Loehrke v. Wanta Builders, Inc.

445 N.W.2d 717, 151 Wis. 2d 695, 1989 Wisc. App. LEXIS 706
CourtCourt of Appeals of Wisconsin
DecidedJuly 26, 1989
Docket88-0463
StatusPublished
Cited by22 cases

This text of 445 N.W.2d 717 (Loehrke v. Wanta Builders, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Loehrke v. Wanta Builders, Inc., 445 N.W.2d 717, 151 Wis. 2d 695, 1989 Wisc. App. LEXIS 706 (Wis. Ct. App. 1989).

Opinion

GARTZKE, P.J.

Wanta Builders, Inc. (the prime contractor) appeals from a judgment in favor of Neal Loehrke and Weyauwega Well Drilling, Inc. (the subcontractor) for $20,672.70 compensatory and punitive damages, interest and costs. The prime contractor contends the trial court erred as a matter of law when it submitted the issue of punitive damages to the jury and that it abused its discretion by awarding preverdict interest on the compensatory damage award.

We conclude that a fiduciary relationship existed between the prime contractor and the subcontractor by virtue of sec. 779.16, Stats., the "trust fund" statute. Violation of a fiduciary duty is a tort for which punitive damages may be awarded if warranted. We conclude that a contractor who fails to pay the subcontractor because of a bona fide dispute as to the amount due has not violated a fiduciary duty under sec. 779.16. We therefore *699 reverse that part of the judgment awarding punitive damages.

We conclude that preverdict interest should be limited to the undisputed part of the subcontractor's claim. We therefore reverse and remand for recalculation of interest.

The critical facts are essentially uncontroverted. The prime contractor engaged the subcontractor to install a well on a county landfill project. The agreed price for the installation was $6,420. The subcontractor installed the well, but on October 19, 1982 it billed the prime contractor for $8,424, including disputed extras. The county paid the prime contractor in February 1983 on its representation that all subcontractors had been paid. Since the prime contractor had not paid the subcontractor, the representation was false.

The presidents of the subcontractor and prime contractor met in April 1983 to settle the account. The prime contractor proposed to settle for $6,892 and tendered a check for that amount, on condition that the subcontractor execute a lien waiver. The lien waiver form provided that the subcontractor would "waive all rights and claims for lien on the buildings ... for the prime contractor." The tender was refused. The subcontractor's president called the prime contractor on a few later occasions, but the prime contractor would not change its conditions.

The presidents met again a few months later. This time the prime contractor's president refused to make even a partial payment until the lien waiver was provided. In September 1983 the subcontractor's president broke into the home of the prime contractor's president, located and removed the $6,892 check, and unsuccessfully attempted to cash it.

*700 The subcontractor then brought this action against the contractor for breach of contract and unjust enrichment, seeking $8,424 compensatory damages and also punitive damages. The prime contractor counterclaimed for trespass.

At the jury trial, the subcontractor's president testified without objection that well drillers had financial difficulties during the period involved. The amount due from the prime contractor was one of the subcontractor's larger outstanding invoices, and it needed payment to cover its own checks. The subcontractor's president claimed that the prime contractor's tactic was to "starve out a sub." 1 Nonpayment had caused him financial problems and difficulties in his marriage and family life. Witnesses for both sides testified at length regarding the extras claimed by the subcontractor, and the prime contractor's president conceded that he had never disputed that the subcontractor was entitled to the original contract price, $6,420.

At the close of the evidence, the court proposed to submit punitive as well as compensatory damage questions to the jury. The prime contractor objected to a question on punitive damages awardable to the subcontractor, on grounds that this was a contract case and there was no evidence of wanton, malicious, or reckless conduct on its part. The subcontractor contended that this was more than a contract case (without identifying the "more") and that the evidence justified it. The court ruled that the evidence would support a finding of wanton, reckless, and wilful refusal "to settle and to make *701 payment to the subcontractor," and submitted punitive damage questions to the jury.

The jury found that the prime contractor owed the subcontractor $7,632.67 on its well-drilling contract, including approved extras, and the court added preverdict interest to this award. The jury found that the prime contractor's "actions regarding payment under the contract [were] done maliciously, in wanton, wilful, or reckless disregard" of the subcontractor's rights and assessed $10,000 punitive damages against the prime contractor. The jury assessed $100 compensatory and $250 punitive damages against the subcontractor for the trespass.

Whether punitive damages are available is a question of law. We are not bound by the trial court's conclusion in this regard and decide the issue de novo. State v. Big John, 146 Wis. 2d 741, 748, 432 N.W.2d 576, 579 (1988).

Wisconsin courts have consistently held that punitive damages are unavailable in a breach of contract action. Autumn Grove Joint Venture v. Rachlin, 138 Wis. 2d 273, 279, 405 N.W.2d 759, 762 (Ct. App. 1987). The American Law Institute has adopted the same rule. "Punitive damages are not recoverable for a breach of contract unless the conduct constituting the breach is also a tort for which punitive damages are recoverable." Restatement (Second) of Contracts sec. 355 (1979). The Restatement rule is followed in almost every jurisdiction which has considered the issue. J. Ghiardi and J. Kircher, Punitive Damages sec. 5.16 (1985).

If, however, a tort duty coincides with a contract obligation, either a contract or a tort action will lie for *702 its breach. Autumn Grove, 138 Wis. 2d at 281, 405 N.W.2d at 763. A tort duty coincides with a contractual obligation when the breaching party has a fiduciary duty to the other party. That was the situation in Anderson v. Continental Ins. Co., 85 Wis. 2d 675, 689, 271 N.W.2d 368, 375 (1978), where an action was brought against a fire insurance company which had refused to honor its insured's claim and the insurer was held to be acting as a fiduciary. This, too, is consistent with the position of the American Law Institute. "A fiduciary who commits a breach of his duty as a fiduciary is guilty of tortious conduct to the person for whom he should act." Restatement (Second) of Torts sec. 874 comment b (1977).

Section 779.16, Stats., provides in part:

All moneys . . . paid or to become due to any prime contractor ... for public improvements are a trust fund only in the hands of the prime contractor . . . and shall not be a trust fund in the hands of any other person. The use of the moneys by the prime contractor ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Century Fence Company v. American Sewer Services, Inc.
2021 WI App 75 (Court of Appeals of Wisconsin, 2021)
Pro-Pac Incorporated v. WOW LogisticsCompany
721 F.3d 781 (Seventh Circuit, 2013)
Bailey v. Skipperliner Industries, Inc.
278 F. Supp. 2d 945 (N.D. Indiana, 2003)
Kernz v. J. L. French Corp.
2003 WI App 140 (Court of Appeals of Wisconsin, 2003)
HMO-W INC. v. SSM Health Care System
2003 WI App 137 (Court of Appeals of Wisconsin, 2003)
Teff v. Unity Health Plans Ins. Corp.
2003 WI App 115 (Court of Appeals of Wisconsin, 2003)
Hartlove v. Maryland School for Blind
681 A.2d 584 (Court of Special Appeals of Maryland, 1996)
Roy Cadek v. Great Lakes Dragaway, Inc.
58 F.3d 1209 (Seventh Circuit, 1995)
Norwest Bank Wisconsin Eau Claire, N.A. v. Plourde
518 N.W.2d 265 (Court of Appeals of Wisconsin, 1994)
Capen Wholesale, Inc. v. Probst
509 N.W.2d 120 (Court of Appeals of Wisconsin, 1993)
Wisconsin Dairies Cooperative v. Citizens Bank & Trust
467 N.W.2d 124 (Wisconsin Supreme Court, 1991)
R.S. Deering Mechanical Contractors v. Livesey Co.
468 N.W.2d 758 (Court of Appeals of Wisconsin, 1991)
Olympia Hotels Corp. v. Johnson Wax Development Corp.
908 F.2d 1363 (Seventh Circuit, 1990)
Pollack v. Calimag
458 N.W.2d 591 (Court of Appeals of Wisconsin, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
445 N.W.2d 717, 151 Wis. 2d 695, 1989 Wisc. App. LEXIS 706, Counsel Stack Legal Research, https://law.counselstack.com/opinion/loehrke-v-wanta-builders-inc-wisctapp-1989.