Locus Construction Co. v. Holley

524 S.W.2d 357, 1975 Tex. App. LEXIS 2749
CourtCourt of Appeals of Texas
DecidedMay 22, 1975
DocketNo. 18582
StatusPublished

This text of 524 S.W.2d 357 (Locus Construction Co. v. Holley) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Locus Construction Co. v. Holley, 524 S.W.2d 357, 1975 Tex. App. LEXIS 2749 (Tex. Ct. App. 1975).

Opinion

AKIN, Justice.

Locus Construction Company sued to recover money alleged to be fraudulently converted for the use and sole benefit of the defendant William Holley, a former executive vice president of Locus. Locus joined National Surety Corporation as a defendant to recover money allegedly due under a blanket position bond insuring Locus against any loss of money or other property which Locus sustained through any fraudulent or dishonest acts of any of its employees. Holley filed a counterclaim against Locus contending that Locus was indebted to Holley in the sum of $17,851 for services performed and moving expenses. Prior to submission of the case to the jury, Locus and Holley stipulated that Locus was entitled to recover from Holley the sum of $12,885.34 and that Holley was entitled to recover from Locus the sum of $5,660.73. The jury found that Holley should be paid $9,522.50 for services rendered and relocation expenses.

Based upon the jury’s verdict and the stipulations of the parties, the trial court entered judgment that Locus take nothing from National Surety and that Holley recover from Locus the sum of $2,797.89 (the difference between the stipulated sums and the jury’s award of money to Holley). Locus appeals.

Three questions are presented by this appeal: (1) Did the trial court err in failing to grant a new trial because the jury’s answer in the negative to special issue number one was against the great weight and preponderance of the evidence? (2) Was Holley entitled to compensation awarded by the jury for services rendered after September 1971, the month for which Holley received his final monthly salary from Locus pursuant to the April 1971 agreement? (3) Did the trial court err in submitting to the jury the question of whether Holley should be reimbursed for his relocation expenses incurred upon his return to Dallas after termination of employment? We answer the first and third questions in the negative and the second in the affirmative. We, therefore, affirm the judgment of the trial court.

Facts

From 1966 through part of 1972, Holley was employed by Locus as executive vice president in charge of all construction projects. In April 1971, Locus decided to discontinue its construction business. Locus’s president and Holley agreed to a plan to complete all existing contracts. This agreement was reduced to writing in a memorandum dated April 27, 1971, from Locus’s president to Holley. The agreement, provided among other things, that for a period of three months Holley was to be paid a salary of $1500 per month by Locus and that he was to receive a rent-free office for the guaranty period of a project known as the Arbrook job; and that Holley would handle any guaranty work on all jobs during the three-month period for cost plus ten percent with no eharge for Holley’s time. Pursuant to this agreement Holley continued the operation of Locus’s construction project. Holley was unable to complete all projects within the three-month period set forth in the memorandum because one of Locus’s subcontractors was unable to honor its contract on the Arbrook project due to financial difficulties. Completion of the Arbrook job was, therefore, substantially delayed.

In connection with the Arbrook project, Accent Electronics billed Locus in June 1971 for certain sound equipment it furnished. Holley directed Locus to make payments to Accent in the sum of $8,053.20 and, thereafter, invoiced Arbrook in his own name for this amount plus a profit. Holley received these funds from Arbrook but did not reimburse Locus. In November 1971, Holley entered the $8,053.20 in Locus’s books as an account payable to Locus by Holley. This transaction was the basis of Locus’s alleged cause of action against both Holley and National Surety.

[359]*359In October 1971, Holley advised Locus’s president that he could no longer continue to operate under the terms of the April 1971 agreement because of the delay precipitated by the subcontractor’s insolvency. Locus’s president advised Holley that he should continue with the project until completion, and that payment for Holley’s additional services would be negotiated at a later time. No such negotiations, however, took place. Holley continued to work on Locus’s contractual commitments until late September 1972, when the problems relating to the Arbrook project were finally solved. This litigation ensued.

(1) Was the Answer to Special Issue Number One Against the Great Weight and Preponderance of the Evidence?

In attacking the take-nothing judgment against National Surety, Locus contends that the trial court erred in failing to grant a new trial because the jury’s answer to special issue number one is against the great weight and preponderance of the evidence. The jury answered in the negative the following question: “Do you find from a preponderance of the evidence that Holley caused Locus to expend $8,053.20 of Locus’s funds to pay for materials upon which only Holley benefitted ? ” [Emphasis added.] We cannot agree with Locus’s contention. It is undisputed that Holley caused Locus to expend the $8,053.20 to pay for materials on the Arbrook job; however, the phrase “upon which only Holley benefitted” is disputed. This language can be construed reasonably under the evidence that both Holley and Locus benefitted; hence, the jury’s answer is supported by evidence in the record. A fair construction of the evidence is that Locus benefitted because it was obligated to complete its contract with Arbrook. Indeed, this was the very basis of Locus’s memorandum agreement with Holley. We hold that the jury’s answer was not against the great weight and preponderance of the evidence.

(2) Compensation For Services Rendered after September 1971

With reference to Holley’s counterclaim for services rendered under the theory of quantum meruit the jury was asked the following question:

Do you find from a preponderance of the evidence that Holley at the insistence and request of Locus performed additional services for the benefit of Locus in excess of those services described in plaintiff’s exhibit one [the April 27, 1971 agreement].

The jury answered this question in the affirmative. Locus contends that there is no evidence or in the alternative, insufficient evidence, to support the jury’s response. We disagree.

Locus’s president admitted that subsequent to April 1971, he and Holley had at least two telephone conversations during which Holley objected to the compensation provisions of the April 27,1971, agreement. During these conversations, Locus’s president instructed Holley to “go ahead with it [the contract work] and we will work it out [your compensation].”

Holley testified that he worked full time for Locus until April 1972, and part-time thereafter until September 1972. This additional work was primarily the result of the insolvency of Locus’s mechanical subcontractor on the Arbrook project. This caused many unanticipated problems such as warranty disputes with the subcontractor’s suppliers for equipment delivered but improperly installed. Holley employed additional personnel and personally directed them to complete the subcontractor’s guaranty work. The uncontroverted evidence supports the jury’s finding that work in addition to that contemplated by the memorandum agreement was performed by Holley and assented to by Locus.

Locus also argues that there is no evidence or, in the alternative, insufficient evi[360]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United Founders Life Insurance Company v. Carey
363 S.W.2d 236 (Texas Supreme Court, 1962)
Garza v. Alviar
395 S.W.2d 821 (Texas Supreme Court, 1965)
Lone Star Gas Co. v. X-Ray Gas Co.
164 S.W.2d 504 (Texas Supreme Court, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
524 S.W.2d 357, 1975 Tex. App. LEXIS 2749, Counsel Stack Legal Research, https://law.counselstack.com/opinion/locus-construction-co-v-holley-texapp-1975.