Lloyd v. Toledo (City)

31 Ohio C.C. Dec. 192, 20 Ohio C.C. (n.s.) 47
CourtLucas Circuit Court
DecidedJanuary 27, 1912
StatusPublished

This text of 31 Ohio C.C. Dec. 192 (Lloyd v. Toledo (City)) is published on Counsel Stack Legal Research, covering Lucas Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lloyd v. Toledo (City), 31 Ohio C.C. Dec. 192, 20 Ohio C.C. (n.s.) 47 (Ohio Super. Ct. 1912).

Opinion

RICHARDS, J.

The plaintiff brings this action as a taxpayer of the city of Tolédo against the city, its officials, and the C. H. Fath & Son Construction Co., for the purpose of enjoining the construction of a bridge over the Maumee river at Cherry street, under the modifying contract of August 9, 1911, and to enforce its construction under the original contract of March 3, 1910, at the compensation claimed by the plaintiff to be provided therein, and for such further relief as he may be entitled to in equity.

The ease has been submitted to us upon the evidence which Avas introduced in the court of common pleas and a large amount of additional evidence taken before a referee in this court, all of which we have carefully read. The question at issue and the amount involved have been such as to command the most thorough consideration of counsel and of 'this court, and in our deliberation Ave have been greatly aided by the able arguments, both oral and typewritten, of counsel.

It appears from the evidence that the city provided the funds, amounting to $825,000, by the sale of bonds, and having taken the preliminary steps entered into the original contract vvith the C. H. Fath & Son Construction Co., on March 3, 1910, for the construction, of a reinforced concrete arch bridge to be [194]*194built under the directions of engineers appointed by the city. Upon the execution of the original contract the work was commenced by the C. H. Fath & Son Construction Co. and has been proceeded with to the present time. On. August 9, 1911, a supplementary or modifying contract was entered into between said company and the city, through the director of public service, the purpose of which was to modify the original method of construction in various respects.

The original plan contemplated that, by means of cofferdams which could be pumped out, the foundations of the piers should be built in the dry, but in working on pier No. 6 water was encountered which appears to have seriously interfered with pursuing the work under that plan. The method adopted in the original plan was found by the city, on the advice of the consulting engineer, to be not feasible nor safe, especially for piers three and four, which adjoin the channel of the river where the head of water is strongest. By the original contract it was intended to use throughout most of the wells for laying the foundations, wooden lagging supported by iron rings, but the modified contract specifies steel cylinders in lieu thereof. The original contract, however, authorizes the use of shields, metal rings or steel cylinders under certain circumstances, when recommended by the engineers. The use of steel cylinders for the purpose intended is, of course, much more expensive than wooden lagging and iron rings, but the new contract provides for the removal from the work of the steel shields except the lower 24 feet 9 inches, and requires a credit to the city of four cents per pound, while the original contract failed to provide for any credit therefor. The modifying contract also provides for a layer of concrete called a blanket over the entire surface of the cofferdams six to ten feet thick, to be laid under water by means of a tremie pipe or other suitable method, and it further substitutes in certain places timber piles in place of concrete piles. In addition to the items already mentioned, the new contract requires the C. H. Fath & Son Construction Co. to provide a compressed air plant and the city agrees to purchase the same at $6,000, if it should require its use, and to pay the net cost of its operation not exceeding $25 per day. The modifying contract extends [195]*195the time for the completion of the bridge for a period of six months beyond the original contract.

The plaintiff contends that the modifying contract of August 9, 1911, is illegal and void for various reasons, and he asks to have it so adjudged by decree of this court.

The first ground of his contention to which we direct attention is based upon the claim that the city council did not authorize the contract and that it was not approved by the board of control, there being no record of such action by that board. Parol evidence has been received, however, which establishes beyond all question that at a meeting of the board of control the modifying contract was duty approved by a unaimous vote. The secretary was not'present at that meeting. The director of public service informed him soon after the meeting of the action taken by the board, for the purpose of having it recorded, but it was overlooked and no record ever made. In the light of this parol evidence, the charge contained in the petition that the director of public service, John R. Cowell, and the city solicitor, Cornell Sehreiber, entered into and approved the contract without the authority of the board of control wholly fails. The statute requires a record of such action to be made, but we have no doubt that the statute is directory only, and the mere oversight of the clerk or secretary in failing to make a record of action duty taken by the board, can not nullify that action nor invalidate the contract based thereon,. The general rule sustaining that doctrine is laid down in 2, Dillon, Municipal Corporations, 5th ed., Secs. 557 and 558 (Secs. 300 and 301 of 4th ed.) Such was the holding in Drott v. Riverside, 2 Circ. Dec. 565 (4 R. 312), and in many other eases, and the rule appears to be founded on excellent reasons. Dillon’s treatise on municipal corporations has been a well recognized standard authority for a generation, and the author in the sections cited uses the following language:

■ “Where the records of a municipal corporation have been so carelessly, and imperfectly kept as not to show the adoption of a resolution or other acts of the city council, and there is no written evidence in existence, parol testimony may be admitted, e. g., to show that certain work was done by authority of the city, by proving the passage of a resolution of the council, the appoint[196]*196ment of a committee to make the expenditure, their report after the work was done, and its adoption by the council.”

That the contract was not specifically authorized by ordinance passed by the city council is not, in and of itself, sufficient to render it invalid. The municipal code contemplates that the city council shall, in inaugurating an improvement, give authority and make the necessary appropriation and shall-take no further action, but that the business shall be conducted to completion by the board or officer having charge of the came. Section 4331 G. C. vests in the director of public service power to make alterations and modifications upon' approval of the board of control.

We have no doubt of the power of a municipal corporation to change or modify, with the consent of the other contracting party, contracts into which it has entered. Upon this proposition we cite Weston v. Syracuse, 158 N. Y. 274 [53 N. E. 12; 43 L. R. A. 678; 70 Am. St. 472]; Meech v. Buffalo, 29 N. Y. 198; Doland v. Clark, 143 Cal. 176 [76 Pac. 958]; 2 Dillon Municipal Corporations, Sec. 820.

Such being the power and authority of the board of control and the director of public service, we are brought to the claim made by plaintiff that the modifying contract was entered into through fraud and bad faith and was an abuse of discretion on the part of that board and the director of public service.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Doland v. Clark
76 P. 958 (California Supreme Court, 1904)
Weston v. . City of Syracuse
53 N.E. 12 (New York Court of Appeals, 1899)
Meech v. . the City of Buffalo
29 N.Y. 198 (New York Court of Appeals, 1864)
Bank of Pennsylvania v. M'Calmont
4 Rawle 307 (Supreme Court of Pennsylvania, 1833)

Cite This Page — Counsel Stack

Bluebook (online)
31 Ohio C.C. Dec. 192, 20 Ohio C.C. (n.s.) 47, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lloyd-v-toledo-city-ohcirctlucas-1912.