Louis Richardson Ranch, Inc. v. Gibson

105 P.2d 143, 40 Cal. App. 2d 520, 1940 Cal. App. LEXIS 138
CourtCalifornia Court of Appeal
DecidedAugust 29, 1940
DocketCiv. 11303
StatusPublished
Cited by1 cases

This text of 105 P.2d 143 (Louis Richardson Ranch, Inc. v. Gibson) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Louis Richardson Ranch, Inc. v. Gibson, 105 P.2d 143, 40 Cal. App. 2d 520, 1940 Cal. App. LEXIS 138 (Cal. Ct. App. 1940).

Opinion

KNIGHT, J.

Plaintiff' brought this action to establish a forfeiture of an oil and gas lease for non-compliance with provisions of the lease requiring that drilling of a well be commenced by a certain date and thereafter prosecuted with due diligence. From a judgment for plaintiff, defendants appeal. They contend that grounds for forfeiture did not exist and that the lease is still in effect.

The lease was executed on May 6, 1936, by plaintiff Louis Richardson Ranch, Inc., as lessor, and defendant Frank J. Gibson as lessee, and covered one hundred acres in Ventura County. Gibson was also given a lease on adjoining property owned by Meda K. Richardson. On July 20, 1936, both leases were assigned to defendant George Duty, Gibson re *522 taining a four per cent royalty interest. Defendant Sherrod had introduced Gibson to the lessor and thereafter worked for Duty, but was not shown to have any interest in the lease.

The lease provided that it should terminate unless drilling was commenced within ninety days from its date, provided that if commenced within thirty days, the sum of $500 paid upon execution of the lease should be returned to the lessee, and if not commenced within thirty days, but within sixty, $250 of this sum should be repaid. Drilling was not commenced within ninety days, but on August 2cl an extension was granted to August 9th. Subsequently time was extended to August 16th, and thereafter to - August 21st. At the time of granting the extension to August 21st, the lessor agreed to extend the time to September 3d if Duty would release the south forty acres of the lease, and the south forty acres of the Meda K. Richardson lease, but Duty did not avail himself of this offer. Defendant Duty represented to Mr. Snyder, president and attorney for plaintiff, that his delay was due to the fact that work was being done on his drilling equipment at Long Beach.

Actual drilling commenced about midnight on August 20th, but the lessor contends that it was not prosecuted with due diligence in that the derrick was not wired for electric lights and therefore continuous drilling could not be maintained. On September 5th, the board of directors of plaintiff corporation held a meeting upon the property, and, according to the testimony of Mr. Snyder, president of plaintiff, he informed the man in charge for defendant Duty that unless there was a showing of diligence it might be necessary to cancel the lease. Snyder suggested that since there had not been due diligence, Duty should put up a $10,000 bond to assure performance.

On September 10th, Snyder wrote to Gibson and Duty that there had been a breach of the obligation of diligent performance, and any further work would be done at their peril; that upon his return from his vacation he would ask the board for cancellation of the lease. No reply was received to this letter. On September 26th, Snyder wrote to Gibson and Duty that on the preceding day the board had cancelled the lease. Action was filed on September 29th.

The court found that actual drilling had commenced on August 21st, within the last extension, but that it had not been commenced in good faith, in that Duty did not have the finan *523 cial ability to carry on and complete the well, and had obtained the extensions by falsely representing his financial ability. It further found that drilling had not been carried on with due diligence, or with any diligence, and that on or about September 6, 1936, defendant ceased operations without sufficient cause or reason.

Defendants' contention is, in effect, that the evidence is insufficient to support the findings which are adverse to them. Defendants further contend that under the lease the plaintiff was required to give notice allowing time to remedy any breach of the obligation of due diligence before declaring a forfeiture.

Defendants take the position that diligent operation did not require continuous drilling; that it would have delayed further the commencement of drilling if the derrick had been wired for night work. Defendants point to the fact that between August 21 and September 5, 1936, the well was drilled to a depth of between 280 and 290 feet. During that period the conductor pipe developed a leak three times, and it had been necessary to stop drilling and recement it, according to testimony on behalf of defendants. The cementing of the first two repair jobs, permitted to set over night, had not held, and on September 5th, when the board of directors came to the lease, it had been recemented a third time. The intent was to let it set several days before starting again. Defendants also offered evidence of other mechanical trouble due to a twist-off.

As a justification for not resuming operations after the shutdown of September 5th, defendants rely on the statements of the board of directors when they visited the lease on September 5th and the letter of September 10th, in which Snyder informed the defendants that work thereafter done was at their peril, and that on his return from his vacation he would ask the board to cancel the lease for breach of the obligations of the lease in respect to drilling. Drilling was not- thereafter resumed." The position of defendants is that there was no lack of due diligence prior to September 5th, and that they were not required to continue operations after that date in order to hold the lease, in view of plaintiff’s notice that it proposed to cancel. (Sec. 1511, Civ. Code.) The derrick and drilling equipment were still on the prop *524 erty at the time of trial. Defendants’ contention is that the lease is still in effect.

The court found, as noted above, that drilling was not commenced in good faith and that Duty did not have financial ability to carry on and complete a well. A number of workmen employed by Duty on the well were not paid in full until after they had filed claims with the labor commissioner. Payments of wages were made as late as December. Mr. Taylor, who furnished water from his pump on the Meda K. Richardson property to Duty, was not paid until October 31st, after he had filed a claim with the labor commissioner. Mr. Boswell, who supplied mud used in drilling the well at a charge of $218, received his last payment in January, 1937.

Defendant Duty testified that the derrick had cost $2,500 and that he owed $1200 on it at the time of trial. His drilling equipment, except for a few small tools, was rented on an unwritten contract to pay $50 a day rent from oil produced. From Duty's own testimony the trial court was clearly warranted in concluding that he was without adequate means to finance drilling of an oil well with due diligence.

The theory of plaintiff was that Duty was deliberately ‘ ‘ stalling ’ ’, awaiting the outcome of a well being drilled about a mile distant by the Honolulu Oil Co. If that well was a success, he would have no difficulty financing his well. If the Honolulu well proved dry, he could surrender the lease under a provision giving such right at any time.

Plaintiff lessor, on the other hand, was anxious that drilling proceed with dispatch. It wished a test of its land to be made without regard to the outcome of the Honolulu well. It had other offers to lease. If Duty was not going forward diligently, it wished to accept one of these offers, which likely would be withdrawn if the Honolulu well proved dry.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Danker v. Lee
291 P.2d 73 (California Court of Appeal, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
105 P.2d 143, 40 Cal. App. 2d 520, 1940 Cal. App. LEXIS 138, Counsel Stack Legal Research, https://law.counselstack.com/opinion/louis-richardson-ranch-inc-v-gibson-calctapp-1940.