Long Island Lighting Co. v. Stone & Webster Engineering Corp.

839 F. Supp. 183, 1993 U.S. Dist. LEXIS 17676, 1993 WL 521266
CourtDistrict Court, E.D. New York
DecidedDecember 13, 1993
DocketCV 91-2894
StatusPublished
Cited by3 cases

This text of 839 F. Supp. 183 (Long Island Lighting Co. v. Stone & Webster Engineering Corp.) is published on Counsel Stack Legal Research, covering District Court, E.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Long Island Lighting Co. v. Stone & Webster Engineering Corp., 839 F. Supp. 183, 1993 U.S. Dist. LEXIS 17676, 1993 WL 521266 (E.D.N.Y. 1993).

Opinion

MEMORANDUM AND ORDER

WEXLER, District Judge.

Long Island Lighting Company (“LILCO”), plaintiff in the above-referenced action, brought suit against Stone & Webster Engineering Corporation (“SWEC”) for breach of contract, negligence, professional malpractice, and gross negligence in connection with SWEC’s work as the Architect-Engineer and as the Construction Manager and Constructor of the Shoreham Nuclear Power Station (“Shoreham”). Presently before the Court is SWEC’s renewed motion to dismiss pursuant to Rule 12(b)(6) of the Federal Rules of Civil Procedure. ■ For the reasons stated below, defendant’s motion is granted.

I. BACKGROUND

This action continues a long line of litigation stemming from the failure of Shoreham. In 1967, LILCO entered into a written agreement with SWEC, in which SWEC was obligated to provide engineering, design, management and supervisory services on all phases of the Shoreham project. In 1973, the contract was amended and SWEC was made the Constructor of the project instead of the Construction' Manager. At the same time, the amendment added language limiting SWEC’s liability under the contract. Section VII.E.l states:

SWEC’s liability irrespective of fault or negligence for the loss or damage to LILCO’s property including the plant, or to any third party for personal injury or death and property damage, occurring during construction or thereafter and arising out of SWEC’s performance of its services under the Agreement shall be limited at contract or at law to the proceeds from the insurance placed by SWEC and LILCO---- Upon completion of construction of the Project, LILCO agrees to, and does hereby release Stone & Webster, its employees, agents, contractors and subcontractors from any liability, whether or not caused by negligence, for loss or damage to LILCO’s property including the plant____

Section VII.E.3 states:

Neither SWEC nor vendors, contractors or subcontractors shall be liable to LILCO, either individually or jointly and irrespective of whether caused by negligence, for loss of anticipated profits, interest, loss by reason of shutdown or nonoperation of the Project or other facilities, or special or consequential loss or damage, arising from any cause whatsoever____

In Long Island Lighting Co. v. Imo Indus., Inc., 6 F.3d 876 (2d Cir.1993), the Second Circuit was called upon to rule on the consequences of this contract language. *185 LILCO had entered into a contract with Imo Industries for the design and manufacture of three diesel generators for use in the Shore-ham plant. LILCO claimed that the generators were defective and brought suit against IMO Industries for breach of contract, breach of warranty, fraud, negligence, strict products liability and RICO violations. LILCO also sued SWEC in its capacity as construction manager, engineer and designer, in tort for negligent supervision of the project and for breach of contract for failing to provide various professional services “consistent with the best engineering and architectural services.”

LILCO sought damages from SWEC for all injuries it claimed to have suffered as a result of the diesel problems. These damages included: (1) the price of the diesels; (2) the cost of investigating the diesel problems; (3) the cost of repair and testing; (4) increased licensing costs; (5) the cost of replacing the defective diesels with alternate power generators; and (6) the cost of future testing and monitoring to insure reliable operations of the diesels. LILCO also sought to amend its complaint to allege the following types of damages against SWEC: (1) the increased costs of construction of Shoreham allegedly caused by the diesel problems; and (2) the cost of defending an action before the Public Service Commission (“PSC”) and the “penalties” assessed against LILCO by the PSC as a result of the diesel problems.

SWEC successfully moved to dismiss the claims against it in the district court on the ground that the contract language found in the amendment barred LILCO’s suit. The Second Circuit summarily affirmed the district court stating only that they had'

reviewed LILCO’s claims against'SWEC, and conclude that they were properly dismissed in view of the unambiguous language in the parties’ contract. Accordingly, we affirm the dismissal of LILCO’s claims for substantially the reasons stated by the district court in LILCO III, 668 F.Supp. at 242-44.

SWEC argued in the Imo case that clauses VII.E.l and VII.E.3 operated to shift the risk of loss to LILCO. LILCO, on the other hand, contended that it sought only direct economic damages from SWEC and therefore neither section was applicable. According to LILCO, section VII.E.l was inapplicable because that section applies only to injury to property and persons. LILCO argued that there is a distinction between the economic damages it was suing for and the property damage referred to in VII.E.l. 1 Moreover, LILCO also argued, that VII.E.3 only limits SWEC’s liability for consequential damages, not for. the direct economic damage it was seeking.

The district court disagreed with LILCO and dismissed all of LILCO’s claims against SWEC. Long Island Lighting Co. v. Imo-Delaval Inc., 668 F.Supp. 237, 244 (S.D.N.Y. 1987) (Goettel, J.). Although the district court found that the bulk of LILCO’s claims were for economic damages, it recognized that at least some of LILCO’s claims were for property damage. Thus, the court stated that, “Lilco’s remedy for any claims for property damage, i.e., damage to the diesels themselves, whether caused by negligence, malpractice or otherwise, is limited to the insurance placed by it and SWEC.” Id. Accordingly, to the extent that LILCO was attempting to recover for damage to the diesels themselves, the court held that VII. E.l barred such recovery. The district court therefore implicitly rejected the distinction LILCO sought to draw between the property damage referred to in VII.E.l and the direct economic damages it was claiming.

Moreover, the district court went on to hold that “the essence of [LILCO’s] claims [were] for economic injury____ [and] clause VII.E.3 specifically exempts Stone & Webster from liability for a variety of economic losses in connection with Shoreham’s operation or nonoperation. This exemption is for financial loss from any cause whatsoever, and encompasses all economic damages alleged in the amended complaint.” Id. Again, the *186 court rejected LILCO’s argument that the type of economic damages it was seeking was somehow not encompassed by VII.E.3.

II. DISCUSSION

A. The Doctrine of Collateral Estoppel Prevents LILCO From Relitigating Whether the Contract Bars Recovery for the Damages it Seeks in this Litigation

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
839 F. Supp. 183, 1993 U.S. Dist. LEXIS 17676, 1993 WL 521266, Counsel Stack Legal Research, https://law.counselstack.com/opinion/long-island-lighting-co-v-stone-webster-engineering-corp-nyed-1993.