds. Goff testified that Ledig later raised the idea of leasing the building to the federal government for office space. Goff stated that LCP submitted a proposal to the government, which agreed in September 2007 to lease the building after extensive renovations were made. Goff testified that he then spoke with RThomson about the project and showed him LCP’s proposal, the government’s requirements and LCP’s estimate of construction costs. Goff stated that he understood the October 2007 letter from Thomson as just a statement that the price of shell work would be cost plus 4% and the price of tenant improvements would be cost plus 5%. He testified that the government required the letter to show that LCP had a contractor and an architect “available” to do the project. Goff stated that he informed Thomson on several occasions that LCP would not be able to pay TGC anything until funding was obtained from a bank. Goff acknowledged that in November 2007 he was informed by Ledig that TGC workers were taking down some ceilings and walls in the building. Goff testified that he then telephoned Thomson and told him to stop any demolition because LCP did not have funding or a final contract with the government. Goff stated that he was told by Ledig about the TGC invoices submitted in December 2007 and March 2008. Goff stated that after each invoice, he phoned Thomson and told him to stop the demolition because LCP did not have any funding for such work.

During his testimony, Goff explained that the building’s lower floor was below ground, the upper floor was at ground level and that the project involved the top floor. Goff asserted that although he visited the building at least two times between October 2007 and the date LCP filed suit, he did not enter the top floor. Goff testified that on his first visit, he went to the rear of the building to pick up a metal shed that had been loaded onto a trailer by TGC workers. On the second visit, he entered the bottom floor to | slook at the electrical circuit box and spoke to some TGC workers who were present. Goff stated that he had given TGC permission to use the building to make cabinets and that he did not see any indication of demolition activity on either of his visits. Goff testified that in March 2008, Thomson said that he was short on cash and needed to borrow money. Goff stated that he agreed to loan $20,000 to Thomson, who did not mention that the money would be a partial payment for the amount owed for demolition. Goff stated that his attorney prepared a promissory note, but could not recall if Thomson ever signed the original note.

Walter Ledig testified that he became co-owner of LCP in 2006 and told Goff about the possibility of leasing the building on Line Avenue to the federal government for office space. Ledig stated that he signed the February 2007 proposal submitted to the government estimating the total project cost as approximately $2 million.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dubois Const. Co. v. Moncla Const. Co.
907 So. 2d 855 (Louisiana Court of Appeal, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
103 So. 3d 414, 2012 WL 3025128, 2012 La. App. LEXIS 976, Counsel Stack Legal Research, https://law.counselstack.com/opinion/louisiana-capital-partners-llc-v-thomson-general-contractors-inc-lactapp-2012.