Livesey v. Festner

44 N.W. 441, 28 Neb. 333, 1889 Neb. LEXIS 351
CourtNebraska Supreme Court
DecidedDecember 31, 1889
StatusPublished

This text of 44 N.W. 441 (Livesey v. Festner) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Livesey v. Festner, 44 N.W. 441, 28 Neb. 333, 1889 Neb. LEXIS 351 (Neb. 1889).

Opinion

Cobb, J.

This cause was appealed from the district court of Douglas county.

The appellee complained in the court below that on April 21,1887, he entered into a written contract with the appellant to furnish the material and labor necessary to build and complete in a good, first-class, and workmanlike manner the mason and brick work, excavating, concreting, pressed brick, and cut stone work for the erection of a brick store building on the east half of lot 2, in block 167, in Omaha, in said county. A copy of the contract was exhibited. For this work the appellant agreed to pay the appellee the sum of $5,100. It was also agreed that the appellee should do extra digging and concreting for the sum of $198, and extra brick work in the basement and first story for the sum of $120, which sums the appellant agreed to pay. In pursuance of which the appellee alleged that he performed all the work, and furnished all the materials required and specified under said contracts, for the erection of said building between April 21 and August 1, 1887, amounting in the'aggregate to the sum of $5,418, and other extra work amounting to $7 additional. The appellant at the time was the owner in fee of said lot.

It was alleged that on November 1, 1887, within four months of the time of doing said work and furnishing said materials, the appellee made an account in writing of the [335]*335amount and value of the same, and, after making oath thereto, filed the same, together with the contract, in the clerk’s office of said, county, and thereby claimed a mechanic’s lien on said lot and buildings for the unpaid balance due him from the appellant under said contract, which was $886, there having been paid prior to said last date the sum of $4,530 ; and there was paid for filing the lien, fees of $3.25; that said sum of $886, with interest at seven per cent per annum from November 1,1887, and the fees for recording the lien remain due and upaid thereon. The appellee asked judgment for the amount due and costs and that the premises be sold to pay the same, etc.

The appellant answered, in the court below, admitting that on April 21, 1887, he entered into a written contract as in the appellee’s petition set forth, but denying that appellee performed all the work required of him under said contract, or that he furnished the materials specified. He further set up that the appellee did not build the wall, or lay in concrete, as in the contract required; that said wall was to be used as a party wall; that appellee knew of this fact, and that the concrete was to be made of the depth of twenty inches, and was but fourteen inches, and that when so laid appellant was to receive from'adjoining property owner one-half of the cost of its erection, but that by reason of the failure of appellee to do as contracted, appellant was greatly damaged in the sum of $1,000. And he further averred that the appellee did not receive, nor had he received up to that date, a certificate from the architect entitling him to final payment; and demanded judgment for the difference of said sums in $110.75, and that the lien of appellee be removed.

The appellee replied denying each and every allegation of the answer.

There was a trial to the court without a jury, upon the petition, answer, replication, and evidence; on consideration whereof the court found there was due to the appellee from [336]*336the appellant, on account of the matters set forth in the petition, the sum of $922.78 and interest at seven per .cent per annum from May 14, 1888; and that on November 3,1887, the appellee made an account in writing of the items and matters set forth in the petition, together with the written contract existing between the parties, and after making oath thereto, as required by law, filed the same in the clerk’s office of said county, and the same was duly recorded therein. The court further found that the appellee had a first valid and subsisting mechanic’s lien for said sum of $922.78 and interest upon the premises described in his petition, to-wit, the east one-half of lot 2, in block 167, in the city of Omaha, in said county, and that the appellee was entitled to have said lien enforced. It was therefore considered, adjudged, and decreed by the court that said appellee have and recover from the appellant, Frederick C. Festner, the said sum of $922.78 and interest thereon at seven per cent from May 14, 1888, and his costs in this action; and in case the same was not paid within twenty days from the entry of that decree, an order should issue to the sheriff of that county commanding him to sell said premises as upon execution and apply the proceeds thereof in payment of the amount so found due upon the confirmation of said sale. To all of which said findings and decree the appellant excepted.on the record and appealed the cause to this court.

There is neither a petition in error, nor assignment of error in this case. Therefore the errors argued by counsel in their brief cannot be considered. The only issue presented by the pleadings is that arising in the allegations of the petition as stated. The contract between the parties was introduced in evidence by the plaintiff. As it appears in the bill of exceptions it is seen that the plaintiff agreed to furnish the material and perform the labor necessary to build, finish, and complete, in a first-class, workmanlike manner, to the full and complete satisfaction of the defend[337]*337ant, all of the mason work, including brick work, excavating, concreting, pressed brick and cut stone for a brick store building to be erected on the half lot therein described; the furnishing of material and performance of labor to be under the supervision and direction of Geo. L. Eisher, architect, and to be in accordance with the plans and specifications, including all writing and figuring on the same, and which plans and specifications were declared to be a part of the contract. The plans and specifications, however, were not. introduced in evidence. It seems to have been taken for granted by all parties throughout the trial that the contract in its terms, or the plans and specifications, or some order of the architect, required the concrete footing under one of the walls of the building designated as a party wall to be-twenty inches in depth. The plaintiff, as a witness in his own behalf, testified, among other things, that it was the contract and agreement between the parties that the concrete footing under the party wall should be twenty inches in height, and that the concrete of the present building is twenty-two inches thick from one end to the other. On cross-examination he repeated that he made the concrete twenty-two inches. To the question, “ When did you make the measurements so that you ascertained the depth of the concrete?” he answered, “At the time we placed it in; and also stated that Nelson, Anderson, and Whitit, men who were working for him at the time, were present when he did it.” He further testified in answer to *

Q. In what way did you make the measurement, rod or line?

A. No, sir; — we take — with the laborers we generally take — in a trench, that way, we generally drive stakes down to the depth we wish it, and we generally place three stakes, one at the end, at each end, and one in the middle, so they can keep it straight, and we place them probably six or seven feet apart, near the trench.

[338]*338Q,. The original depth of the concrete was to be fourteen inches, wasn’t it?

A.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
44 N.W. 441, 28 Neb. 333, 1889 Neb. LEXIS 351, Counsel Stack Legal Research, https://law.counselstack.com/opinion/livesey-v-festner-neb-1889.