Lopez v. Consolidated Edison Co.

357 N.E.2d 951, 40 N.Y.2d 605, 389 N.Y.S.2d 295, 1976 N.Y. LEXIS 3047
CourtNew York Court of Appeals
DecidedOctober 21, 1976
StatusPublished
Cited by20 cases

This text of 357 N.E.2d 951 (Lopez v. Consolidated Edison Co.) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lopez v. Consolidated Edison Co., 357 N.E.2d 951, 40 N.Y.2d 605, 389 N.Y.S.2d 295, 1976 N.Y. LEXIS 3047 (N.Y. 1976).

Opinion

Jasen, J.

Plaintiffs Lozaro Lopez and Eugene Sudlow were injured by a natural gas explosion in a manhole under construction pursuant to a contract between their employer, Peckham Road Corporation (Peckham) and the Consolidated Edison Company (Con Ed). The injured workmen instituted negligence actions against Con Ed. Rita Sudlow brought a derivative action against Con Ed, seeking damages for loss of her husband’s services. Con Ed commenced a third-party action against Peckham for full indemnification, basing its action on an indemnification provision in the contract between the parties. The issue of liability was tried separately and the jury returned a verdict in favor of the plaintiffs. The trial court, to whom resolution of the indemnification issue had been left, dismissed the third-party complaint. The Appellate Term, with one Justice dissenting, modified the judgment by adding to the interlocutory judgment a decretal paragraph dismissing the third-party complaint and affirmed the modified judgment. The Appellate Division affirmed, with four members of the court agreeing with the views expressed by the Appellate Term and the fifth member voting to reverse on the dissenting opinion at the Appellate Term. Leave to appeal to our court was granted upon a certified question: Was the order of the court below properly made?

The issue before us is a very narrow one. We are not asked to review the jury verdict rendered against Con Ed on the issue of liability to the plaintiffs in the main action. On appeal of that aspect of the case to the Appellate Term, the court found that there was sufficient evidence to sustain the verdict, and the issue was pursued no further. Nor does this case involve an apportionment of damages pursuant to the principles first enunciated in Dole v Dow Chem. Co. (30 NY2d 143). [607]*607Con Ed has chosen to rely entirely on the indemnity provisions contained within its contract with Peckham and the courts below have found that Peckham did not commit any acts of negligence that contributed to the accident and which would trigger the application of the indemnification clause in the contract. Thus, the sole issue for our consideration is whether there is sufficient evidence in the record to sustain this determination as a matter of law. We are of the view that there is substantial evidence to support the finding that Peckham did not act negligently with respect to its employees and we conclude, therefore, that the order of the Appellate Division should be affirmed and the certified question answered in the affirmative.

Peckham entered into a lump sum contract with Con Ed to furnish supervision, labor, materials and equipment necessary to excavate trenches and openings at specified locations in White Plains, New York, to install outside plant facilities to be furnished by Con Ed, and to backfill the excavations. In essence, Peckham was to install manholes, vaults and ducts necessary for the placement of underground electrical cables. The contract contained a number of general conditions, including a provision that the "Contractor expressly undertakes and agrees to provide and maintain at his own cost and expense adequate, safe and sufficient walkways, platforms, barricades, warning lights, scaffolds, ladders, runways for concrete carriers, hoists and all necessary and proper equipment, apparatus and appliances useful in carrying on the work and to make the place of work and the ways and approaches thereto safe and free from avoidable danger (Emphasis added.) This portion of the contract also contained a clause whereby the contractor agreed to "indemnify and save harmless the Company from and against any and all liability arising from injury to person or property occasioned wholly or in part by any act or omission of the Contractor, his agents, servants or employees”. (Emphasis added.)

The contract also contained a number of more detailed specifications. In a provision entitled "Scope of Work”, the contractor agreed to furnish all supervision, labor, materials and equipment necessary to excavate trenches; to backfill trenches and other openings; to unload, handle, job store and install precast concrete manholes and conduits; to install field constructed manholes and conduits; to unload, handle, job store, install and connect gas pipes and fittings to be furnished [608]*608by Con Ed; to transport gas pipe, conduit and other gas and electric materials that the company may order the contractor to transport; and to excavate pole and anchor holes. Although the contract indicated that the contractor was required to perform other work associated with "gas and electric installations”, it was specified that Con Ed "employees will insert and remove stoppers and make all connections to and disconnections from live gas mains.”

Pursuant to another contractual provision, Con Ed stationed an employee, Gus Navario, on the job site to supervise the work being conducted by Peckham and its employees. Eugene Sudlow was the assistant superintendent for Peckham and was responsible for a work crew of 12 employees. According to the testimony produced at the trial, in June, 1967, Sudlow and his work crew were engaged in the installation of a precast manhole vault on Main Street in White Plains. On June 7, a test hole, in essence a trench, was dug and the men discovered that a gas service pipe lay across the site of the proposed manhole excavation. Sudlow testified, over objection, that, in accordance with usual procedure, he notified Navario of the exposed pipe and Navario, in turn, called in a special work crew to close off the pipe. The Con Ed employees severed the service pipe from the gas main and sealed the main. The dead service pipe was removed and the Peckham employees resumed their work. The manhole excavation was completed on June 8 and Peckham installed the vault on the next day, a Friday. On Monday, Sudlow and his crew were to remove certain "knock outs” from the precast manhole vault. In the morning, Sudlow smelled gas in the vicinity where the service pipe had been removed. Navario allegedly stated, "there is no gas, you are crazy, they cut the pipe last week.” In the afternoon, before entering the vault, Sudlow conferred with Navario to ask about the gas and to confirm that the knock outs had been properly selected. Navario again stated, "sure, everything is okay, go right into the manhole—everything is checked out.” Sudlow and Lopez entered the manhole without first testing for the presence of gas. After a few blows with a crowbar at one of the knock outs, there was a spark and the manhole was consumed by a fire fed by gas. After the accident, Con Ed discovered a "slight leak” in the main pipe that, according to expert testimony, may have resulted from stress placed upon the main when the service pipe was disconnected.

We assume, although we need not decide, that the indem[609]*609nity provision in the contract is broad enough to require Peckham to indemnify Con Ed from damages occasioned by Con Ed’s own negligence. (See, e.g., Margolin v New York Life Ins. Co., 32 NY2d 149; Levine v Shell Oil Co., 28 NY2d 205.) Nevertheless, the indemnity clause, by its own terms, has no application unless there has been an "act or omission” by Peckham resulting in injury to persons or property. The sole claim lodged by Con Ed against Peckham is that Peckham did not test the manhole for the presence of gas before permitting its employees to enter it. We believe that, under the circumstances of this case, Peckham was under no duty to provide the technical machinery necessary to conduct tests for the presence of gas.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vilsaint v. SL Green Realty Corp.
2021 NY Slip Op 03480 (Appellate Division of the Supreme Court of New York, 2021)
Luken v. Luken
48 Misc. 3d 559 (New York Supreme Court, 2015)
Roling v. ETrade Securities LLC
860 F. Supp. 2d 1035 (N.D. California, 2012)
Ramos v. City of New York
78 A.D.3d 418 (Appellate Division of the Supreme Court of New York, 2010)
Guinter v. I. Park Lake Success, LLC
67 A.D.3d 406 (Appellate Division of the Supreme Court of New York, 2009)
Gentile v. Merrill Lynch, Pierce, Fenner & Smith, Inc.
9 Misc. 3d 111 (Appellate Terms of the Supreme Court of New York, 2005)
Mejia v. Trustees of Net Realty Holding Trust
304 A.D.2d 627 (Appellate Division of the Supreme Court of New York, 2003)
Leone v. Leewood Service Station, Inc.
212 A.D.2d 669 (Appellate Division of the Supreme Court of New York, 1995)
County of Nassau v. Prudential Star Cleaning Contractors, Inc.
148 A.D.2d 410 (Appellate Division of the Supreme Court of New York, 1989)
Martin v. Consolidated Edison Co.
144 A.D.2d 547 (Appellate Division of the Supreme Court of New York, 1988)
Martin v. Consolidated Edison Co. of New York, Inc.
140 A.D.2d 674 (Appellate Division of the Supreme Court of New York, 1988)
Stratford Group, Ltd. v. Interstate Bakeries Corp.
590 F. Supp. 859 (S.D. New York, 1984)
Schiavone Construction Co. v. County of Nassau
717 F.2d 747 (Second Circuit, 1983)
Vey v. Port Authority of New York & New Jersey
429 N.E.2d 762 (New York Court of Appeals, 1981)
Autera v. Arlen Realty & Development Corp.
429 N.E.2d 818 (New York Court of Appeals, 1981)
Stevens v. Consolidated Edison Co. of New York, Inc.
63 A.D.2d 979 (Appellate Division of the Supreme Court of New York, 1978)
Carollo v. Consolidated Edison Co. of New York, Inc.
57 A.D.2d 853 (Appellate Division of the Supreme Court of New York, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
357 N.E.2d 951, 40 N.Y.2d 605, 389 N.Y.S.2d 295, 1976 N.Y. LEXIS 3047, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lopez-v-consolidated-edison-co-ny-1976.