Lloyd A. Ebert v. Village of Gresham

CourtCourt of Appeals of Wisconsin
DecidedOctober 27, 2020
Docket2019AP002178
StatusUnpublished

This text of Lloyd A. Ebert v. Village of Gresham (Lloyd A. Ebert v. Village of Gresham) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lloyd A. Ebert v. Village of Gresham, (Wis. Ct. App. 2020).

Opinion

COURT OF APPEALS DECISION NOTICE DATED AND FILED This opinion is subject to further editing. If published, the official version will appear in the bound volume of the Official Reports. October 27, 2020 A party may file with the Supreme Court a Sheila T. Reiff petition to review an adverse decision by the Clerk of Court of Appeals Court of Appeals. See WIS. STAT. § 808.10 and RULE 809.62.

Appeal No. 2019AP2178 Cir. Ct. No. 2018CV146

STATE OF WISCONSIN IN COURT OF APPEALS DISTRICT III

LLOYD A. EBERT AND KAREN EBERT,

PLAINTIFFS-APPELLANTS,

V.

VILLAGE OF GRESHAM D/B/A ELECTRIC UTILITIES,

DEFENDANT-RESPONDENT,

FRONTIER COMMUNICATIONS OF WISCONSIN, LLC, CHARTER COMMUNICATIONS (CCI), INC. (FICT NAME), CHARTER COMMUNICATIONS, INC. (CORP NAME), CHARTER COMMUNICATIONS, LLC, CHARTER COMMUNICATIONS HOLDING CO., LLC, CHARTER COMMUNICATIONS VI, LLC, CHARTER COMMUNICATIONS OPERATING, LLC AND CHARTER COMMUNICATIONS HOLDINGS (DE), LLC,

DEFENDANTS.

APPEAL from an order of the circuit court for Shawano County: WILLIAM F. KUSSEL, JR., Judge. Affirmed. No. 2019AP2178

Before Stark, P.J., Hruz and Seidl, JJ.

¶1 STARK, P.J. In 2003, the Village of Gresham installed underground electrical wiring within a water main easement on property owned by Lloyd and Karen Ebert. Fourteen years later, in December 2017, the Eberts’ attorney wrote to the Village demanding that it remove the wiring and threatening suit if the Village refused to do so. After the Village failed to comply, the Eberts filed the instant lawsuit, asserting that the presence of the underground wiring on their property constituted a continuing trespass and seeking a declaratory judgment and injunctive relief. The Village moved to dismiss the Eberts’ lawsuit, arguing they had failed to comply with the notice of claim statute, WIS. STAT. § 893.80 (2017-18).1 The circuit court granted the Village’s motion, concluding the Eberts were required— but failed—to file a notice of injury within 120 days of the date the wiring was installed.

¶2 The Eberts now appeal, arguing that because the underground wiring constitutes a continuing trespass, a new “event” for purposes of the notice of claim statute occurs every day that the wiring remains on their property. The Eberts therefore argue that the notice of injury they provided to the Village in December 2017 was timely. The Eberts also argue that we should recognize and

1 All references to the Wisconsin Statutes are to the 2017-18 version unless otherwise noted.

The notice of claim statute contains two notice provisions that serve different purposes. See Yacht Club at Sister Bay Condo. Ass’n, Inc. v. Village of Sister Bay, 2019 WI 4, ¶19, 385 Wis. 2d 158, 922 N.W.2d 95. This case involves the “notice of injury” provision set forth in WIS. STAT. § 893.80(1d)(a), rather than the “notice of claim” provision set forth in § 893.80(1d)(b). See Yacht Club, 385 Wis. 2d 158, ¶20. Thus, although the parties and the circuit court framed the issue as whether the Eberts had timely filed a “notice of claim,” we refer to the relevant notice as a “notice of injury.” However, we refer to the statute as a whole as the “notice of claim statute,” in accordance with past case law. See id., ¶19.

2 No. 2019AP2178

apply an exception to the notice of claim statute under the specific circumstances of this case. We reject the Eberts’ arguments and affirm.

BACKGROUND

¶3 The following facts are undisputed, unless otherwise noted. The Eberts own property in the Village, which they purchased in 1998. Their property is subject to a water main easement, which was recorded with the Shawano County Register of Deeds on May 21, 1990. The recorded easement grants the Village “a perpetual easement for the purpose of maintaining an existing water[ ]main in, upon and over” a thirty-foot-wide corridor located along the western boundary of the Eberts’ property.

¶4 The Village is a public utility and provides electricity to properties located in the Village. Sometime in 2003, the Village caused underground electrical wiring to be installed within the water main easement on the Eberts’ property. The Eberts did not receive any compensation from the Village for its installation of the wiring.

¶5 At the time the wiring was installed, Lloyd Ebert was the Village’s administrator. Ebert contends that in 2003, he notified Kenneth Beyer, the Village’s then-president, that the underground wiring exceeded the scope of the water main easement. Beyer, however, denies that any such conversation took place. It is undisputed that the Eberts did not file any written notice of injury with the Village regarding the electrical wiring at any point during 2003.

¶6 Instead, on December 7, 2017—approximately fourteen years after the wiring was installed in the water main easement—the Eberts’ attorney sent a letter to the Village asserting that there was no utility easement permitting the

3 No. 2019AP2178

presence of electrical wiring on the Eberts’ property. As such, counsel asserted the wiring constituted “a continuing trespass and an unlawful intrusion” on the Eberts’ property. Counsel advised the Village that the Eberts planned to file suit if the wiring was not removed by January 31, 2018. The Eberts’ attorney sent a second letter to the Village on January 30, 2018, again asserting that the wiring constituted a continuing trespass. The Village’s attorney responded on April 27, 2018, and substantially denied the Eberts’ claims.

¶7 On July 5, 2018, the Eberts filed the instant lawsuit against the Village, asserting claims for: (1) continuing trespass; and (2) physical injury or interference with real property under WIS. STAT. § 844.01(1).2 As relief, the Eberts sought a declaratory judgment, an injunction requiring the removal of the wiring, and a finding that the Village was “occupying the Ebert Property without having the right to do so.”

¶8 The Village moved to dismiss the Eberts’ claims, arguing the Eberts had failed to comply with the notice of claim statute.3 Although denominated as a motion to dismiss, the Village submitted evidentiary materials in support of its motion. The parties and the circuit court therefore treated the motion as a motion

2 The Eberts’ complaint also asserted claims against Frontier Communications of Wisconsin, LLC, which had installed underground telephone wiring in the water main easement sometime after 2001, and Charter Communications, which had installed underground cable wiring in the easement in 2017. The Eberts ultimately settled their claims against Frontier and Charter, and those parties were dismissed from this lawsuit. As a result, we do not further address the Eberts’ claims against Frontier and Charter. 3 The Village also argued dismissal was warranted because the Eberts’ claims were barred by the applicable statute of limitations. In the alternative to its motion to dismiss, the Village moved for a more definite statement under WIS. STAT. § 802.06(5). However, the Village later voluntarily withdrew both its motion to dismiss on statute of limitations grounds and its motion for a more definite statement.

4 No. 2019AP2178

for summary judgment, and the Eberts submitted their own evidentiary materials in opposition to the motion.

¶9 The circuit court ultimately granted the Village’s motion and entered an order dismissing the Eberts’ claims. The court concluded that under WIS. STAT. § 893.80(1d)(a), the Eberts were required to provide the Village with a written notice of injury within 120 days after the underground electrical wiring was installed in the water main easement in 2003. The court further found that the Eberts did not provide a written notice of injury until their attorney wrote to the Village on December 7, 2017—long after the 120-day notice period had expired.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hardy v. Hoefferle
2007 WI App 264 (Court of Appeals of Wisconsin, 2007)
Vanstone v. Town of Delafield
530 N.W.2d 16 (Court of Appeals of Wisconsin, 1995)
Gillen v. City of Neenah
580 N.W.2d 628 (Wisconsin Supreme Court, 1998)
State Ex Rel. Kalal v. Circuit Court for Dane County
2004 WI 58 (Wisconsin Supreme Court, 2004)
Aicher Ex Rel. LaBarge v. Wisconsin Patients Compensation Fund
2000 WI 98 (Wisconsin Supreme Court, 2000)
E-Z Roll Off, LLC v. County of Oneida
2011 WI 71 (Wisconsin Supreme Court, 2011)
Munger v. Seehafer
2016 WI App 89 (Court of Appeals of Wisconsin, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Lloyd A. Ebert v. Village of Gresham, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lloyd-a-ebert-v-village-of-gresham-wisctapp-2020.