Loma Prieta Lumber Co. v. Hinton

108 P. 528, 12 Cal. App. 766, 1910 Cal. App. LEXIS 287
CourtCalifornia Court of Appeal
DecidedMarch 9, 1910
DocketCiv. No. 724.
StatusPublished

This text of 108 P. 528 (Loma Prieta Lumber Co. v. Hinton) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Loma Prieta Lumber Co. v. Hinton, 108 P. 528, 12 Cal. App. 766, 1910 Cal. App. LEXIS 287 (Cal. Ct. App. 1910).

Opinion

COOPER, P. J.

This action was brought to recover the sum of $1,845.60 for mill work furnished by plaintiff, to be *767 used and which was used in the construction of a building for the defendant. The court filed findings, upon which judgment was entered in favor of defendant. This appeal is from the judgment and the order denying plaintiff’s motion for a new trial.

There is no controversy as to the following facts: That the building was constructed for defendant; that the cost of the building exceeded $1,000, and that there was no contract in writing, and no contract of any kind filed for record; that one Bugbee was the architect who drew the plans and specifications, and one Johnson was the superintendent in personal charge of the construction of the building; that the mill work was furnished by plaintiff and was of the reasonable value of $1,845.60; that plaintiff has not been paid for said mill work; that no lien was filed against the building.

The court found in effect that plaintiff did not furnish the mill work to defendant at her instance or request, and upon this finding judgment was ordered in favor of defendant. It is here claimed that this finding is not supported by the evidence, and that is the main question, and, in fact, the only question that need be considered in this case.

On behalf of the plaintiff, Bugbee testified that he drew the plans and specifications for the building, and that he was to receive ten per cent on the total cost of the building for his services in drawing the plans and superintending the construction; that he informed defendant that he would have to employ a superintendent to take charge of the hiring of the labor and purchasing the materials and to let the subcontracts, and that defendant would have from time to time to advance the money as needed to pay for such labor and materials; that to this the defendant consented, and that the witness, in pursuance of such arrangement, employed Johnson as superintendent, agreeing to pay Johnson one-half of the ten per cent which he was to receive, and that either himself or Johnson purchased the necessary materials, employed the labor, let the subcontracts and paid for the same with moneys advanced by defendant as needed; that he told defendant that he thought the building could be constructed for a total cost of $8,000, but afterward several changes were made at the request of defendant, such as putting in basins and wardrobes in each room, which considerably increased

*768 the cost. Johnson testified on behalf of the plaintiff that he was the superintendent in charge of the building, and that the contract or arrangement was made in his presence substantially as testified to by Bugbee; that he ordered the labor and materials from time to time; that plaintiff furnished the mill work at his request; that he had every laborer sign a payroll, which was turned over to defendant, and that she gave the witness money to pay the men according to the payroll; that defendant would come on Friday or Saturday to look at the payroll and then go to the bank and get the money with which to pay the men, and then hand the money to the witness; that defendant did this fifteen or twenty times; that the witness kept a payroll in his own handwriting, from which he refreshed his memory, and that defendant paid the following items: November 10, $26.25; December 8, $34.95; January 26, $12.50; December 19, $72.95; February 9, $169.25; February 16, $361.60; February 23, $207.20; March 2, $396.95; March 9, $254.75, which said items were on the payroll for labor. The witness continued from such payroll to give other items for labor, plumbing and other materials which were furnished for the building and used in the construction thereof. He further testified that for getting the bills and the money to pay them promptly two per cent discount was allowed, and defendant desired to and did get such discount; that defendant went with witness to the bank and introduced him, and asked the bank to let witness have money from time to time on her orders, and that he did often go and get the money with which to pay the bills upon the orders given him by defendant; that the changes and extras in the building in deviation from the original plans as made from time to time added $2,000 to $2,500 to its cost.

If the above-quoted testimony is true the defendant is liable to the plaintiff as a matter of law, for the reason that Bugbee and Johnson were her agents in the purchase of the materials, which included the mill work.

Defendant’s counsel further insist that the evidence offered by defendant shows that she made an oral contract with Bugbee, by the terms of which he was to construct the building as an independent contractor for $8,000. Defendant testified in her own behalf, and her statement of the contract is as follows: “I wish to say that he suggested the *769 $8,000 himself, and when I could get $5,000—-the bank notified me that they had collected $5,000 insurance, and I went to Mr. Bugbee and asked him what we could do with that on the lot; he said for ‘$8,000 I could put you up a rooming house with sixty rooms,’ and I said, ‘A temporary building?’ He said, ‘Oh, no, a building that will last twenty years.’ I said, ‘I will see if the bank will let me have $3,000 more in addition and let you then know.’ The bank allowed me the loan of $8,000—$3,000 in addition to what I had received from the insurance, and then I went to Mr. Bugbee and said we can get no more, and I had no more, and he said he could do it, and he began to excavate and got Mr. Johnson to excavate—not much excavating, it was more clearing away the bricks from the lot.” The witness further said that Mr. Bugbee agreed to construct the building for $8,000; but in -order to arrive at the truth we must examine her testimony as a whole.

In cross-examination she testified that she paid out $2,440 in addition to the $8,000 for the construction of the building, and also $300 additional for clearing the lot. She also admitted that she paid the following amounts for material and labor on the building, to wit: Plumbing, $1,000; the Linwood Company, $600; painting, $150; hardware, $154; Christian Lumber Co. bill, $150; electric wiring, $23; that the roofing was $63, of which she had paid $40 and was paying $10 a month on that. She further testified that there was a balance of $300 due for lumber, which she had agreed to pay; and further as follows:

‘‘Mr. Bugbee always promised to give me an accounting, but he went away without doing it.
‘‘Q. What do you mean by that? A. I wanted to know how much it was.
“Q. You wanted to know how much the labor bill was? A. Yes, sir.
‘‘Q. And Mr. Bugbee said he would give you an accounting? A. Yes, sir.
“Q. How many times did you ask him for such an accounting? A. I would remind him and he would put me off. . . .
‘ ‘ Q. In the talk with Mr. Bugbee concerning the construction of this building what was said about his compensation?
*770 A. He said that $8,000 would cover everything. He said he could contract for the building, but he didn’t like to sign a.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
108 P. 528, 12 Cal. App. 766, 1910 Cal. App. LEXIS 287, Counsel Stack Legal Research, https://law.counselstack.com/opinion/loma-prieta-lumber-co-v-hinton-calctapp-1910.