Long Island Lighting Co. v. Federal Energy Regulatory Commission

20 F.3d 494, 305 U.S. App. D.C. 304
CourtCourt of Appeals for the D.C. Circuit
DecidedApril 15, 1994
DocketNo. 92-1438
StatusPublished
Cited by5 cases

This text of 20 F.3d 494 (Long Island Lighting Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Long Island Lighting Co. v. Federal Energy Regulatory Commission, 20 F.3d 494, 305 U.S. App. D.C. 304 (D.C. Cir. 1994).

Opinion

Opinion for the court filed by District Judge REYNOLDS.

REYNOLDS, District Judge:

The Long Island Lighting Company (“LILCO”) seeks review of a decision of the Federal Energy Regulatory Commission (“the Commission”) holding that contracts between LILCO and the New York Power Authority (“NYPA”) did not give LILCO the right to curtail its transmission of electricity to NYPA’s customers on Long Island.1 For reasons stated below, we conclude that the Commission’s interpretation of the contracts was in error, and we therefore reverse.

I. BACKGROUND

A. Facts

In 1981, LILCO, a gas and electric utility serving Long Island, New York, entered into two agreements with NYPA, a corporate agency of the State of New York that supplies hydroelectric power to various municipalities and businesses. The agreements required LILCO to transmit power generated by NYPA to certain of NYPA’s customers located on Long Island. LILCO’s obligation to provide such transmission services was expressly conditioned, however, on its ability to do so without sacrificing “reliabl[e] and economical ] service [to] its own customers.” (Joint Appendix (“J.A.”) at 18-19, 33-34.) LILCO’s “own customers” were those to whom LILCO actually supplied, power, either by generating it or purchasing it, as distinguished from those to whom LILCO merely transmitted power that had been supplied by others, as in the case of NYPA’s customers. Service to NYPA’s customers was thus assigned a lower priority than service to LILCO’s customers.

This arrangement was to be effectuated, pursuant to Section 1.2 of the 1981 agreements, as follows. On the first day of each year, NYPA would notify LILCO of its “anticipated scheduled” transmission needs “for each month from June of the same year through May of the following year.” (Id. at 19-20, 34.) LILCO would then have until March 1 to notify NYPA whether the requested transmission services would be made available. LILCO was required to provide such services if:

the actual capability of its transmission system allows LILCO to transmit [the quantity of power NYPA wishes to have transmitted] and also allows LILCO to meet its obligations to the Municipalities and to import power from generating facilities it owns in whole or in part located [496]*496outside of its service territory and to import power it plans to purchase pursuant to contracts of six months’ duration or longer.

(Id. at 20-21, 34 (emphasis added).)

Until 1991, power was transmitted from the mainland to Long Island primarily by way of a single cable, the “Y-50” cable, which, jointly owned by LILCO and the Consolidated Edison Company of New York, Inc., lay beneath Long Island Sound. By the late 1980s, it had become evident that there was, or soon would be, the need for additional transmission capacity between the mainland and Long Island, and so plans were developed for the construction of a second cable, the “Y-49 cable.” LILCO might have financed the project itself but was not in a financial position to do so (owing in part to its difficulties with the Shoreham Nuclear Power Plant). Instead, in 1987, LILCO and NYPA entered into a contract, the Sound Cable Project Facilities and Marketing Agreement (“SCP Agreement”), whereby NYPA agreed to finance construction of the Y-49 cable and LILCO agreed to reimburse NYPA for construction costs through monthly payments for use of the cable.

NYPA, which retained ownership of the Y-49 cable under the SCP Agreement, also retained control over allocation of the cable’s transmission capacity. In that regard, Section 7.4 of the SCP Agreement provides:

LILCO shall initially be allocated the full capacity of the [Y-4.9 cable]. In the event that [NYPA] allocates [Y-49 cable] capacity to other parties, LILCO’s monthly payment obligations ... shall be [proportionately] reduced during the period of such allocation....

(J.A. at 54 (emphasis added).) On the subject of responsibility for operation and maintenance, Section 5.1 of the SCP Agreement provides:

[NYPA] shall be responsible for the operation and maintenance of the [Y-49 cable]; however, LILCO agrees to operate and to perform routine maintenance functions on the [portions of the cable facilities] which are within LILCO’s service area. LILCO further agrees that it will operate and maintain the [Y-49 cable] in accordance with procedures approved by [NYPA] after consultation with LILCO ... Nothing in this agreement shall preclude [NYPA] from performing such [routine maintenance] functions itself or, after consultation with LILCO, to subcontract to third parties for such work.

(J.A. at 48-49 (emphasis added).)

At one point during the negotiations leading up to the SCP Agreement, LILCO proposed that the new Y-49 cable, rather than the old Y-50 cable, be used for transmission of power to NYPA’s Long Island customers and that NYPA therefore pay “a direct proportionate share” of the cost of the Y-49 cable, which, being new, was far more expensive to use than the Y-50 cable. (J.A. at 74.) Such an arrangement would be justified, LILCO claimed, because “[u]nder some conditions, LILCO may be forced to terminate [transmission] to [NYPA’s] customers [on the Y-50 cable,] and only this new interconnection will permit the reestablishment of service.” (Id.) NYPA refused to accept the proposal, however, on the ground that it would shift “a disproportionate share of the [Y-49 cable] costs to [NYPA’s] customers.” (Id. at 76.) Further, NYPA contended, “If LILCO wishes to pursue this matter, the proper vehicles are the applicable [1981] transmission agreements under which LILCO delivers [NYPA] power to these customers and not the SCP agreement.” (Id. at 77.) There does not appear to have been any subsequent negotiation on this point.

The Y-49 cable was scheduled to be completed in June 1991 and to become operational in October 1991. On December 28, 1990, in accordance with the 1981 agreements, NYPA notified LILCO of its anticipated transmission needs for the annual period beginning June 1, 1991. In response, on February 8, 1991, LILCO notified NYPA that it would not be able to provide the requested transmission services because the capacity of the Y-50 cable was insufficient to accommodate transmission to both NYPA’s customers and LILCO’s. LILCO therefore suggested that NYPA exercise its right under Section 7.4 of the SCP Agreement to allocate to itself a portion of the Y-49 cable’s capacity and use that as an alternative means of transmitting [497]*497power to Long Island, an option that would proportionately reduce LILCO’s payments' to NYPA for use of the Y-49 cable.

Instead, NYPA filed a complaint with the Commission claiming that LILCO’s refusal to provide the requested transmission services violated the 1981 agreements. Under those agreements, NYPA claimed, “the actual capability of [LILCO’s] transmission system” includes not only the capacity of the Y-50 cable, as LILCO claimed, but also that of the Y-49 cable, and is therefore sufficient to permit transmission to both NYPA’s and LILCO’s customers. It appears to be undisputed that if the capacity of the Y-49 cable is not taken into account, LILCO’s transmission system does not have sufficient capacity to serve both NYPA’s and LILCO’s customers.

B. The Commission’s Decision

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
20 F.3d 494, 305 U.S. App. D.C. 304, Counsel Stack Legal Research, https://law.counselstack.com/opinion/long-island-lighting-co-v-federal-energy-regulatory-commission-cadc-1994.