Lobar, Inc. v. Lycoming Masonry, Inc.

876 A.2d 997, 2005 Pa. Super. 201, 2005 Pa. Super. LEXIS 1357
CourtSuperior Court of Pennsylvania
DecidedJune 1, 2005
StatusPublished
Cited by5 cases

This text of 876 A.2d 997 (Lobar, Inc. v. Lycoming Masonry, Inc.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lobar, Inc. v. Lycoming Masonry, Inc., 876 A.2d 997, 2005 Pa. Super. 201, 2005 Pa. Super. LEXIS 1357 (Pa. Ct. App. 2005).

Opinion

OPINION BY BENDER, J.:

¶ 1 Lycoming Masonry, Inc. (Defendant) appeals from the order denying part of its motion for summary judgment against Lobar, Inc. (Plaintiff). Plaintiff brought suit against Defendant on two counts; one count for breach of contract and a second count for promissory estoppel. Defendant moved for summary judgment on both counts. The trial court concluded that no contract was formed between the parties, and therefore, it granted Defendant’s motion for summary judgment on the count for breach of contract. But the court denied the motion for summary judgment on Plaintiffs claim for promissory estoppel. For the following reasons, we reverse.

¶ 2 The trial court summarized the facts of this case as follows:

Plaintiff is a general contractor which, in the process of bidding on a job, obtained a bid for the masonry work from Defendant, a masonry subcontractor. Plaintiff used Defendant’s number in *998 calculating its own bid and upon being awarded the contract, informed Defendant it was choosing Defendant to perform the masonry work. Plaintiff sent a written sub-contract agreement to Defendant but Defendant refused to sign such. Plaintiff then rebid the masonry work and entered a subcontract agreement with another masonry subcontractor, at a much higher cost. Plaintiff brought the instant action to recover the difference in what it had to pay the other subcontractor over what Defendant bid to do the job, based on both a breach of contract claim and a claim of promissory estoppel.
In its motion for summary judgment, Defendant contends the facts support neither theory. Specifically, Defendant contends no contract was entered because the terms of the subcontract agreement sent to it by Plaintiff differed substantially from the terms of the bid, thus constituting a counter-offer, rather than an acceptance of the bid.... In its motion for summary judgment, Plaintiff contends that indeed a contract was formed and further, that promissory es-toppel should be applied to support a judgment in its favor.
The parties do agree that Defendant’s bid was an offer. Plaintiff contends such offer was accepted by its use of Defendant’s bid in submitting its own bid to the owner. Defendant contends, however, that since the subcontract agreement sent to it by Plaintiff contained terms substantially different from the terms of the bid, Plaintiff did not accept its offer but instead returned a counter-offer.
It is also undisputed that Plaintiffs insistence [that] Defendant use a certain type of Concrete Masonry Units, much more expensive than the type Defendant hoped to use, played a large part in Defendant’s refusal to follow through on its bid, and the Court finds as a fact that this insistence was actually the only reason.[FN.7] Further, there is no dispute the written specifications for the project upon which Defendant relied required the use of the more expensive type of Concrete Masonry Units, and Defendant was fully aware of this fact.
[FN.7] While Defendant contends in the instant litigation this was only one factor, arguing the differences in the terms of the subcontract agreement led to its refusal to perform, other circumstances belie this contention: Defendant has signed the same subcontract agreement more than once in the past, and, in fact, when Plaintiff rebid the work in this particular matter,. Defendant submitted a new bid knowing full well the same subcontract agreement would follow, yet never mentioned any disagreement with any of the terms of such. .

Trial Court Opinion (T.C.O.), 7/20/04, at 1-2, 4-5.

¶ 3 After both parties filed motions for summary judgment, the trial court denied Plaintiffs motion in its entirety. The trial court granted Defendant’s motion for summary judgment on Plaintiffs breach of contract count and denied it on the promissory estoppel count. Defendant subsequently filed a petition for permission to appeal pursuant to Pa.R.A.P. 1311, which this Court granted. Our order granting review limited the scope of our review to the issue of the denial of Defendant’s motion for summary judgment on the promissory estoppel claim. In its brief, Defendant has presented two questions for our review:

A. Because the issue of whether Ly-coming Masonry is liable to Lobar can *999 be determined using contractual principles of offer and acceptance, was it error for the lower court to apply the doctrine of promissory estoppel?
B. Alternatively, did the lower court commit error by applying the doctrine of promissory estoppel to the construction bidding process?

Brief for Appellant at 3. 1 It is important to note that the propriety of the court’s grant of summary judgment to Defendant on the breach of contract count is not presently before us. 2

¶ 4 Our scope and standard of review of a court’s ruling on a motion for summary judgment is as follows:

Our scope of review of a trial court’s order disposing of a motion for summary judgment is plenary.... Our standard of review is the same as that of the trial court; thus, we determine whether the record documents a question of material fact concerning an element of the claim or defense at issue. If no such question appears, the court must then determine whether the moving party is entitled to judgment on the basis of substantive law.

Stanton v. Lackawanna Energy, Ltd., 820 A.2d 1256, 1258 (Pa.Super.2003).

¶ 5 Defendant claims that the trial court committed an error of law because it did not follow our Supreme Court’s ruling in Hedden v. Lupinsky, 405 Pa. 609, 176 A.2d 406 (1962), where the court rejected a general contractor’s claim for promissory es-toppel against a subcontractor. Defendant argues that Hedden is controlling precedent. We agree.

¶ 6 In Hedden, the plaintiffs were general contractors and the defendant was a subcontractor. The defendant submitted a bid by telephone to the plaintiffs for ceramic tile work that was to be done as part of the construction of a proposed addition to a hospital. The plaintiffs used the defendant’s bid in calculating its own bid for the entire project, and the general contract was awarded to the plaintiffs.

¶7 The plaintiffs then sent a sub-contract to the defendant, which the defendant refused to sign. The sub-contract contained several clauses that either did not exist in the “General Conditions and General Requirements,” which was within the specifications for the tile work, or conflicted with provisions within the General Conditions and General Requirements. See id. at 407. The court described these inconsistent particulars as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Universal Atl. Sys., Inc. v. Honeywell Int'l, Inc.
388 F. Supp. 3d 417 (E.D. Pennsylvania, 2019)
Benec, P. v. Armstrong Cement & Supply
Superior Court of Pennsylvania, 2016
Arcadia Petroleum Ltd. v. Sun International Ltd.
192 F. App'x 164 (Third Circuit, 2006)
Tyco Electronics Corp. v. Davis
895 A.2d 638 (Superior Court of Pennsylvania, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
876 A.2d 997, 2005 Pa. Super. 201, 2005 Pa. Super. LEXIS 1357, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lobar-inc-v-lycoming-masonry-inc-pasuperct-2005.