Louis and Stacey Pyle v. St. Joseph, LLC

Louisiana Court of Appeal·Decided June 14, 2022·No. 2021CA1003·Unknown

Opinion

NOT DESIGNATED FOR PUBLICATION STATE OF LOUISIANA

COURT OF APPEAL

FIRST CIRCUIT

2021 CA 1003

LOUIS AND STACEY PYLE

VERSUS

ST. JOSEPH, LLC

JUN 1 ·4 2022'

Judgment Rendered:- - - - - -, 2022

********

Appealed from the 22"d Judicial District Court In and for the Parish of St. Tammany State of Louisiana

Case No. 2019-13329

The Honorable August J. Hand, Judge Presiding

********

Laurie M. Pennison Counsel for Plaintiffs/Appellees Mandeville, Louisiana Louis and Stacey Pyle

Ralph S. Whalen, Jr. Counsel for Defendant/Appellant New Orleans, Louisiana St. Joseph, LLC

********

LANIER, J.

The defendant, St. Joseph, LLC (St. Joseph), appeals a partial summary judgment of the Twenty-Second Judicial District Court granted in favor of the plaintiffs, Louis and Stacey Pyle. For the following reasons, we reverse and remand.

FACTS AND PROCEDURAL HISTORY On May 30, 2018, the Pyles and St. Joseph entered into a contract for the construction of a home in Abita Springs, Louisiana. In the contract, St. Joseph agreed to build a private residence for the Pyles. Article 3, subpart 3.1 of the contract provided that the Pyles would pay St. Joseph the sum of $313,310.82, subject to additions and deductions provided for in the contract documents, 1 plus a contractor fee of$34,244.00. The total contract price was $347,554.82.

Subpart 3.2 of the contract specified that the contract price was based on allowances for materials. Subpart 7.1 stated that when the costs of items were more than or less than the allowances, the contract sum would be adjusted accordingly by a written change order prior to ordering and installing the items. During construction, the Pyles requested a change order via email, and a price quote was submitted by St. Joseph. Due to this change and other changes, the Pyles contend that they paid $41, 106.62 in addition to the total contract sum.

Upon the house's completion but before a certificate of occupancy was granted, St. Joseph invoiced the Pyles for $111,345.91, and filed a statement of

1 Subpart 6.1 of the contract lists the contract documents as:

this Agreement, Drawings, Specifications, Selection Sheets, Estimated Cost Analysis, addenda issued prior to the execution of this Agreement, other documents listed in this Agreement and only written modifications issued after execution of this Agreement which have been signed or initialed by both the [Pyles] and [St. Joseph.] There are no agreements between the parties other than the Contract Documents and no oral agreements exist between the parties.

lien and privilege in the conveyance records of St. Tammany Parish on May 16, 2019. 2 A copy of the lien was forwarded to the Pyles on June 25, 2019. St. Joseph explained that it had incurred additional labor costs during the construction, and that the contract was a "cost-plus" contract, entitling St. Joseph to recover overages attributable to the increases in the cost of construction. The Pyles, however, claimed that the contract was a "lump sum" contract with a fixed amount, which they paid. The Pyles claimed that the additional $41,106.62 they paid for allowance changes was not included in the invoice submitted by St. Joseph.

The Pyles filed a petition for declaratory judgment and breach of contract/breach of warranty pursuant to Louisiana's New Home Warranty Act (NHWA), La. R.S. 9:3141 et seq., on July 3, 2019. St. Joseph filed an answer and reconventional demand on October 14, 2019, in which it claimed: the contract was a cost-plus contract made evident by the contract's language; the Pyles had requested numerous revisions and additions, which significantly modified the cost and scope of the entire project; the Pyles had breached the contract in bad faith by refusing to pay the outstanding balance; that St. Joseph relied on the Pyles' representations regarding the design documents to its detriment; and that the Pyles were unjustly enriched by the work done by St. Joseph.

The Pyles filed a motion for partial summary judgment on April 13, 2020.

In their supporting memorandum, the Pyles asserted that the contract was a lump sum contract; therefore, St. Joseph could not charge additional costs, and the lien St. Joseph filed should be cancelled. The Pyles also requested all court costs and attorney fees associated with removal of the lien be paid by St. Joseph.

In its review of the motion for partial summary judgment, the trial court found the contract to be a lump sum contract. In a judgment signed November 17,

2 The Pyles' petition and the statement oflien and privilege filed by St. Joseph show the total invoiced amount as $122,756.11.

2020, the trial court granted the Pyles' motion for partial summary judgment, ordered the lien filed by St. Joseph to be cancelled, and awarded costs and attorney fees to the Pyles. 3 St. Joseph timely appealed. 4

ASSIGNMENTS OF ERROR

St Joseph raises the following assignments of error:

1. The trial court erred in granting a partial summary judgment where there were contested facts.

2. The trial court erred in holding the contract in question was a lump sum contract.

ST AND ARD OF REVIEW

The standard of review for the granting of a partial summary judgment is de novo. Spanish Lake Wildlife Refuge & Botanical Gardens, Inc. v. Parish of Ascension ex rel. Martinez, 2011-1882 (La. App. 1 Cir. 5/4/12), 2012WL1580760, *3 (unpublished), writ denied, 2012-1677 (La. 11/2/12), 99 So.3d 671. Summary judgments are favored by the courts as a procedure to secure a "just, speedy, and inexpensive determination." La. C.C.P. art. 966(A)(2). Summary judgment shall be granted "if the motion, memorandum, and supporting documents show that there is no genuine issue as to material fact and that the mover is entitled to judgment as a matter of law." La. C.C.P. art. 966(A)(3).

"[I]f the mover will not bear the burden of proof at trial on the issue that is

before the court ... , the mover's burden on the motion does not require him to 3 On December 16, 2020, St. Joseph liled an ex parte consent motion for designation of the judgment as final pursuant to La. C.C.P. art. 1915(B)(l). On December 18, 2020, the trial court signed an order designating the judgment as final pursuant to La. C.C.P. art. 1915(B)(l) and made the express determination that there was no just reason for delay. 4 A Show Cause Order was issued by this court in reference to the November 17, 2020 judgment on appeal because, although the judgment ordered the "Statement of Lien" filed by St. Joseph to be cancelled, the lien itself was not attached to the judgment, and because the attorney fee award was uncertain. On February 10, 2022, the record was supplemented with an amended judgment signed by the trial court on January 12, 2022, which attached the referenced lien and awarded a definite amount of attorney fees. Thus, on March 4, 2022, we maintained the appeal.

negate all essential elements of the adverse party's claim, action, or defense[.]" Id. Rather, the movant must "point out to the court the absence of factual support for one or more elements essential to the adverse party's claim, action, or defense." Id. Thereafter, if the adverse party fails to produce factual support sufficient to establish that he wi II be able to satisfy his evidentiary burden of proof at trial, there is no genuine issue of material fact. See Id.

DISCUSSION

Free access — add to your briefcase to read the full text and ask questions with AI

Louis and Stacey Pyle v. St. Joseph, LLC, (La. Ct. App. 2022).

Louis and Stacey Pyle v. St. Joseph, LLC (Louis and Stacey Pyle v. St. Joseph, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Revere v. Dolgencorp, Inc.
923 So. 2d 101 (Louisiana Court of Appeal, 2005)
Clovelly Oil Co. v. Midstates Petroleum Co.
112 So. 3d 187 (Supreme Court of Louisiana, 2013)