Little Cypress-Mauriceville Consolidated Independent School District v. Pal Environmental Safety Corp.

CourtCourt of Appeals of Texas
DecidedJanuary 16, 2025
Docket09-24-00069-CV
StatusPublished

This text of Little Cypress-Mauriceville Consolidated Independent School District v. Pal Environmental Safety Corp. (Little Cypress-Mauriceville Consolidated Independent School District v. Pal Environmental Safety Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Little Cypress-Mauriceville Consolidated Independent School District v. Pal Environmental Safety Corp., (Tex. Ct. App. 2025).

Opinion

In The

Court of Appeals

Ninth District of Texas at Beaumont

__________________

NO. 09-24-00069-CV __________________

LITTLE CYPRESS-MAURICEVILLE CONSOLIDATED INDEPENDENT SCHOOL DISTRICT, Appellant

V.

PAL ENVIRONMENTAL SAFETY CORP., Appellee

__________________________________________________________________

On Appeal from the 260th District Court Orange County, Texas Trial Cause No. 230198-C __________________________________________________________________

MEMORANDUM OPINION

This is an interlocutory accelerated appeal about a contractual agreement

between Appellant Little Cypress-Mauriceville Consolidated Independent School

District (“Appellant,” “LCM,” or “District”) and PAL Environmental Safety Corp.

(“Appellee” or “PAL”). PAL agreed to perform remediation services at several of

LCM’s campuses after Hurricane Harvey in 2017. PAL performed work for LCM,

LCM made certain payments to PAL but refused to pay further requested amounts,

1 and PAL filed a lawsuit against LCM, asserting claims for a suit on sworn account,

a breach of contract, and seeking damages and attorney’s fees. LCM filed a plea to

the jurisdiction, arguing that the claims are barred by governmental immunity and

that PAL stated no basis for a waiver of immunity necessary to establish jurisdiction

over LCM. The trial court denied LCM’s plea to the jurisdiction, and LCM appeals

arguing the trial court erred in denying its plea to the jurisdiction. See Tex. Civ. Prac.

& Rem. Code Ann. § 51.014(a)(8) (permitting an interlocutory appeal of a trial

court’s order denying a governmental entity’s plea to the jurisdiction); Tex. Loc.

Gov’t Code Ann. §§ 271.151-160 (“Chapter 271, Subchapter I,” setting forth the

requirements for adjudication of claims arising under written contracts with local

governmental entities); Tex. R. App. P. 28.1(a) (providing rules for accelerated

appeals). We affirm.

Procedural Background

PAL’s First Lawsuit Against LCM

On September 11, 2017, LCM and PAL entered into a written contract

(“Contract”) for PAL to perform emergency clean-up services at various campuses

in the LCM school district due to damages sustained during Hurricane Harvey. The

Contract gave a “contract estimate” of $10,500,000, and described this amount as a

“not to exceed price for work performed based upon currently known conditions

[and] not a lump sum contract price[.]” The scope of work under the Contract

2 outlined several specific items related to storm damage and also included “[o]ther

Emergency Protective Measures as may be requested or required[,]” and the

Contract also stated,

The Work described in this Scope of Work is based upon an initial inspection only. Because of unknowns and uncertainties when dealing with damages of the nature reflected in this Scope of Work, changes to this Scope of Work, including changes in or to the rates, charges and time frames specified herein, may become necessary as the Work progresses.

The Contract further provided that “[c]hange order forms will be submitted in

writing to [LCM] or AUTHORIZED REPRESENTATIVES[,]” and also stated,

“[a]ssignments given to ‘PAL’ personnel that deviate from initial understanding of

scope of work either verbally or in writing will be considered a CHANGE ORDER.”

On December 12, 2018, PAL filed suit against LCM in trial cause number

D180501-C, asserting claims for breach of contract and suit on sworn account and

alleging that, although LCM had paid PAL $10,500,000, there was still a balance

due of $9,703,548.07. In October of 2019, the parties entered into a Rule 11

Agreement that states the parties agreed that the statute of limitations was tolled for

24 months (as of the date the trial court signed an order dismissing the action), and

that if LCM did not pay PAL the unpaid balance, PAL would refile its lawsuit and

the 24 months that the suit was tolled would not be counted against the limitations

period. The trial court signed an Order Granting Non-Suit Without Prejudice

dismissing PAL’s claims against LCM in trial cause number D180501-C. 3 PAL Refiles Its Suit Against LCM

On July 13, 2023, PAL filed its second suit against LCM in trial cause number

230198-C, again asserting claims for suit on a sworn account and breach of contract

and adding a claim for quantum meruit and unjust enrichment. 1 According to the

Original Petition (“Petition”) in the second suit, once PAL began work, it

encountered conditions that were previously unknown and that required additional

work and cost, and that LCM instructed PAL verbally and in writing to complete the

additional work. PAL alleged that on December 15, 2017, PAL remitted invoices to

LCM totaling approximately $13,400,000, and at LCM’s request, on January 8,

2018, PAL representatives addressed the LCM Board of Trustees to explain its work

and invoices. The Petition alleged that, on January 24, 2018, PAL delivered its final

invoices to LCM, totaling $20,203,548.07.

According to the Petition, PAL did not receive full payment by the summer

of 2018. PAL alleges that LCM told PAL that LCM was waiting on funding from

FEMA (the Federal Emergency Management Agency) related to the work, and that

FEMA might require “a separate written change order to further document the added

scope of work” that PAL performed. PAL further alleges that it submitted a written

change order to LCM in August of 2018, but the LCM Board of Trustees did not

execute the change order. PAL asserts that in a meeting on August 13, 2018, the

1 PAL’s equitable claims are not at issue in this appeal. 4 LCM Board of Trustees noted, “[i]n accordance with FEMA regulations, the District

must pay reconstruction costs and then be reimbursed[,]” but LCM failed to pay PAL

in full. In its Petition, PAL alleges that it entered into a tolling agreement with LCM

based on assurances from LCM that it was working to obtain payments from FEMA

and to make payment to PAL, yet LCM has failed to pay in full. According to the

Petition, LCM paid PAL $10,500,000 and there is a remaining balance of

$9,703,548.07. PAL contends the Legislature waived immunity for this breach of

contract claim against LCM pursuant to sections 271.151 and 271.152 of the Texas

Local Government Code. See Tex. Loc. Gov’t Code Ann. §§ 271.151-.152 (setting

forth requirements for adjudication of claims arising under written contracts with

local governmental entities). PAL also contends that the suit was timely pursuant to

the parties tolling agreement and that PAL is entitled to attorney’s fees.

PAL attached documents to the Petition including a copy of the parties’

written agreement; copies of invoices from PAL to LCM; and an affidavit from

Joseph Annarumma, PAL’s Vice President of Finance, stating that LCM still owes

PAL $9,703,548.07.

LCM’s Plea to the Jurisdiction and Original Answer Subject to Plea

LCM answered the Petition with a general denial and asserted various

defenses, including that PAL’s claims are barred by governmental immunity, statute

of limitations, and failure to exhaust administrative remedies. LCM also filed a Plea

5 to the Jurisdiction (“Plea”), arguing that (1) PAL’s claims are not based on a properly

executed written contract stating its essential terms, (2) PAL failed to exhaust its

administrative remedies before filing its lawsuit, and (3) PAL’s claim is barred by

limitations.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Liberto v. D.F. Stauffer Biscuit Co.
441 F.3d 318 (Fifth Circuit, 2006)
Ford Motor Co. v. Ridgway
135 S.W.3d 598 (Texas Supreme Court, 2004)
Texas Department of Parks & Wildlife v. Miranda
133 S.W.3d 217 (Texas Supreme Court, 2004)
Valence Operating Co. v. Dorsett
164 S.W.3d 656 (Texas Supreme Court, 2005)
City of Galveston v. State
217 S.W.3d 466 (Texas Supreme Court, 2007)
Harris County Hospital District v. Tomball Regional Hospital
283 S.W.3d 838 (Texas Supreme Court, 2009)
Kirby Lake Development, Ltd. v. Clear Lake City Water Authority
320 S.W.3d 829 (Texas Supreme Court, 2010)
The City of Houston v. Steve Williams
353 S.W.3d 128 (Texas Supreme Court, 2011)
Tooke v. City of Mexia
197 S.W.3d 325 (Texas Supreme Court, 2006)
Bland Independent School District v. Blue
34 S.W.3d 547 (Texas Supreme Court, 2000)
Wichita Falls State Hospital v. Taylor
106 S.W.3d 692 (Texas Supreme Court, 2003)
Dow Chemical Company v. Benton
357 S.W.2d 565 (Texas Supreme Court, 1962)
Padilla v. LaFrance
907 S.W.2d 454 (Texas Supreme Court, 1995)
City of Roanoke v. Town of Westlake
111 S.W.3d 617 (Court of Appeals of Texas, 2003)
Tanenbaum Textile Co. v. Sidran
423 S.W.2d 635 (Court of Appeals of Texas, 1967)
Breceda v. Whi
187 S.W.3d 148 (Court of Appeals of Texas, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
Little Cypress-Mauriceville Consolidated Independent School District v. Pal Environmental Safety Corp., Counsel Stack Legal Research, https://law.counselstack.com/opinion/little-cypress-mauriceville-consolidated-independent-school-district-v-pal-texapp-2025.