Opinion issued November 21, 2012
In The
Court of Appeals For The
First District of Texas ———————————— NO. 01-11-00566-CV ——————————— LOIS A. BENNETT, AS REPRESENTATIVE OF THE ESTATE OF NORMAN C. BENNETT, JR., Appellant V. SPECTRUM CONSTRUCTION, INC., Appellee
On Appeal from the 55th District Court Harris County, Texas Trial Court Case No. 2009-70812
MEMORANDUM OPINION
Lois Bennett, as representative of the estate of Norman C. Bennett, Jr.,
appeals from a take-nothing judgment in favor of Spectrum Construction following
a bench trial. In one issue, Lois argues that the trial court erred by rendering a take-nothing judgment because, (1) her husband, Norman Bennett, had a personal
service contract with Spectrum Construction, which was terminated upon
Norman’s death, and (2) Norman was entitled to recover for work performed under
quantum meruit.
We reverse and remand for a new trial.
Background
On June 6, 2003, Spectrum Construction and Norman Bennett signed a
subcontractor base agreement supplying terms for Norman to provide electrical
work on future jobs. Norman was a self-employed electrician doing business as
Bennett Electric Company. The president of Spectrum Construction, Allen
Petrucciani, had hired Norman on many prior occasions.
Around September 2006, Spectrum Construction had been hired to turn a
Schlozsky’s into a Vision Source. On September 28, 2006, Spectrum Construction
contracted with Norman to serve as the electrician on the Vision Source project.
At trial, Allen testified that part of the reason Spectrum Construction contracted
with Norman was on the basis of Norman’s skill and knowledge as an electrician.
He also said that Spectrum Construction tries “to hire the electrician who is best
suited for the project . . . and the project was most appropriate for Norman.”
After he started work under his contract but before he completed the work,
Norman died of a heart attack. Lois was appointed as executor of Norman’s estate.
2 Lois brought suit against Spectrum Construction, based on quantum meruit,
alleging that Spectrum Construction owed Norman for the time and services
provided before his untimely death.
It is undisputed by the parties that Norman performed some work before his
death, though the parties did dispute the amount of work done and whether
Spectrum Construction could offset its costs for completing the electrical work
against Lois’s claim. Following a bench trial, the trial court rendered a take-
nothing judgment against Lois.
Standard of Review
When, as here, the trial court did not make findings of fact or conclusions of
law, we infer all facts necessary to support the judgment if they are supported by
the evidence. See Moki Mac River Expeditions v. Drugg, 221 S.W.3d 569, 574
(Tex. 2007). If a complete reporter’s record is part of the appellate record, the
legal and factual sufficiency of the trial court’s implied findings may be challenged
on appeal using the same standards of review applicable to a jury’s findings. Mays
v. Pierce, 203 S.W.3d 564, 571 (Tex. App.—Houston [14th Dist.] 2006, pet.
denied).
An appellant attacking the legal sufficiency of an adverse finding on an issue
on which she had the burden of proof must demonstrate that the evidence
conclusively establishes all vital facts in support of the issue. Dow Chem. Co. v.
3 Francis, 46 S.W.3d 237, 241 (Tex. 2001). The appellant must show that there is
no evidence to support the fact finder’s finding and that the evidence conclusively
establishes the opposite of the finding. See id. The ultimate test for legal
sufficiency is whether the evidence would enable a reasonable and fair-minded fact
finder to reach the verdict under review. City of Keller v. Wilson, 168 S.W.3d 802,
827 (Tex. 2005).
When examining a legal sufficiency challenge, an appellate court reviews
the evidence in the light most favorable to the challenged finding and indulges
every reasonable inference that would support it. Id. at 822. We consider evidence
favorable to the finding if a reasonable fact finder could consider it, and disregard
evidence contrary to the finding unless a reasonable fact finder could not disregard
it. Id. at 827. In an appeal of a judgment rendered after a bench trial, we may “not
invade the fact-finding role of the trial court, who alone determines the credibility
of the witnesses, the weight to give their testimony, and whether to accept or reject
all or any part of that testimony.” Volume Millwork, Inc. v. W. Hous. Airport
Corp., 218 S.W.3d 722, 730 (Tex. App.—Houston [1st Dist.] 2006, pet. denied).
Liability
In the first part of her sole issue, Lois argues that the evidence establishes as
a matter of law that she can recover under quantum meruit against Spectrum
Construction. Specifically, she argues that (1) Norman had a personal service
4 contract with Spectrum Construction, (2) the personal services contract was
terminated upon Norman’s death, and, accordingly, (3) she can recover under
Lois sought to recover from Spectrum Construction under the theory of
quantum meruit. Quantum meruit is an equitable remedy based on the notion of an
implied contract preventing unjust enrichment. See City of Ingleside v. Stewart,
554 S.W.2d 939, 943 (Tex. Civ. App.—Corpus Christi 1977, writ ref’d n.r.e). To
recover under quantum meruit the
claimant must prove that (1) valuable services were rendered or materials furnished; (2) for the person sought to be charged; (3) which services and materials were accepted by the person sought to be charged [and] used and enjoyed by him; (4) under such circumstances as reasonably notified the person sought to be charged that the plaintiff in performing such services was expecting to be paid by the person sought to be charged.
Tricon Tool & Supply, Inc. v. Thumann, 226 S.W.3d 494, 502 (Tex. App.—
Houston [1st Dist.] 2006, pet. denied).
As a general rule, the presence of an express contract bars recovery under
quantum meruit. In re Kellogg Brown & Root, Inc., 166 S.W.3d 732, 740 (Tex.
2005). It is undisputed that there was a contract between Norman and Spectrum
Construction concerning the work performed by Norman. The question, then, is
whether any exception applies to allow Lois to recover under quantum meruit.
5 The Supreme Court of Texas has recognized three exceptions to the general
rule that an express contract bars recovery under quantum meruit. “First, recovery
in quantum meruit is allowed when a plaintiff has partially performed an express
contract but, because of the defendant’s breach, the plaintiff is prevented from
completing the contract.” Truly v. Austin, 744 S.W.2d 934, 936 (Tex. 1988).
Free access — add to your briefcase to read the full text and ask questions with AI
Opinion issued November 21, 2012
In The
Court of Appeals For The
First District of Texas ———————————— NO. 01-11-00566-CV ——————————— LOIS A. BENNETT, AS REPRESENTATIVE OF THE ESTATE OF NORMAN C. BENNETT, JR., Appellant V. SPECTRUM CONSTRUCTION, INC., Appellee
On Appeal from the 55th District Court Harris County, Texas Trial Court Case No. 2009-70812
MEMORANDUM OPINION
Lois Bennett, as representative of the estate of Norman C. Bennett, Jr.,
appeals from a take-nothing judgment in favor of Spectrum Construction following
a bench trial. In one issue, Lois argues that the trial court erred by rendering a take-nothing judgment because, (1) her husband, Norman Bennett, had a personal
service contract with Spectrum Construction, which was terminated upon
Norman’s death, and (2) Norman was entitled to recover for work performed under
quantum meruit.
We reverse and remand for a new trial.
Background
On June 6, 2003, Spectrum Construction and Norman Bennett signed a
subcontractor base agreement supplying terms for Norman to provide electrical
work on future jobs. Norman was a self-employed electrician doing business as
Bennett Electric Company. The president of Spectrum Construction, Allen
Petrucciani, had hired Norman on many prior occasions.
Around September 2006, Spectrum Construction had been hired to turn a
Schlozsky’s into a Vision Source. On September 28, 2006, Spectrum Construction
contracted with Norman to serve as the electrician on the Vision Source project.
At trial, Allen testified that part of the reason Spectrum Construction contracted
with Norman was on the basis of Norman’s skill and knowledge as an electrician.
He also said that Spectrum Construction tries “to hire the electrician who is best
suited for the project . . . and the project was most appropriate for Norman.”
After he started work under his contract but before he completed the work,
Norman died of a heart attack. Lois was appointed as executor of Norman’s estate.
2 Lois brought suit against Spectrum Construction, based on quantum meruit,
alleging that Spectrum Construction owed Norman for the time and services
provided before his untimely death.
It is undisputed by the parties that Norman performed some work before his
death, though the parties did dispute the amount of work done and whether
Spectrum Construction could offset its costs for completing the electrical work
against Lois’s claim. Following a bench trial, the trial court rendered a take-
nothing judgment against Lois.
Standard of Review
When, as here, the trial court did not make findings of fact or conclusions of
law, we infer all facts necessary to support the judgment if they are supported by
the evidence. See Moki Mac River Expeditions v. Drugg, 221 S.W.3d 569, 574
(Tex. 2007). If a complete reporter’s record is part of the appellate record, the
legal and factual sufficiency of the trial court’s implied findings may be challenged
on appeal using the same standards of review applicable to a jury’s findings. Mays
v. Pierce, 203 S.W.3d 564, 571 (Tex. App.—Houston [14th Dist.] 2006, pet.
denied).
An appellant attacking the legal sufficiency of an adverse finding on an issue
on which she had the burden of proof must demonstrate that the evidence
conclusively establishes all vital facts in support of the issue. Dow Chem. Co. v.
3 Francis, 46 S.W.3d 237, 241 (Tex. 2001). The appellant must show that there is
no evidence to support the fact finder’s finding and that the evidence conclusively
establishes the opposite of the finding. See id. The ultimate test for legal
sufficiency is whether the evidence would enable a reasonable and fair-minded fact
finder to reach the verdict under review. City of Keller v. Wilson, 168 S.W.3d 802,
827 (Tex. 2005).
When examining a legal sufficiency challenge, an appellate court reviews
the evidence in the light most favorable to the challenged finding and indulges
every reasonable inference that would support it. Id. at 822. We consider evidence
favorable to the finding if a reasonable fact finder could consider it, and disregard
evidence contrary to the finding unless a reasonable fact finder could not disregard
it. Id. at 827. In an appeal of a judgment rendered after a bench trial, we may “not
invade the fact-finding role of the trial court, who alone determines the credibility
of the witnesses, the weight to give their testimony, and whether to accept or reject
all or any part of that testimony.” Volume Millwork, Inc. v. W. Hous. Airport
Corp., 218 S.W.3d 722, 730 (Tex. App.—Houston [1st Dist.] 2006, pet. denied).
Liability
In the first part of her sole issue, Lois argues that the evidence establishes as
a matter of law that she can recover under quantum meruit against Spectrum
Construction. Specifically, she argues that (1) Norman had a personal service
4 contract with Spectrum Construction, (2) the personal services contract was
terminated upon Norman’s death, and, accordingly, (3) she can recover under
Lois sought to recover from Spectrum Construction under the theory of
quantum meruit. Quantum meruit is an equitable remedy based on the notion of an
implied contract preventing unjust enrichment. See City of Ingleside v. Stewart,
554 S.W.2d 939, 943 (Tex. Civ. App.—Corpus Christi 1977, writ ref’d n.r.e). To
recover under quantum meruit the
claimant must prove that (1) valuable services were rendered or materials furnished; (2) for the person sought to be charged; (3) which services and materials were accepted by the person sought to be charged [and] used and enjoyed by him; (4) under such circumstances as reasonably notified the person sought to be charged that the plaintiff in performing such services was expecting to be paid by the person sought to be charged.
Tricon Tool & Supply, Inc. v. Thumann, 226 S.W.3d 494, 502 (Tex. App.—
Houston [1st Dist.] 2006, pet. denied).
As a general rule, the presence of an express contract bars recovery under
quantum meruit. In re Kellogg Brown & Root, Inc., 166 S.W.3d 732, 740 (Tex.
2005). It is undisputed that there was a contract between Norman and Spectrum
Construction concerning the work performed by Norman. The question, then, is
whether any exception applies to allow Lois to recover under quantum meruit.
5 The Supreme Court of Texas has recognized three exceptions to the general
rule that an express contract bars recovery under quantum meruit. “First, recovery
in quantum meruit is allowed when a plaintiff has partially performed an express
contract but, because of the defendant’s breach, the plaintiff is prevented from
completing the contract.” Truly v. Austin, 744 S.W.2d 934, 936 (Tex. 1988).
There is no allegation or evidence in the record that Spectrum Construction
breached the contract first or in any way prevented Norman from completing the
contract. Accordingly, this exception does not apply.
Second, “[r]ecovery in quantum meruit is sometimes permitted when a
plaintiff partially performs an express contract that is unilateral in nature.” Id. at
937. It is undisputed that the contract between Norman and Spectrum Construction
was bilateral. Accordingly, this exception does not apply.
Third, a breaching plaintiff in a construction contract can recover the
reasonable value of services less any damages suffered by the defendant if the
defendant accepts and retains “the benefits arising as a direct result of the
[plaintiff’s] partial performance.” Id. The parties dispute whether Norman’s death
constitutes a breach of the contract. Central to this dispute is whether Norman’s
contract was a contract for personal services.
“Under the principles of contract law, contractual obligations generally
survive the death of a party and bind his estate if the contract is capable of being
6 performed by the estate representative.” Cardwell v. Sicola-Cardwell, 978 S.W.2d
722, 726 (Tex. App.—Austin 1998, pet. denied). A personal services contract, in
contrast, is “terminated by death.” Gilliam v. Kouchoucos, 340 S.W.2d 27, 28
(Tex. 1960). A personal services contract is one that “depends on the existence of
a particular person, . . . on the skill or character of the other party, or . . . on a
personal confidence between the parties.” Cardwell, 978 S.W.2d at 726; see also
Van Zandt v. Fort Worth Press, 359 S.W.2d 893, 895–96 (Tex. 1962) (holding
personal service contract is done personally by a particular individual versus a
contract for services performed by a corporation).
Though Spectrum Construction contracted with the Bennett Electric
Company, it is a sole proprietorship. “A sole proprietorship does not have a
separate legal existence distinct from the operator of the business.” Garcia v. Shell
Oil Co., 355 S.W.3d 768, 778 (Tex. App.—Houston [1st Dist.] 2011, no pet.).
Accordingly, Spectrum Construction contracted with Norman individually.
During trial, Allen stated that part of the reason Spectrum Construction
contracted with Norman was on the basis of his skill and knowledge as an
electrician. Allen also testified that Spectrum Construction tries “to hire the
electrician who is best suited for the project . . . and the project was most
appropriate for Norman.” In addition, the record shows that Allen and Norman
had an ongoing work relationship and that Spectrum Construction regularly relied
7 on Norman. Based on the above testimony, we conclude that Norman was hired
for projects because of his personal knowledge and skill, and Spectrum
Construction had confidence and trust in Norman’s work.
The record does indicate that Norman had two other electricians working
with him. The record also indicates, however, that they were lower-skilled
electricians, that Norman was doing work under the contract, that they were
working under the direction of Norman, and that Norman was the party responsible
for the completion of the work. Accordingly, this fact does not undercut the claim
that the contract was a personal services contract.
Similarly, Spectrum Construction argued at trial that, while they did award
the contract to Norman, they could have awarded the contract to any number of
electricians. No court has held that, in order for a contract to be classified as a
personal service contract, there must be a showing that the services provided could
only have been performed by that one person, and we decline to adopt such a
holding here. A party is only required to show that the contract depended on the
skill or character of the other party, not that it depended on the skill or character of
the other party to the exclusion of all other people. See Cardwell, 978 S.W.2d at
726.
We hold Norman’s contract with Spectrum Construction was a personal
service contract. Because it was a personal service contract, it terminated upon
8 Norman’s death and did not constitute a breach. See id. (holding survival of
certain person in a personal service contract is constructive condition to any further
obligation of either party of contract).
If the three exceptions recognized in Truly are the only available exceptions
to recovering under quantum meruit when a contract exists, Lois is essentially
thrust into a situation in which she cannot recover at all for the work performed by
Norman. Substantial performance is a condition precedent to recovery under an
express contract. Murray v. Crest Constr., Inc., 900 S.W.2d 342, 345 (Tex. 1995).
While the parties dispute how much work Norman performed prior to his death, no
one argues that he substantially performed under the contract. Accordingly, breach
of contract would not have been a viable path for recovery. If the Truly exceptions
are the only exceptions to allow a party to recover under quantum meruit, then that
is also not a viable path for recovery. This would mean, then, that a plaintiff who
has breached a contract can recover under quantum meruit, while a plaintiff who
has not breached but also cannot complete the contract due to circumstances
beyond his control cannot recover at all. This would have the effect of forcing a
party who believes he may not be able to substantially complete the contract due to
factors beyond his control to either stop work and breach the contract or continue
working with the risk of being unable to recover at all. We do not see this as a
viable result.
9 We also do not find it to be supported by the law. In Truly, after the
supreme court determined that the three exceptions did not apply to the plaintiff, it
continued to determine whether the principles of quantum meruit applied to him in
general. 744 S.W.2d at 938. This would have been unnecessary if the three
exceptions the court had recognized were exclusive.
Similarly, in Pepi Corp., we recognized a common theme to the Truly
exceptions: “an inability to recover under contract because of a failure of this
condition precedent [of substantial performance]—either because of a breach
preventing completion of the condition precedent or because of a lack of any legal
obligation that creates the condition precedent.” Pepi Corp. v. Galliford, 254
S.W.3d 457, 463 (Tex. App.—Houston [1st Dist.] 2007, pet. denied). After
holding that the Truly exceptions did not apply to the plaintiff, we went on to
analyze whether the plaintiff fell under the common theme of the exceptions and
concluded he did not. Id.
In Benson, the Fort Worth Court of Appeals recognized another exception to
the general rule that a party cannot recover under quantum meruit when a contract
exists. Benson v. Harrell, 324 S.W.2d 620, 623 (Tex. Civ. App.—Fort Worth
1959, writ ref’d n.r.e.). It held, “There may be recovery on quantum meruit for the
reasonable value of the part of the contract performed where there has been a
mutual abandonment, or where further performance is prevented by a cause for
10 which neither party is responsible and by reason of which further performance is
excused.” Id. This exception is in line with the common theme to the Truly
exceptions. It would also allow recovery for a plaintiff who has not substantially
performed through no fault of his own. Accordingly, we adopt the holding of the
Fort Worth Court of Appeals.
It is undisputable that Norman’s death prevented further performance and
that neither party is responsible for Norman’s death. Because we have held that
the contract is a personal service contract, death excuses further performance of the
contract. See Cardwell, 978 S.W.2d at 726 (holding survival of certain person in a
personal service contract is constructive condition to any further obligation of
either party of contract). Accordingly, the express contract was not a bar to Lois’s
recovery under quantum meruit.
As stated above, to recover under quantum merui,t Lois must prove that
Norman rendered valuable services that were accepted and used by Spectrum
Construction under such circumstances that reasonably notified Spectrum
Construction that Norman was expecting to be compensated. See Thumann, 226
S.W.3d at 502; City of Ingleside, 554 S.W.2d at 943.
During trial, Spectrum Construction’s representative conceded that Bennett
provided valuable services to and accepted by Spectrum Construction in which
Bennett expected to be paid.
11 Q: You conceded that Norman provided services for two days on the job correct?
A: It appears to be.
Q: Okay. Do you concede that Spectrum accepted the benefit of those services?
A: Yes.
Q: Did you concede that at the time Spectrum accepted the benefit of those services, Spectrum expected to pay for those services?
Q: Do you concede that Spectrum got the benefit of the permits?
Q: And do you concede that Spectrum should pay for the cost of the benefit of those permits?
No contrary evidence was presented at trial. We hold that there is legally
sufficient evidence in the record to support Lois’s claim for quantum meruit. We
sustain the first portion of Lois’s sole issue.
Damages
In the remainder of her sole issue, Lois contends that the trial court erred in
granting a take-nothing judgment in favor of Spectrum Construction because there
was sufficient evidence in the record to support her claim for damages.
Lois testified that Norman worked for eight days and completed both the “T-
Pole” phase and the demolition phase. In contrast, Allen testified that Norman
12 worked two days and only completed the “T-Pole” phase. Though the amount of
work completed is in dispute, both parties concede that at least some work was
done. Nevertheless, the court rendered a take-nothing judgment.
After the trial, the court indicated that it believed Spectrum Construction
could offset the costs incurred in completing the work that exceeded the amount of
contract price. The concept behind offset is to allow parties with mutual debts the
ability pay what is owed to one another. Sommers v. Concepcion, 20 S.W.3d 27,
35 (Tex. App.—Houston [14th Dist.] 2000, pet. denied). Pursuant to Texas law,
Spectrum Construction pleaded as an affirmative defense, “that the damages
claimed by [Norman] should be offset by the cost of the labor and materials
expended by [Spectrum Construction] in completing the work left unfinished by
Bennett Electric Company.” See Tex. R. Civ. P. 94; Brown v. Am. Transfer &
Storage Co., 601 S.W.2d 931, 936 (Tex. 1980) (acknowledging offset as an
affirmative defense, which must be pleaded).
As we have held above, however, Norman did not breach his contract.
Instead, the contract merely terminated. While contractual obligations generally
survive the death of one of the parties, a personal service contract terminates at
death. Cardwell, 978, S.W.2d at 726. It is this termination that prevents a party
from recovering under a claim of breach of contract. See id. at 726, 728 (holding
contract was not for personal services and, therefore, plaintiff could recover for
13 breach of contract). With no breach, Norman does not owe Spectrum Construction
for the costs incurred by Spectrum Construction to complete the Vision Source job
after Norman’s death. In other words, Spectrum Construction does not have a
conclusive claim against Norman. Therefore, Bennett does not owe a debt to
Spectrum Construction, making offset inappropriate.
We sustain the remainder of Lois’ sole issue.
Conclusion
When the evidence is insufficient to support an award of zero damages, but a
fact issue remains as to the amount to be awarded, the proper remedy is to remand
for a new trial. See Smith v. Patrick W.Y. Tam Trust, 296 S.W.3d 545, 548–49
(Tex. 2009) (remanding for new trial when right to attorneys’ fees established as a
matter of law, when jury awarded zero dollars in attorneys’ fees, and when fact
issue remained about proper amount of attorneys’ fees to award). Because
damages are unliquidated and liability is contested, we must remand for a new trial
on liability as well. See TEX. R. APP. P. 44.1(b) (prohibiting separate trial solely on
unliquidated damages if liability is contested).
Laura Carter Higley Justice
Panel consists of Justices Jennings, Higley, and Sharp. 14