Junius Long filed the present lawsuit against the Industrial Development Board of the Town of Vincent and H.L. Fuller Construction Company, Inc. (hereinafter "Fuller"), for the enforcement of a lien. In November 1989, the trial court granted Fuller's motion to compel arbitration and for a stay of the proceedings, pursuant to an arbitration agreement between the parties. The case was removed from the active docket and placed on the administrative docket. Long did not take the necessary steps to comply with the order to arbitrate the dispute, and in May 1992, Fuller filed a motion with the trial court to enforce its November 1989 order compelling *Page 1388
arbitration. In July 1992, the trial court granted Fuller's motion. Long filed a notice of appeal with this Court, contending that the July 1992 order compelling arbitration was in error. He argues in his brief that this appeal was taken pursuant to
In cases where the Federal Arbitration Act is applicable,
The trial court granted Fuller's motion to compel arbitration in November 1989. The proper method of review of that decision would have been a petition for a writ of mandamus. Long had a remedy but failed to seek it; this appeal is due to be dismissed.
APPEAL DISMISSED.
HORNSBY, C.J., and ALMON, ADAMS and STEAGALL, JJ., concur.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
619 So. 2d 1387, 1993 WL 143724, Counsel Stack Legal Research, https://law.counselstack.com/opinion/long-v-industrial-development-bd-ala-1993.