Looms v. Standard Printing Co.

172 S.W. 933, 162 Ky. 492, 1915 Ky. LEXIS 98
CourtCourt of Appeals of Kentucky
DecidedFebruary 3, 1915
StatusPublished

This text of 172 S.W. 933 (Looms v. Standard Printing Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Looms v. Standard Printing Co., 172 S.W. 933, 162 Ky. 492, 1915 Ky. LEXIS 98 (Ky. Ct. App. 1915).

Opinion

OpiNion op the Court by

Judge Settle

Affirming.

The appellant, George Looms, is the owner of a four-story building on First street, between Market and Jefferson, in the city of Louisville, which he, in May, 1910, leased for a term of twenty years from September 1, 1910, to the Globe Printing Company, at a rental of $2,000.00 per annum, payable in equal installments at the end of each month. This contract was reduced to writing and duly signed by the parties thereto. It contains the following clause:

“Party of the first part (appellant Looms)' is to make an allowance of fifteen hundred dollars ($1,500.00) out of the first year’s rent; said sum to be expended in installing heating plant and in rearranging elevator.” i

A portion of the premises was to be occupied by the lessor himself until December 1, 1910. The lessee, Globe Printing Company, an extensive printing concern, owning a large quantity of heavy machinery, be--' gan to move into the property early in September, 1910, but did not get all of its machinery therein until sometime in the month of December. It was clearly understood between the parties to the contract that the elevator then in the building was inadequate for the use the Globe Printing Company would have to make of it, and that it would have to be enlarged and otherwise changed; also that a heating plant would be indispensably necessary to the Globe Printing Company’s use of the leased premises. When the Globe Printing Company commenced to move into the property it at the same time began to take bids on the heating plant, but none of the bids immediately made were accepted, be[494]*494cause they were thought to he excessive; and, in view of the fact that it would have been impossible to install the heating plant in time for the winter season, a large stove was used for heating the building during the winter following the removal of the Globe Printing Company therein. The situation as to the elevator, however, was different, and the Globe printing Company at once began its rearrangement, and by March 20, 1911, had so far progressed with the work on the elevator as to have ■expended $1,040.00 thereon and practically completed it.

On the date last mentioned the Globe Printing Company was adjudged a bankrupt and a receiver in bankruptcy appointed to. take charge of all its property, including the leased premises. He at once had done the little work required to complete the elevator. Soon thereafter the receiver was elected trustee of the bankrupt and operated the plant as such until it, together with the leasehold in question and all rights thereunder, was sold to the appellee, Standard Printing Company. Prior to this sale the trustee in bankruptcy took up with the appellant, Looms, the matter of rent in arrears, and insisted upon withholding the rent then due the latter upon the leased premises until the $1,500.00 stipulated in the lease should be deducted, but shortly thereafter the referee in bankruptcy adjudged that the trustee pay the rent then in arrears and reserve all rights to the allowance of the $1,500.00 out of future rents. This adjustment of the matter made the lease more valuable to the trustee in selling the property. The lease, being an asset of the bankrupt’s estate, was, by direction of the bankrupt court, sold to the appellee with the plant and other effects of the bankrupt on April 21, 1911. When the order of sale was made it was objected to by appellant for the reason thus stated in the pleading filed by him in the bankruptcy proceeding:

‘ ‘ George Looms objects to any allowance being made to the trustee herein, or the Globe Printing Company, in any amount, for costs of installing an elevator in the premises now occupied by said trustee, because, by the terms of the said lease, no allowance was to be made until the heating plant had been installed and■ the elevator rearranged; that the said lessee’s contract to install said heating plant and rearrange the elevator was an entirety contract and said lessee was entitled to no compensation for same whatsoever until the full contract had been carried out and completed. ’ ’

[495]*495As by the sale the property and leasehold went into the hands of the appellee, Standard Printing- Company, with the right to complete the heating plant and deduct the $1,500.00, the latter right constituted a valuable part of the consideration in the sale of the property. At the time of the sale the rearrangement of the elevator had been completed. Although appellee had moved into the property following its purchase in April, 1911, the trustee in bankruptcy paid to appellant the July and.Au-. gust rent, owing to the fact that, notwithstanding’ the sale, he continued as receiver to close up unfinished printing bids which had not been embraced in the sale. Immediately after appellee’s purchase of the plant and leasehold it accepted a bid for the installation of the heating plant, and it was completed in the early fall and the heating plant put in operation in time for use during the winter of 1911. The installation of the heating plant appears to have cost $1,833.60, and the elevator $1,527.00, making the total cost of the heating plant and elevator $3,360.60. The heating plant and elevator constitute permanent improvements which increase the vendible value of the property at least as much as they cost.

After the completion of the heating plant appellee advised appellant of its purpose to withhold the rent due him on the building, as it accrued from month to month, until it received the $1,500.00 which the lease stipulated should be allowed out of the rent for installing the heating plant and rearranging the elevator. Thereupon appellant refused to allow the $1,500.00 to be so deducted from the rent, claiming a forfeiture of the' lease, and threatened appellee with a forcible detainer proceeding for the possession of the leased premises, if not peaceably surrendered. To prevent the threatened forcible detainer proceedings appellee instituted an action in equity in the Jefferson 'Circuit Court, chancery branch, first division, asking an injunction; that it bo given leave to pay into court all rents as due until the court could determine the rights of the parties; and finally asked that it be given a judgment against appellant for the $1,500.00. The case was transferred by the chancery court to the common pleas branch, second division, and on the trial in the latter court a jury was waived and the law and facts, by agreement of the parties, submitted to the court, which adjudged that ap-[496]*496pellee recover of appellant the $1,500.00 claimed in the petition, with interest thereon at the rate of six percent. per annum from April 14, 1913, until paid, and its costs in the action expended. The court’s written conclusions of law and fact appear in the record. The appellant, being dissatisfied with that judgment, by this appeal, seeks its reversal.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
172 S.W. 933, 162 Ky. 492, 1915 Ky. LEXIS 98, Counsel Stack Legal Research, https://law.counselstack.com/opinion/looms-v-standard-printing-co-kyctapp-1915.