Livingston v. Scully

38 La. Ann. 781
CourtSupreme Court of Louisiana
DecidedOctober 15, 1886
DocketNo. 180
StatusPublished
Cited by12 cases

This text of 38 La. Ann. 781 (Livingston v. Scully) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Livingston v. Scully, 38 La. Ann. 781 (La. 1886).

Opinion

Tlie opinion of the Court was delivered by

Watkins, J.

Plaintiff sues for the recovery of $5000 damages, resulting from defendant’s alleged violation of his contract; $870.62 on open account; and for the annulment of the contract.

The contract was entered into on July 1, 1882, and contains reciprocal covenants.

Plaintiff agreed to furnish all labor,’ tools, cement aud all other material to he used in the piers of said bridge,” (the railroad bridge across Red River at Shreveport), and set the same in the piers, to the full satisfaction of the engineer in charge, for the sum of $8 per cubic yard.

[783]*783“ He also agrees to set cut stone facings for said piers, to be furnished at railroad bridge site, and furnish all labor, cement, tools and other materials to be used in construction of same, for $6 per cubic yard, payments of ninety per cent to be paid by said Peter Scully, on or about the 15th of each month, or as soon as received and paid by the railroad company.” The remainder was to be paid upon the completion of the work and its acceptance by the railroad company.

All the work was to be done under the supervision of the engineer, in charge, and to his full satisfaction.

It further stipulated that plaintiff should “ push the work, and give it his own personal attention, and finish said work on or about the 1st of January, 1883.

Under this contract defendant undertook “ to furnish foundations and such tools as he may have to spare, on work, free of cost,” etc.

Plaintiff alleges that Scully “made a subsequent verbal agreement with him to pay for all necessary building material contracted for, to those delivering the material, about the 15th of the month ; and also, that he would furnish and deliver to petitioners all the cement needed for building said piers at $1.25 per barrel.

He shows that he was on “ hand promptly with men and material, and the necessary arrangements to do and complete the work according to contract:” and had made some contracts for materials, such as sand, brick, etc., to be furnished; and that he was put to a heavy expense therefor, and “ did bis part Of the work in due time, and was not in default,” etc.

He represents that he did -‘extra work that was not included in his contract, and furnished money, lumber and material, etc., to Scully,” whereby he became indebted to him in the sum of $870.25, for payment of which demand has been made.

He represents “that said Scully did not have the foundations for the piers ready, so that petitioner could do his part of the work ; that owing to dissensions between said Scully and the railroad company as to who should pay for the sheet pilings, and mistake as to the amount of dredging required for the foundations, and other causes, that said Scully should have foreseen, and provided against, the work was delayed, and petitioner kept idle, and on expenses, without being able to go on with his work.”

He further alleges “ that in consequence of said Scully’s failures to do as he had promised and agreed to, petitioner found himself delayed so long, and at such heavy loss and damage that he was unwilling to suffer it longer; and, even if he had been, that the failure of Mr. Scully to. [784]*784comply with Ms agreement with petitioner in reference to the brick Johnson was to furnish, and the money due, as per account, caused his debts to accumulate, and his credit to be impaired to such an extent that he found it impossible to go on writh the work.”

He shows “that he notified Mr. Scully about the 1st of January, 1883, that he (Scully) had forfeited his right to hold him bound to his contract, and that petitioner could claim damages,” which he estimates to be $5000, for profits of which ho had been deprived.

In plaintiff’s amended petition he states that Scully did not complete the foundation of pier five until September, 1882, and pier six in November, 1882, and that between those dates defendant “ could have had other foundations ready, but that he, by positive order, x>ereniptorily stopped all work on the foundations and piers, and did not permit it to be begun again until about the 1st of November following.”

He avers that he made application to Mr. Alfred Noble in September, the engineer in charge, to have the foundations of x>iers five and six got ready, so that he could go on with his work; and, afterward he made a similar axix>lication to Mr. Patton, representing the defendant, to the same effect, “ and Mr. Patton stated that he could not, and would not, do anything without orders from defendant, and that Scully’s orders were that all work be stojiped,” and that during, this time he was kept idle, and unable to comx>ly with his part of the agreement, and that his time was worth $10 per day for that time.

The defendant, for answer, admits the contract for the construction of the foundations for the piers for the railroad bridge as evidenced by the written agreement of July 1st, 1882, but denies that plaintiff has complied with its terms, and specially denies that plaintiff “ was in any manner forced, or compelled by him to abandon his contract, and quit work, but that said abandonment was the voluntary act of plaintiff, and wilfully done, in order to injure resx>ondent, and retard him in the construction of the bridge that plaintiff has thereby forfeited all rights under it, and has incurred a liability- to him in damages in the sum of $5750; and that he owes him, in addition, the sum of $1029, on open account, for which sums he claims judgment, against the plaintiff in reconvention.

Wo have thus analyzed the x>laintiff’s x>etitions, original and amended, and defendant’s answer, because it has been made an important question in this case whether the defendant was xmt in mora as a condition X>recedent to the institution of this suit.

Defendant’s counsel contend that it is a condition precedent to the recovery of damages, for the passive.violation of a commutative con[785]*785tract, that the obligor must be put in mora, and that this must be alleged and proved.

Plaintiff’s counsel insist that their petition sets out an active, as well as a,passive violation of the written and parol contracts, and that the defendant was put in default antecedent to the institution of this suit.

R. C. C. 1912, provides: “ The effects of being put in default are not only that, in contracts to give, the thing, which is the object of the stipulation, is at the risk of the person in default; hut in the cases hereinafter provided for, it is a prerequisite to a recovery of damages and of profits, and fruits or the rescission of the contract.”

R. C. C. 1913 provides : “In commutative contracts, when reciprocal obligations are to he performed at the same time, or the one immediately after the other, the party who ivishes to put the other in default, must, at the time and place expressed in or implied hy the agreement, offer to perform, as the contract requires, that which on his part was to he performed, otherwise the opposite party will not he legally put in default.”

R. C. C. 1931 provides: “A contract may be violated either actively, by doing something inconsistent with the obligation it has proposed, or passively, by not doing

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Elliott v. Dupuy
127 So. 2d 260 (Louisiana Court of Appeal, 1961)
Goudeau v. Daigle
124 F.2d 656 (Fifth Circuit, 1942)
Greater New Orleans Homestead Ass'n v. Harvey
158 So. 852 (Louisiana Court of Appeal, 1935)
Perry Mill Elev. v. D. A. Varnado Son
147 So. 510 (Louisiana Court of Appeal, 1933)
Oppenheimer v. Bobb
120 So. 523 (Louisiana Court of Appeal, 1929)
Winsberg v. Lasseigne
6 La. App. 699 (Louisiana Court of Appeal, 1927)
Silk v. Crosset Shoe Shop
6 La. App. 42 (Louisiana Court of Appeal, 1927)
McMillan v. Mills
3 La. App. 9 (Louisiana Court of Appeal, 1925)
Pipes v. Payne
101 So. 144 (Supreme Court of Louisiana, 1924)
J. H. Garrison & Son v. Sherill Hardwood Lumber Co.
100 So. 253 (Supreme Court of Louisiana, 1924)
Cousin v. Schmidt
79 So. 427 (Supreme Court of Louisiana, 1918)
State v. Brown
52 So. 176 (Supreme Court of Louisiana, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
38 La. Ann. 781, Counsel Stack Legal Research, https://law.counselstack.com/opinion/livingston-v-scully-la-1886.