Louis M. McMaster Inc. v. Pennsbury Village Company and Klingbeil Company, A/K/A Klingbeil, Haddox & Company

460 F.2d 520, 1972 U.S. App. LEXIS 9710
CourtCourt of Appeals for the Third Circuit
DecidedMay 5, 1972
Docket71-1347
StatusPublished

This text of 460 F.2d 520 (Louis M. McMaster Inc. v. Pennsbury Village Company and Klingbeil Company, A/K/A Klingbeil, Haddox & Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Louis M. McMaster Inc. v. Pennsbury Village Company and Klingbeil Company, A/K/A Klingbeil, Haddox & Company, 460 F.2d 520, 1972 U.S. App. LEXIS 9710 (3d Cir. 1972).

Opinion

OPINION OF THE COURT

SEITZ, Chief Judge.

Plaintiff Louis M. McMaster, Inc., agreed in writing with defendant Pennsbury Village Company (“Pennsbury”) as owner and defendant Klingbeil Company (“Klingbeil”) as agent to perform all necessary grading with regard to defendants’ proposed Pennsbury Village project. Plaintiff was to provide all machinery for the job and to employ qualified operators. Also, plaintiff was to supervise its work. Compensation was to be on an hourly basis pursuant to a negotiated schedule of rates applicable to specific categories of equipment, op *522 erators and supporting personnel. Defendant was to pay plaintiff according to monthly invoices, with ten per cent of each billing being retained until all excavation work was completed to defendants’ satisfaction. It is undisputed that later, on October 29, 1964, the parties deleted this 10% provision and initialed the modification. Thereafter, each invoice was payable in full upon receipt.

Plaintiff terminated its work under the contract in March, 1966. At the time plaintiff’s invoice for that month was not prepared. It was mailed to defendants in April and defendants refused to pay the balance indicated as owing. Plaintiff then filed this action. In their answer to plaintiff’s complaint defendants admitted liability to plaintiff for the amount billed. But they contended that because plaintiff failed to perform the obligations of his contract in a workmanlike manner, damage totalling $55,735.24 had resulted with regard to certain living units being constructed as part of the overall project. Defendants counterclaimed against plaintiff to recover this amount. Trial was held before the district judge without a jury. At the close of the evidence the court awarded plaintiff $3,295.32 on its complaint against defendants and awarded defendants $55,735.24 on their counterclaim against plaintiff. Plaintiff appeals the award under the counterclaim.

At trial it was undisputed that defendants had incurred expenses in the amount of their counterclaim in repairing the damage sustained by various of their project buildings. Likewise, it was conceded by plaintiff that such damage had resulted from improper excavation work. The sole issue was plaintiff’s responsibility for the work as performed and whether, pursuant to its contract with defendants, plaintiff was required to indemnify defendants for their loss.

Plaintiff concedes that if its ultimate undertaking with defendants obligated it, as an independent contractor, to supervise the excavation work then plaintiff is liable to defendants for amounts expended by them to repair the damaged structures. The contract provided that plaintiff was to “give . . . personal supervision to the Work.” “Work” is defined by section (2) of the contract:

“The Contractor agrees, as his sole cost and expenses, to perform with speed and diligence, all of the labor and services, and to furnish all the materials, plant and equipment necessary to complete in a good, substantial, workmanlike and approved manner in accordance with the terms and provisions of the Agreement, and of the instruction of the Owner made in accordance with the Agreement all Excavation Work as per plans prepared by Burgess & Niple Ltd., Engineers. . . . ”

As written this provision would appear to make patent that plaintiff contracted to accept full supervisory responsibility for “all [ejxcavation [w]ork.” The only provision of the contract which plaintiff points to as indicating a contrary conclusion is the last paragraph of section 7 which provides:

“Owner agrees to pay an additional Five Dollars and Sixty Cents ($5.60) per hour for the Contractor’s foreman and/or Three Dollars and Thirty-Six Cents ($3.36) per hour for the Contractor’s grease-and-maintenance men when these men are working for the Owner, provided such work has been authorized by the Job Superintendent. (Italics plaintiff’s.)

Plaintiff contends that the italicized language of this paragraph demonstrates that defendants reserved ultimate control over the operators and other workers supplied by plaintiff. We cannot accept this contention. We recognize that plaintiff’s invoices, paid by defendants, evidence that defendants in fact did utilize directly the services of plaintiff’s grease-and-maintenance men on occasion. However, nothing in the record permits the conclusion that these men were used in connection with the excavation work. Rather, they well could have *523 been employed to service equipment used for other construction aspects of defendants’ project. Apparently, no foremen were “hired” by defendants under this paragraph. Nevertheless, we do not think the fact that the contract provides for the hiring of foremen by defendants necessarily compels the conclusion that defendants intended to supervise excavation. Foremen, too, could have been hired by defendants to supervise the crews of grease-and-maintenance men assigned to service equipment used other than for excavation. Absent proof that the grease-and-maintenance men billed to defendants under this paragraph in fact were not used exclusively for non-excavation purposes, we are unwilling to relieve plaintiff of its responsibility under the contract on the basis of this single paragraph.

In this regard it is noted that the written contract for the most part was a standardized printed agreement. Typewritten insertions interspersed throughout its length tailored the agreement to plaintiff’s particular job. Plaintiff maintains that the typewritten portions should be emphasized when interpreting the contract. However, the contract in its entirety is internally consistent. In the absence of ambiguity such disproportionate emphasis would be improper. Cf. Unit Vending Corp. v. Lacas, 410 Pa. 614, 190 A.2d 298, 300 (1963).

An alternative position of plaintiff is that, regardless of its responsibility under the original written contract, oral modifications thereto, agreed upon by the parties simultaneously with deletion of the retainage provision, effectively relieved plaintiff from all supervisory duties with regard to excavation. According to plaintiff, oral modifications negotiated October 29, 1964, altered the existing contract to such an extent that, thereafter, it was nothing more than an equipment rental agreement. Typically, plaintiff could not be held responsible for the faulty excavation under such an arrangement. See McCollum v. Smith, 339 F.2d 348, 351 (9th Cir. 1964). The short answer to plaintiff’s contention, however, is that the written contract fails to evidence any material modifications other than with regard to the retainage provision.

If the oral modifications suggested by plaintiff in fact were negotiated they would be inconsistent with the present contract as reasonably interpreted. Neither party has acknowledged any possible problem with the parol evidence rule. Application of that principle would seem to exclude altogether plaintiff’s evidence of any contemporaneous oral understanding with defendants modifying plaintiff’s responsibility under the contract. However, we need not decide this appeal on that basis. The only evidence presented concerning such an oral understanding was the testimony of plaintiff’s president.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Unit Vending Corp. v. Lacas
190 A.2d 298 (Supreme Court of Pennsylvania, 1963)
Siidekum v. Animal Rescue League of Pittsburgh
45 A.2d 59 (Supreme Court of Pennsylvania, 1945)

Cite This Page — Counsel Stack

Bluebook (online)
460 F.2d 520, 1972 U.S. App. LEXIS 9710, Counsel Stack Legal Research, https://law.counselstack.com/opinion/louis-m-mcmaster-inc-v-pennsbury-village-company-and-klingbeil-company-ca3-1972.