Long Dock Co. v. Mallery

12 N.J. Eq. 431
CourtSupreme Court of New Jersey
DecidedNovember 15, 1858
StatusPublished
Cited by1 cases

This text of 12 N.J. Eq. 431 (Long Dock Co. v. Mallery) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Long Dock Co. v. Mallery, 12 N.J. Eq. 431 (N.J. 1858).

Opinion

The following opinions were delivered.

Whelpley, J.

Complainants and Mallery entered into a contract under seal, dated the 28th May, 1858, by which Mallery, for the prices specified, agreed to furnish all the implements necessary to construct the Bergen tunnel, on the New York and Erie Railroad, and do the work according to the specifications in the agreement; and complainants agreed that whenever-, in the opinion of their engineer, the contract should have been wholly completed by Mallery, they would pay for the same in full at the specified prices. And by a subsequent clause of the agreement, it was stipulated that payments should be made from time to time, as the work progressed, on the certificate of the engineer for work done, such percentage to be deducted from the value of the work done in no ease to be less than ten per cent., as the engineer might think proper. The work was to be completed by the 7th December, 1857.

Mallery began his work, and progressed so that he received on monthly estimates, up to the month of June, 1857, $378,000. The company retained ten per cent., or $42,000.

By the contract, the company had the right to retain, until the completion of the contract work, the whole price, except the ninety per cent., which, by this clause, they had agreed to pay during its progress on the certificate of the engineer; the ninety per cent, was excepted out of the operation of the clause postponing payment of the whole price till the end of the work; indeed it might have been much less than ninety per cent., as the reserved per cent, was to be in no case less than ten; that was a minimum, no maximum was fixed. If the estimates were correct, the company had in hand, on account of this re[445]*445servation, on the 8th June, 1857, §42,000. This money Mallery had no right to demand until the close of his contract, although he might have performed his contract to the letter.

The character of the work required heavy expenditures for labor and materials. To meet it, Mallery required not only Ms cash payments, but also the reserved fund of §42,000. He applied to complainants to pay Mm this in advance of the completion of the work; he did not ask the company to modify the contract, nor hold out any inducement for this advance, save that thereby the progress of the work would be more rapid. The company received no new consideration — the advance was a gratuitous favor extended to him, which the company could have denied without dishonor. His request was acceded to on his own terms, that he should make a mortgage opon Ms tools and apparatus belonging to the execution of the work, which mortgage, he states in liis answer, was “ to answer the same purposes which the retaining of said ten per cent, was intended to answer by the terms of the contract.”

It was executed, and the money paid to him. It recites s‘ that it was, among other things, agreed in the contract that ten per cent, of the estimates of the work done by him should he retained until said work was completed, and the contract fully performed, in the manner and within the time designated therein, the same being retained as security for such performance, and that the money had been paid upon Ms giving this mortgage; that said contract should be fully performed, or the money refunded with interest.”

The proviso in the mortgage was double.

, 1st. That if Mallery should well and truly perform in all things the said contract within the time and in the manner therein specified — or 2d, in case said contract should not be fully performed in the manner therein specified within the time herein mentioned (i. e. 7th De[446]*446cember, 1857,) and stipulated for the completion thereof, that he should at the said time (i. e. 7th December, 1857,) repay to the complainant the said sum of $42,000 and interest from the date of said mortgage.

No doubt the parties to this arrangement understood their relative positions to be unchanged by it, except that the custody of the $42,000 was to be changed, pending the completion of the work up to the time fixed for its completion, from the treasury of the company to that of Mallery. It was nothing but a conditional payment of money supposed to have been earned by him, but not yet d.ue and payable, to accommodate and relieve his present wants, to be returned repaid on the 7th December, 1857, if the tunnel was not then complete.

The terms of the proviso were not, that in case the contract was not performed as far as he was bound to perform it, considering the relative performance of the company, he should repay the money, but that in case said contract should not be fully performed in the manner therein specified within the time therein mentioned for the completion thereof, he would repay the money with interest. The sum was not to be apportioned in view of part performance — the money referred to was to be repaid with interest without abatement or division.

Clearer language could not have been used to denote that the performance contemplated by the proviso was to be absolute actual performance, not constructive legal performance, or rather partial performance, with an excuse for nonperformance of the residue. Time was made the essence of the proviso.

If the company designed to retain the vantage ground given them by the contract and the reserved ten per cent, it was necessary to fix a time for the repayment of the money. If the repayment was dependant upon whether or not Mallery in good faith strove to fulfil his contract, if the proviso had expressed that idea, the company would have perceived that the condition of the mortgage [447]*447did not secure them or answer the same purposes which the retaining of the ten per cent, was intended to answer. The tunnel was not completed at the time specified, and is now incomplete.

The complainants’ hill claims that the condition of the mortgage has not been performed; that the tunnel has not been completed; that the time fixed for the repayment of the money has passed, and it is still unpaid; and that, for these reasons, they are entitled to a sale of the mortgaged premises. They have also alleged that certain creditors of Mallery have, by virtue of an attachment out of the Hudson Circuit, levied upon and seized the mortgaged property, and the same is about to be sold by auditors appointed under the writ, at public auction in parcels, so that the property will go into the possession of a great number of purchasers, some of whom will be irresponsible ; that this will render the plaintiffs security at best, but security almost worthless.

The prayer of the bill is for an injunction and receiver. The injunction was granted.

The defendants, Mallery and Clark, one of the attaching creditors, have severally answered the bill. The injunction was dissolved, and the appointment of a receiver denied.

From this order the appeal has been taken.

All parties concur in one thing — all desire a sale of the property. Mallery desires a sale under the attachments, the complainants under the mortgage. The creditors claim the proceeds on payment of their debts, the complainant on payment of his mortgage.

The claim of the complainants is not to be paid the proceeds, as absolutely due them, but to have the money returned to their custody, whence it was taken for the accommodation of Mallery.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Geiger v. Metz
78 A.2d 152 (New Jersey Superior Court App Division, 1950)

Cite This Page — Counsel Stack

Bluebook (online)
12 N.J. Eq. 431, Counsel Stack Legal Research, https://law.counselstack.com/opinion/long-dock-co-v-mallery-nj-1858.