Lobo Recording Corp. v. Waterland

197 F.R.D. 23, 2000 U.S. Dist. LEXIS 15319, 2000 WL 1553518
District Court, E.D. New York·Decided September 5, 2000·No. No. 98-CV7486·Published·Cited by 2 cases

Opinion

MEMORANDUM OF DECISION AND ORDER

SPATT, District Judge.

This diversity action involves allegations of breach of warranty, negligence, and fraud by the Plaintiff Lobo Recording Co. (“Lobo”) against Defendant Waterland Design (“Waterland”) and its owner Vincent Van Haaff, with regard to the design of a recording studio. Presently before the Court is the Defendants’ motion to amend their answer to add additional counterclaims and interpose a third-party complaint.

BACKGROUND

In August 1997, Lobo contacted Waterland and its owner, Van Haaff, to discuss the possibility of Waterland designing a recording studio for them and refurbishing two existing studios owned by Lobo. On September 20, 1997, Waterland submitted a set of design proposals for the renovation of several existing recording studios and the construction of a new “Studio A” in a building owned by Lobo in Deer Park, New York.

Lobo commenced construction of Studio A according to Waterland’s plans in April 1998. According to the complaint, “construction and project management were under the control and supervision of Waterland and Van Haaff.” At some point, problems arose with the construction that gave rise to the instant lawsuit.

According to Lobo, Waterland’s plans were insufficiently detailed to construct the studios; the plans were not in compliance with building code provisions; and they failed to include conduits for wiring suitable to meet Lobo’s needs, among other things. Lobo alleges that, because of the defective construction, it was required to destroy and rebuild all three studios, and has incurred more than a million dollars in damages and lost profits. On December 4, 1998, Lobo commenced this action against Waterland and Van Haaff, claiming breach of contract, breach of warranty, and negligence.

On March 3, 1999, Waterland and Van Haaff filed an answer denying Lobo’s accusations and alleging numerous counterclaims. According to the Defendants, during the initial planning stages of the project, they advised Lobo that construction of the studios would require numerous professionals, including architects, structural engineers, electrical engineers, and air conditioning engineers specifically experienced in the construction of recording studios. Lobo instead retained contractors and architects with no experience working on studios, and who were therefore unable to carry out the plans designed by Waterland. In addition, the Defendants contend that Lobo began construction before full technical details could be obtained; Lobo caused certain construction tasks to be performed out of sequence; and Lobo refused to spend additional money to remedy the problems as per Van Haaffs suggestions. The Defendants raised counterclaims for monies due and ow[25] ing in the sum of $39,000 plus interest; for an account stated; and based on quantum meruit. In addition, the Defendants alleged that Lobo was advertising its studios as being designed by Van Haaff and Waterland, even though the completed studios, although originally based on Van Haaffs designs, are inferior to Waterland’s standards. Accordingly, the Defendants also raised counterclaims under the Lanham Act; for dilution of trademark under N.Y. Gen. Business Law § 368 — d; for common law unfair competition; and for wrongful use of Van Haaffs name under the New York Civil Rights Law § 50.

After issue was joined, the parties proceeded to discovery, including depositions of Van Haaff and Lobo’s President, Carlos Aviles. On November 10,1999, Lobo filed an amended complaint, adding a cause of action for fraud on the grounds that Van Haaff held himself out as an architect and Waterland as an “architectural design company” when, in fact, Van Haaff was not an architect. Lobo also added a cause of action seeking a refund of fees paid to the Defendants on the ground that Van Haaff, not being an architect, was not permitted to charge for architectural services. On January 18, 2000, the Defendants filed an answer to the amended complaint, including only their original counterclaims.

On March 2, 2000, the Defendants filed the instant motion to amend their answer to add additional counterclaims and a third-party complaint against Aviles, Lobo’s President. The proposed counterclaims and third-party complaint allege that Van Haaffs studio designs constitute “trade secrets,” and that Lobo and Aviles misappropriated those trade secrets by providing them to “third-party competitors” of the Defendants who had been hired by Lobo as “replacement studio designer[s]” without Van Haaffs or Water-land’s permission. The proposed counterclaims and third-party complaint allege misappropriation of trade secrets; direct and contributory copyright infringement; and common law copyright infringement relating to Lobo and Aviles turning over the plans to these third-parties.

On April 14, 2000, shortly after briefing had been completed on the Defendants’ motion, United States Magistrate Judge Michael Orenstein certified discovery as complete, pending the Court’s determination of the motion. Judge Orenstein indicated that if the motion was denied, the ease would be ready for trial, but if the Defendants’ motion was granted, the Plaintiff could seek to reopen discovery on the new counterclaims.

DISCUSSION

Because the Defendants wish to add counterclaims, the provisions of Fed. R. Civ. P. 13 come into play. Rule 13(a) requires a defendant serving an answer to plead any counterclaims “arising] out of the transaction or occurrence that is the subject of the opposing party’s claim” that the party knows about. Here, at the time the Defendants filed their answer to the amended complaint on January 18, 2000, they were already aware of the facts giving rise to the proposed “trade secrets counterclaims,” since they admit they learned of those facts at the deposition of Jeff Glixman, Lobo’s manager, in November 1999. The Defendants do not deny that the trade secrets counterclaims arise out of the same transaction as Lobo’s complaint; indeed the Defendants allege that the two matters are inextricably entwined. Therefore, the Defendants’ failure to assert these counterclaims in its January 18, 2000 answer to the amended complaint requires treating the instant motion as one under Rule 13(f) to excuse the omission of a compulsory counterclaim. Rule 13(f) states that “[wjhen a pleader fails to set up a counterclaim through oversight, inadvertence, or excusable neglect, or when justice requires the pleader may by leave of court set up the counterclaim by amendment.”

Free access — add to your briefcase to read the full text and ask questions with AI

Lobo Recording Corp. v. Waterland, 197 F.R.D. 23, 2000 U.S. Dist. LEXIS 15319, 2000 WL 1553518 (E.D.N.Y. 2000).

197 F.R.D. 23 (Lobo Recording Corp. v. Waterland) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Collection Center, Inc. v. Bydal
2011 ND 63 (North Dakota Supreme Court, 2011)
State v. Tompkins
2011 ND 61 (North Dakota Supreme Court, 2011)