Loretta Tutein v. InSite Towers

572 F. App'x 107
CourtCourt of Appeals for the Third Circuit
DecidedJuly 10, 2014
Docket13-3869
StatusUnpublished
Cited by2 cases

This text of 572 F. App'x 107 (Loretta Tutein v. InSite Towers) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Loretta Tutein v. InSite Towers, 572 F. App'x 107 (3d Cir. 2014).

Opinion

OPINION

RENDELL, Circuit Judge:

Appellants, homeowners on St. Croix, sued Insite Towers, LLC (“Insite”) over its construction of a cellular transmission tower, and related personal injuries and property damage. Appellants have also sued the U.S.V.I. Department of Planning and Natural Resources (“DPNR”) for failing to abide by its own regulations in permitting the construction of the tower. The District Court dismissed the case because of Appellants’ failure to exhaust administrative remedies. For the reasons set forth below, we will affirm in part and reverse in part the judgment of the District Court.

I. Background

A. Facts

The facts of this case are essentially undisputed. On July 22, 2008, Puerto Rico Tower, Inc. (predecessor in interest to In-Site) applied for an Earth Change Permit from the DPNR to construct a 100-foot tall cellular transmission tower on a parcel of land on St. Croix designated as Plot Number 72. DPNR deemed that application completed on September 11, 2008, and issued the permit two weeks later. On October 7, 2008, InSite applied for a Building Permit to construct the cell tower and the permit was issued on October 29, 2008. (App. 125.)

In December 2008, before InSite began construction, DPNR issued a moratorium on the construction of cell towers in the Virgin Islands. During the moratorium, a new statute governing the construction of cell towers was enacted and DPNR drafted the accompanying regulations. The statute, 29 V.I.C. § 294a, was enacted on October 7, 2011 and the corresponding regulations, 29 V.I. A.D.C. § 1, were promulgated on December 28 of that year.

However, before the issuance of the regulations, on December 15, 2011 the Commissioner of the DPNR responded to a request from InSite to waive the moratorium and allow construction of the tower on Plot Number 72. The Commissioner granted the waiver and, in so doing, required InSite to comply with the terms of the then-pending new regulations, as well as to limit the tower to 75 feet.

InSite then formally filed for renewal of the Earth Change Permit and the Building Permit for Plot Number 72. On January 12, 2012, DPNR received InSite’s application and issued the permits the same day. In April 2012, InSite posted the permits along the boundary of Plot Number 72. Construction of the tower was completed soon thereafter. However, as of the date of the District Court héaring, it had not been activated.

Appellants brought suit, alleging that the manner in which DPNR granted In-Site the permits to construct the tower violated law and regulations, which required notice to homeowners and a hearing, and also constituted a procedural and substantive due process violation. Appellants also allege that the tower constitutes a (1) private nuisance, (2) public nuisance, (3) negligent infliction of emotional distress, (4) intentional infliction of emotional distress and (5) negligence per se. (App. 124.) They subsequently filed a motion for preliminary injunction, requesting the District Court order the tower be removed and enjoining activation. The motion was denied.

*110 B. District Court Opinion

InSite, joined by DPNR, then filed a motion to dismiss. InSite argued that Appellants had failed to exhaust their administrative remedies, by not appealing the DPNR decisions to the Virgin Islands Board of Land Use Appeals (“BLUA”). Appellants contended that they were excused from exhausting such remedies. The District Court noted that a plaintiff may be excused from completing administrative appeals where, inter alia, (1) the challenged agency action constitutes a clear and unambiguous violation of statutory and constitutional rights, or (2) where the administrative procedures are inadequate to prevent irreparable injury.

The District Court determined that the regulations accompanying this statute were not retroactively enforceable, and so, viewing the renewal to relate back to the original permit granted in 2008, held that certain claims concerned acts prior to December 28, 2011, the issue-date of the new regulations, and therefore lacked merit. Concerning claims after December 28, the Court determined that the new regulations did not require DPNR “to provide notice to the public or an opportunity to be heard regarding the renewal or reissuance of previously approved permits.” (App. 15.) Accordingly, the District Court concluded that no statutory violation had been shown. The Court similarly found that no clear constitutional violations had been shown sufficient to excuse Appellants from exhausting their administrative remedies.

Appellants also argued that the BLUA could not provide injunctive relief and so the administrative procedures were inadequate to prevent the irreparable injury suffered by plaintiffs. The District Court rejected this claim, finding that the BLUA can reverse or modify any order of the DPNR, such that an appeal to the BLUA was not clearly inadequate to prevent the alleged harm. The Court concluded that Appellants had not excused their failure to exhaust administrative remedies and so granted the motion to dismiss. Appellants now urge that the District Court erred in dismissing the case. Separately, Appel-lees maintain an alternative argument which was advanced before, but not addressed by the District Court, namely that Appellants’ claims are preempted by federal statute.

II. Standard of Review 1

When reviewing a dismissal for failure to state a claim, we review the decision de novo. Similar to the standard at the district court, we must accept all well-pleaded allegations as true and all favorable inferences that can be drawn from them. However, “[wjhen the District Court declines to grant an exception to the application of exhaustion principles, we review for abuse of discretion.” Harrow v. Prudential Ins. Co. of Am., 279 F.3d 244, 248 (3d Cir.2002).

III. Discussion

The nature of Appellants’ claims makes resolution of this issue a close call. On the one hand, they complain of DPNR’s failure to follow its own procedures. On the other hand, they attack InSite’s failure to provide adequate notice of construction, and, further, contend that whether or not the proper procedures were followed, they have nuisance and other related claims against InSite. Accordingly, this action appears to be a hybrid, some aspects of which are directed at the DPNR and cry out for agency exhaustion, while other as *111 pects stand on their own against a private party, InSite.

A. Claims Against InSite

We note initially that the administrative appeals process at the BLUA is geared towards the correction of agency action. That is, a BLUA appeal is only open to those aggrieved by an agency decision. 29 V.I.C. § 295(a) (“Any person who feels that an injustice has been done him by any order ... of the Commissioner of Planning and Natural Resources ... may appeal therefrom to the Board of Land Use Appeals....”) Further, the relief that the BLUA may provide is generally limited to correcting the agency action. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rabin v. NASDAQ OMX PHLX LLC
182 F. Supp. 3d 220 (E.D. Pennsylvania, 2016)
Pate v. Government of the Virgin Islands
62 V.I. 271 (Superior Court of The Virgin Islands, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
572 F. App'x 107, Counsel Stack Legal Research, https://law.counselstack.com/opinion/loretta-tutein-v-insite-towers-ca3-2014.