Louis R. Tucker v. Calmar Steamship Corporation v. Jarka Corp. Of Baltimore, Third-Party

457 F.2d 440, 1972 U.S. App. LEXIS 10664, 1972 A.M.C. 1159
CourtCourt of Appeals for the Third Circuit
DecidedMarch 17, 1972
Docket71-1634
StatusPublished
Cited by22 cases

This text of 457 F.2d 440 (Louis R. Tucker v. Calmar Steamship Corporation v. Jarka Corp. Of Baltimore, Third-Party) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Louis R. Tucker v. Calmar Steamship Corporation v. Jarka Corp. Of Baltimore, Third-Party, 457 F.2d 440, 1972 U.S. App. LEXIS 10664, 1972 A.M.C. 1159 (3d Cir. 1972).

Opinion

SOBELOFF, Senior Circuit Judge:

Appellant Louis Tucker, a longshoreman, sought damages from the Calmar Steamship Corporation, owner of the S.S. PENNMAR, for injuries he sustained while assisting in transferring a load of steel pipe to the vessel’s cargo hold from a railroad gondola car stationed on an adjacent pier. Tucker alleged that the accident was caused by the ship’s unseaworthiness and the Calmar Corporation’s negligence. The District Judge found for the defendant on both grounds.

*442 The only question before us is the correctness of the District Judge’s ultimate decision that Tucker failed to prove unseaworthiness or negligence. 1 We conclude that the District Court’s finding that the ship was seaworthy is clearly erroneous and we therefore reverse. 2

I

At approximately 9 p. m. on the evening of March 5,1966, appellant was working on a railroad gondola car loaded with steel pipe. His duty was to secure a draft of pipe for transfer to the ship’s cargo hold by fastening a metal strap around one end of the draft. A co-worker would similarly secure the other end of the draft. A draft ordinarily contains about 15 to 20 steel pipes. The pipe involved in the accident was 4 to 6 inches in diameter and about 30 feet long. To get the straps around both ends, one end of the draft would be “broken-out” — lifted by a sling — so that the two longshoremen could reach under the pipe and fasten the straps at each end. Tucker, working on the end not raised in the breaking-out operation, was seriously injured when a pipe slipped out of the sling and rolled down on him, throwing him from the railroad ear onto the pier.

At the time of the accident, the breaking-out was accomplished by the use of a house fall. The house fall, pictured in Figure 1, is a cable running from the

ship’s port winch to a pulley attached to a post on the roof of the pier’s warehouse and then down to a hook to which the sling is attached. A load on the *443 sling at the end of the fall is raised by winding the cable onto the winch. On the occasion with which we are concerned, the pipe slipped out of the sling because the house fall had lifted the sling holding one end of the draft too high. Whereas the sling is normally lifted only 3 or 4 feet in the breaking-out procedure, in this instance it was lifted nearly 6 feet. At that elevation and angle, the sling could not hold the draft and one pipe slipped out and descended on Tucker.

Joseph Haskins, a man experienced in breaking-out pipe where a house fall is in use, was the winch operator at the time of the accident. Called as a witness by the shipping company, he explained how the sling came to be lifted too high. He testified that the tension on the house fall caused by the weight of the load on the sling tended to pull the ship towards the pier. 3 When the load was released, the tension on the cable slackened and the ship returned to its original position vis-a-vis the dock. On the night of the accident, as often occurs, both the fore and aft winches of the ship were loading cargo. Haskins was operating the forward winch next to the #1 hold; another operator was working a winch to the rear of the ship by the #3 hold. When both winches were lifting a load and one released the tension on its house fall before the other, the ship would start to return to its original position and this movement away from the pier would pull the other, taut house fall, causing the load on the end of the still taut line to be lifted higher than anticipated. Haskins explained that the winch at the #3 hold had just released its load and the ship had begun to move away from the dock. Consequently, Haskins’ house fall raised the draft at the end of his line higher than desired. Haskins’ explanation of the cause of the accident was not disputed and was accepted by the District Judge.

Because of the recognized proclivity of a ship to move away from the pier when one of two operating house falls is relaxed, resulting in a variation in the height of the load on the other, still taut fall, the winch operator is required to make quick compensatory maneuvers to avoid an accident of the kind which injured plaintiff. To correct for the ship’s motion and keep the load at the proper height, the winch operator must, with exact timing, relax the tension of his fall as the ship moves away from the dock. Haskins testified that in the darkness of night a winch operator could not see the movement of the sling so as to make the necessary fine correction, but had to rely on a deckman standing on the ship to relay signals from the longshoremen breaking-out the pipe. Haskins said on cross-examination that, although a deck-man was present during daylight, from his experience he did not rely ;on the deckman when he could see the breaking-out operation for himself; but he always needed a deckman at night. The lighting on the night of the accident was described as “very poor” by witnesses for both parties, and at the time of the accident the longshoremen were searching for additional lights. While Haskins said the lighting that night was adequate for him to see the deckman, it is noteworthy that no one contradicted Haskins’ further assertion that at night, even after the lighting was somewhat improved, he could not see the movement of the sling.

Haskins in his testimony took pains to distinguish between day and night operations with a house fall. He emphasized that in daylight, by looking at the gondola car, rather than at the deckman, he could better and more speedily compensate for the motion of the ship.

[I]f I’m looking at the load, at the men working at the time [the ship moves] I can just slack off a little bit and give it a little more slack to extend, but if *444 I’m watching the deckman, I can’t do this. (Transcript p. 136).
In the daytime mostly, we can usually see those things happening that way and you have more chance of slacking away and extending, giving it more fall so that it won’t pull the load any at all. (Transcript p. 138).-
[You have less accidents because] when you take a signal from the deck-man, you’re usually a few seconds late but if you’re getting it direct — if you’re looking directly at a situation, you are more accurate. (Transcript p. 159).

By ignoring the deckman in daylight and relying on his own observation Haskins said he had avoided several accidents by reason of his quicker reaction time in response to the ship’s motion. Several times earlier on the day of the accident, during the daylight hours, Haskins said he was readily able to correct for the ship’s movement.

There was uncontroverted testimony that other methods of breaking-out the pipe were available, namely the use of the ship’s boom or a land-based heister. Both alternative methods were described by Haskins as safer and steadier than the house fall method because only the use of the house fall causes the ship to move towards the pier when the fall is carrying a heavy load. In Haskins’ view, if one of the other means had been used that night, rather than the house fall, the accident would not have occurred.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Janes v. Alaska Railbelt Marine, LLC
309 P.3d 867 (Alaska Supreme Court, 2013)
Signal Intl LLC
Fifth Circuit, 2009
Torres Vazquez v. Commercial Union Insurance
367 F. Supp. 2d 231 (D. Puerto Rico, 2005)
Pappas v. Potomac Party
Fourth Circuit, 2000
Piper Aircraft Corporation v. Wag-Aero, Inc.
741 F.2d 925 (Seventh Circuit, 1984)
Cunningham v. Rendezvous, Inc.
699 F.2d 676 (Fourth Circuit, 1983)
Portier v. Texaco, Inc.
426 So. 2d 623 (Louisiana Court of Appeal, 1982)
United States v. Paducah Towing Co.
692 F.2d 412 (Sixth Circuit, 1982)
Cooper v. Keyes Offshore, Inc.
421 So. 2d 385 (Louisiana Court of Appeal, 1982)
Sacillotto v. National Shipping Corp.
381 F. Supp. 558 (D. Maryland, 1974)
George Garrett v. Enso Gutzeit O/y
491 F.2d 228 (Fourth Circuit, 1974)
Williams v. Nitta Kisen K.K. Ltd.
365 F. Supp. 265 (S.D. Texas, 1973)
Tucker v. Calmar Steamship Corporation
356 F. Supp. 709 (D. Maryland, 1973)
Jones v. United States
342 F. Supp. 392 (E.D. Virginia, 1972)
Scoggins v. Sea-Land Service, Inc.
340 F. Supp. 1100 (E.D. Virginia, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
457 F.2d 440, 1972 U.S. App. LEXIS 10664, 1972 A.M.C. 1159, Counsel Stack Legal Research, https://law.counselstack.com/opinion/louis-r-tucker-v-calmar-steamship-corporation-v-jarka-corp-of-ca3-1972.