Logemann v. Pauly

76 N.W. 604, 100 Wis. 671, 1898 Wisc. LEXIS 257
Wisconsin Supreme Court·Decided October 11, 1898·Published

Opinion

Pinney, J.

This action was brought to recover $2,400, tbe price of a marine boiler, and $826.17 for work and labor done and materials furnished therefor, which constituted tbe second cause of action. As to tbe second cause of action tbe defendant admitted an indebtedness of $634.87, denying tbe remainder, while as to tbe first be admitted tbe whole thereof, but alleged a counterclaim by reason of delay in finishing tbe boiler. There was a trial before a referee. Tbe only material question for review in this court is whether tbe amount of damages awarded to tbe defendant on his counterclaim for delay in furnishing tbe boiler was erroneous, as being too low. The referee found that tbe plaintiffs sold, furnished, and delivered materials to tbe defendant and performed work and labor for him on and between May 1, 1895, and September 1, 1895, of tbe. value of $826.17. This was tbe purport of tbe fourth finding of tbe referee, and it was excepted to as being contrary to and unsupported by tbe evidence; but tbe exception fails to point out tbe item or items excepted to, and it does not appear to have been seriously pressed.

Tbe third and fourth assignments of error relate to tbe damages to tbe defendant upon bis counterclaim by reason of want of timely completion of tbe boiler. By tbe contract it was to be ready for delivery April 1, 1895. It was not so ready, and tbe referee found it was delivered June 22,1895, and that defendant lost tbe use of bis steamer “ Westover ” for eighty-two days in consequence of this delay. Tbe respondents claim that it should be at least twenty-five days less, but tbe court affirmed tbe referee on this point, and it was also found that tbe delay was not waived by tbe defendant. It appears that tbe boiler was ordered for use in one of two [673] boats operated by tbe defendant, namely, either the “West-over” or the “A. T. Bliss,” both of which were used by defendant for transporting lumber and other freight to and from different ports upon the lakes. The referee found that by reason of the plaintiffs’ failure to deliver said boiler at the time specified in the contract, defendant was deprived of the use of the steamer “Westover” for a period of eighty-two days, and that a fair reasonable rental value of said steamer during the time the defendant was so deprived of her use was $20 a day,-amounting to $1,640, and that the defendant was entitled to offset against the amount due to the plaintiff for the purchase price of said boiler and the extra work aforesaid the said sum of $1,640, the damages aforesaid, and that the plaintiffs were entitled to judgment -against the defendant for the sum of $1,586.17, with inter•est from September 1, 1895.

The trial court, on motion to review and set aside the report upon the question of the amount of damages the defendant was entitled to recover on his counterclaim, applied the rule in Shepard v. Milwaukee G. L. Co. 15 Wis. 318-329, affirmed in Poposkey v. Munkwitz, 68 Wis. 322, that “ value ” and “net profits,” in such cases, are convertible terms, and that profits lost are recoverable “ when they are not so conjectural and remote as to be incapable of ascertainment with reasonable certainty; ” that what the defendant might have made out of his boat for the eighty-two days was what he had lost, whether it was called “value,” “rental value,” or “ net profits,” all of which terms, in such connection, mean the same thing; and, on the ground that the defendant’s evidence on the subject was conjectural and uncertain, reduced the sum of $20 per day for damages for loss of the use of the boat to $10, making the entire allowance on that ground $820, instead of $1,640. The report was thus modified, and judgment wa,s entered thereon accordingly, as .stated.

[674] The evidence, expert and otherwise, on the subject of the defendant’s damages by reason of having been deprived of the use of the “Westover” for the period of eighty-two days, took a wide range, and cannot well be condensed so as to be either instructive or useful. It involved no legal principle, and none appears to have been argued in connection with it. It was a question of fact, and of the deduction or conclusion the evidence would warrant. It appeared that the defendant had invested large sums of money in vessel property on the lake for carriage of lake freights, and that the boiler contracted for was designed and meant for use in the steam barge “Westover,” chartered by the defendant, and used in connection with the tow barge called the “ Bliss,” of which the plaintiffs had knowledge before and at the time of the contract; and there was evidence tending to show that by reason of failure to deliver the boiler as agreed the defendant’s boats “Westover” and “ Bliss ” were unable to carry cargoes of freight, and were obliged to lie idle until August 3, 1895; and that, if the plaintiffs had delivered the boiler as agreed, the defendant would and could have carried freight and cargoes during the months of April, May, June, July, and part of August; that the defendant, by reason of the failure of the plaintiffs to so deliver the boiler, was deprived of the use of said boats, and the income thereof, and it was claimed that the reasonable value of the use of said boats during said period was $5,100. It was admitted that at the time the contract was executed the plaintiffs knew the boilers were designed for use in one of defendant’s boats. The evidence shows that the boiler wa^s not set out of the plaintiff’s shop until June 26, 1895, and that when it was set out it was simply the shell of the boiler, with none of the fixtures and other appliances complete, as required by government regulations, agreed to be furnished and attached to it, ready for water and steam pipes; and there does not appear to be any evi-[675] clen.ce that the time in which the work was to have been completed was extended beyond April 1st.

Free access — add to your briefcase to read the full text and ask questions with AI

Logemann v. Pauly, 76 N.W. 604, 100 Wis. 671, 1898 Wisc. LEXIS 257 (Wis. 1898).

76 N.W. 604 (Logemann v. Pauly) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Shepard v. Milwaukee Gas Light Co.
15 Wis. 318 (Wisconsin Supreme Court, 1862)
Poposkey v. Munkwitz
32 N.W. 35 (Wisconsin Supreme Court, 1887)