Lizza and Sons, Inc. v. Daniel A. D'OnfrO

282 F.2d 175, 1960 U.S. App. LEXIS 3826
CourtCourt of Appeals for the First Circuit
DecidedAugust 18, 1960
Docket5571_1
StatusPublished
Cited by3 cases

This text of 282 F.2d 175 (Lizza and Sons, Inc. v. Daniel A. D'OnfrO) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lizza and Sons, Inc. v. Daniel A. D'OnfrO, 282 F.2d 175, 1960 U.S. App. LEXIS 3826 (1st Cir. 1960).

Opinion

HARTIGAN, Circuit Judge.

This is an appeal from a judgment of the United States District Court for the District of Massachusetts entered May 29, 1959 dismissing plaintiff’s complaint against the defendants.

Plaintiff, Lizza and Sons, Inc. [hereinafter referred to as Lizza], is a general construction contractor. Lizza was awarded a contract by the Massachusetts Turnpike Authority for construction of the Lee-Becket section of the Massachusetts Turnpike. Defendants D’Onfro are members of the same family who as partners do business as Daniel D’On-■fro’s Sons. This partnership [hereinafter referred to as D’Onfro’s Sons] is also a contractor in the construction business. Hartford Accident and Indemnity Company [hereinafter referred to as Hartford] is an issuer of contract and performance bonds.

Plaintiff alleged in its complaint that D’Onfro’s Sons agreed with Lizza to build on subcontract various items on bridge and culvert structures involved in the Lee-Becket section of the Turnpike, and that Hartford had issued a performance bond in favor of Lizza. Plaintiff further alleged D’Onfro’s Sons had breached its contract and Hartford had not performed on its bond, and sought judgment from D’Onfro’s Sons and Hartford for damages, interest and costs.

Defendants answered denying the existence of any agreement between Lizza and D’Onfro’s Sons, and denying any breach of contract or damage to Lizza. Hartford also alleged that since there was no contract between Lizza and D’On- *177 fro’s Sons there was no basis for liability on the part of Hartford. 1

After trial before the court, judgment was entered for the defendants dismissing the plaintiif’s complaint. The district court made findings and conclusions that may be summarized as follows. In May 1955 Lizza asked D’On-fro’s Sons to submit quotations for the structures on the Lee-Becket section. Lizza used the quotations of D’Onfro’s Sons in making its bid on the section. Following the opening of the bids, Lizza met with Daniel and Ralph D’Onfro and insisted that D’Onfro’s Sons take $8,000 less than its total quotation. On J,uly 13, 1955 Ralph and Daniel D’Onfro went to Lizza and generally discussed the work to be covered by the subcontract and the price. No agreement was reached but Lizza was to draft a contract and if D’Onfro’s Sons liked it they would execute it. On July 19 Lizza sent a draft to D’Onfro’s Sons.

A week later Daniel D’Onfro conferred with Joseph F. Marino, project manager of Lizza, at Lizza’s Oyster Bay, New York office. Daniel D’Onfro brought with him a letter setting out D’Onfro’s Sons objections to the draft. He also brought two bonds in favor of Lizza, each of which recited that “the Principal [D’Onfro’s Sons] had entered into a certain written contract with the Obligee [Lizza] dated the 26th day of July.” At their conference Marino and Daniel D’Onfro discussed the suggested changes desired by D’Onfro’s Sons. They reached a general but loose understanding, and each recognized there would have to be precise draftsmanship. The tenor of the conference indicated that the two men were considering possible amendments to a draft. Daniel D’Onfro at the end of the conference said he would be satisfied “if it is all put into the other contract.” By this Daniel D’Onfro indicated he intended not to be bound except by precise words spelled out in a written agreement.

Marino prepared a new draft on July 27. D’Onfro’s Sons rejected the draft. Lizza made no claim that there had been an overall oral agreement of which this draft was a memorial.

In the middle of August D’Onfro’s Sons prepared a draft and procured a new bond from Hartford. This bond also recited: “the Principal has enter-

ed into a certain written contract with the Obligee dated the 26th of July, 1955.” 2 Lizza received the bond and draft but never assented to the draft.

In September D’Onfro’s Sons submitted another draft to Lizza. Lizza made deletions and thereafter signed it. D’On-fro’s Sons never manifested assent to these deletions.

As a matter of ultimate fact no contract between the parties was made on July 26, 1955 or on any other date. This is based on the following considerations. On July 13, 1955 Ralph D’Onfro asked for a written draft. On July 19 Lizza sent a complicated document. The main theme of the July 26 conference was a set of possible amendments to the draft. As to these amendments there was no precise agreement. Marino’s notations of “rewrite” and “reword” manifest an intention to do more than merely record a perfected agreement. Daniel D’Onfro’s words at the conclusion of the conference manifest an intention not to be bound before the changes were put in writing and executed formally. After *178 the July 26 conference both parties acted as though each knew the other manifested an intention at the conference to be bound only by a solemnly executed writing. This is the most likely inference from the subsequent correspondence, the preparation of other drafts and the failure of either party to suggest that there had been a complete agreement.

Since Lizza and D'Onfro's Sons never manifested assent to any agreement there was no contract the performance of which Hartford could guarantee. Hartford is, therefore, not liable to the plaintiff on its bond.

In this appeal plaintiff alleges error (1) in various findings and conclusions of the district court in regard to any agreement between Lizza and D’Onfro’s Sons and (2) in the district court’s conclusion of no liability as to defendant Hartford.

Plaintiff relies heavily on the testimony of Marino to demonstrate the error of the district court’s findings that the purpose of the July 26 conference was to consider possible amendments to the draft and that Marino and Daniel D’Onfro reached only a “general but loose understanding” on those amendments. However, the testimony of Marino was clearly not credited by the district court, since Marino testified to complete agreement by Daniel D’Onfro to the changes precisely as made by Marino in the July 27 draft. Since this testimony was not credited by the district court and its rejection is not lightly to be overturned by an appellate court, F.R. Civ.P. 52(a), 28 U.S.C.A., we are not convinced that these findings of the district court were clearly erroneous. There is support for the view of the conference taken by the district court in the documents used at that conference and in the deposition of Daniel D’Onfro and the district court had an opportunity to observe the witness, Marino, and judge of his credibility.

Plaintiff also strongly contends that the district court erred in its inference from the testimony and the documentary evidence that Daniel D’Onfro manifested an intent not to be bound until the execution of a written document. Plaintiff further contends that there is error in the district court’s inference of the same intent from the conduct of Lizza and D’Onfro’s Sons subsequent to the conference of July 26. However, we do not believe that these inferences are unreasonable in view of the whole record. Nor are we persuaded that the inferences which plaintiff urges are more likely than those made by the district court. Accordingly we find no basis for rejecting the district court's inferences and the conclusions based on them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
282 F.2d 175, 1960 U.S. App. LEXIS 3826, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lizza-and-sons-inc-v-daniel-a-donfro-ca1-1960.