Lisa Sinclair v. CMI Solar & Electric, Inc.

CourtDelaware Court of Common Pleas
DecidedOctober 31, 2024
DocketCPU4-23-001732
StatusPublished

This text of Lisa Sinclair v. CMI Solar & Electric, Inc. (Lisa Sinclair v. CMI Solar & Electric, Inc.) is published on Counsel Stack Legal Research, covering Delaware Court of Common Pleas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lisa Sinclair v. CMI Solar & Electric, Inc., (Del. Super. Ct. 2024).

Opinion

IN THE COURT OF COMMON PLEAS FOR THE STATE OF DELAWARE IN AND FOR NEW CASTLE COUNTY

LISA SINCLAIR, ) ) Appellant, ) ) V. ) C.A. No: CPU4-23-001732 ) CMI SOLAR & ELECTRIC, INC., ) ) Appellee. ) Submitted: September 10, 2024 Decided: October 31, 2024 Lisa Sinclair James R. Donovan, Esq. 26 Deer Run Doroshow, Pasquale, Krawitz & Bhaya Newark, DE 19711 1008 N. Walnut Street Self-represented Appellant Milford, DE 19963 Attorney for Appellee DECISION AFTER TRIAL

Danberg, C.J. This breach of contract action, which is before the Court on appeal de novo from a decision of the Justice of the Peace Court, stems from an agreement between Appellant Lisa Sinclair (“Ms. Sinclair”) and Appellee CMI Solar & Electric, Inc. (“CMI”) for the sale and installation of a generator. On September 10, 2024, the case proceeded to trial on Ms. Sinclair’s breach of contract claim and breach of implied warranty of good quality and workmanship.’ At the conclusion of trial, the Court reserved decision. This is the Court’s final decision after trial.

FACTS AND PROCEDURAL HISTORY

On or about April 19, 2021, Ms. Sinclair and CMI entered into an installation agreement (the “Agreement”) whereby CMI was to supply and install a generator (the “Generator”) into Ms. Sinclair’s home.” The Agreement included the Generator, a 5-year limited manufacturer’s warranty, permits and inspection fees, and a 120 gallon above ground propane tank supplied and installed by Dixieland Energy

(hereinafter “Dixieland”).? Further, the Agreement specified the use of composite

! Originally CMI initiated suit between the parties for a breach of contract claim in the Justice of the Peace Court to recover for Ms. Sinclair’s refusal to pay the balance owed under the parties’ contract. In Justice of the Peace Court, Ms. Sinclair brought counterclaims for a breach of contract and breach of implied warranty of good quality and workmanship. After the Justice of the Peace Court’s order, Ms. Sinclair filed a notice of appeal and, although she was the defendant below, Ms. Sinclair filed her counterclaim as the operable “complaint” in this Court. While not consistent with Rule 72.3—which requires the plaintiff-below to file the complaint on appeal—CMI failed to object, or otherwise challenge the procedural error, and given that the notice of appeal was timely filed, Ms. Sinclair’s procedural error did not divest this Court of jurisdiction. See CCP Civ. R. 12(h); see, e.g., Emerald Prs v. Berlin, 726 A.2d 1215, 1224 (Del. 1999) (“Issues not briefed are deemed waived.”).

2 Ex. 5 at 1.

3 Ex, 2 at 2-3. wiring.’ Notably, CMI’s “installation philosophy”—which as expressly stated— guaranteed not only that Ms. Sinclair’s Generator would function properly, but also that it would be installed safely, thoroughly, and with an attention to aesthetics.° In exchange, Ms. Sinclair agreed to pay $6,560.95,° of which she put down a $4,020 deposit on May 7, 2021.’

Unfortunately, execution of the Agreement seemed doomed from the start. Delivery of the Generator was delayed for months, largely due to the COVID-19 pandemic.® It was not until early 2022, nearly nine-months after execution of the Agreement, that installation of the Generator commenced. Had delivery delays been the extent of the shortcomings, perhaps this contract would have been fulfilled with only slight irritation. Regrettably, the installation did not proceed satisfactorily.

The next issue arose over the installation of the Generator, a project which spanned three days. At Ms. Sinclair’s insistence, the Generator was installed atop of an existing wooden platform. While seasoned journeymen completed most of the

project, inexperienced apprentices were allowed to work unsupervised for a period

4 Ex. 2 at 2-3.

> Ex, 2 at 1.

6 Ex, 2 at 1.

7 Ex, 12 at 2; Ex. 30 at 3.

8 Ex. 7 at 3. It should be noted that CMI failed to keep Ms. Sinclair updated about the progress of the Generator’s delivery. Instead, Ms. Sinclair reached out and followed-up not only with CMI but with the Generator’s manufacturer to find out about delivery. Further, the Generator was damaged in shipment but two of the same generators where delivered, allowing CMI to use the second one for installation. of time.? At trial, CMI conceded that allowing the unsupervised apprentice work was improper. Indeed, issues with the quality of work were undeniable. By all accounts, it did not live up to the “aesthetically pleasing” contractual term. Further, the installation was not up to code and thus failed the electrical inspection.'? However, CMI promptly remedied the electrical deficiencies and passed reinspection within a month. |!

The installation of the propane tank, which fueled the generator, also did not proceed smoothly. CMI’s subcontractor for this part, Dixieland, performed the work without a permit.'2 Consequently, Ms. Sinclair was fined $300. '> Moreover, by CMI’s own admission, the placement of the propane tank was in violation of county code as it was less than ten (10) feet from the Generator." At this stage, Ms. Sinclair was not shy in expressing her dissatisfaction with the work performed. After numerous complaints, CMI informed Ms. Sinclair, via email, its “work is

completed” while also acknowledging outstanding work yet to be performed.!°

° Ex. 13 at 1.

10 x. 15 at 1 (inspection failed for two issues: (1) a cover on a PVC conduit; and (2) open breakers knockouts in Ms. Sinclair’s panel).

"Rx. 20 at 1.

12 Fx. 17 at 1; Ex. 18 at 1; Ex. 22 at 1.

13 Bx. 1 at 1; Ex. 20 at 1. Testimony of Mr. Davis revealed that CMI did pay for the $300 fine issued by New Castle County for working without a permit.

14 By, 17 at 1; Ex. 18 at 1; Ex. 40 at 5. Dixieland was subcontracted by CMI. As such, CMI was responsible for all work completed by Dixieland.

'S Ex, 22 at 1.

4 Conspicuously, this communication occurred a few weeks in advance of the scheduled final inspection.

The day before final inspection, CMI notified Ms. Sinclair that the project as it existed was fated to fail final inspection and corrective action was needed.!° Specifically, the county inspector indicated that the Generator could not be positioned atop the wooden platform.'? This issue was forecasted early on; the wooden platform had been a subject of much discussion.'® According to CMI, they advised Ms. Sinclair that the wooden platform was not a proper base, but Ms. Sinclair insisted that it would not be a problem. Ms. Sinclair, on the other hand, maintains that she expressed concern about the platform all along.!? In any event, CMI’s eleventh hour notification coupled with their prior expression that “work is completed” struck a nerve with Ms. Sinclair. Despite its request, Ms. Sinclair prohibited CMI’s return to her property and refused to pay the final invoice of $3,080.73. ”°

Subsequently, Ms. Sinclair endeavored to have the work completed by other contractors. In doing so, she discovered additional inadequacies in the work

performed by CMI. Namely, SER wiring was used to connect the Generator to the

16 Ex. 24 at 1; Ex. 25 at 1.

'7 Ex, 25 at 1.

18 Ey, 2 at 11; Ex. 6 at 1; Ex. 18 at 1; Ex. 25 at 1; Ex. 27 at 1; Ex. 29 at 1; Ex. 34 at 1; Ex. 36 atl. '9 Ex, 16 at 1; Ex. 18 at 1.

20 Rx. 24 at 1; Ex. 26 at 1. electrical box while the Agreement specifically called for composite wiring. 21 Also, an internal switch on the generator was not turned on, which resulted in the emission of carbon dioxide into her garage. Additionally, the replacement contractor had to relocate the propane tank to comply with county code. In total Ms. Sinclair spent $8,810.83 to remedy these issues. 7”

Due to Ms.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

USH Ventures v. Global Telesystems Group, Inc.
796 A.2d 7 (Superior Court of Delaware, 2000)
Emerald Partners v. Berlin
726 A.2d 1215 (Supreme Court of Delaware, 1999)
Johnson v. State
929 A.2d 784 (Supreme Court of Delaware, 2007)
VLIW TECHNOLOGY, LLC v. Hewlett-Packard Co.
840 A.2d 606 (Supreme Court of Delaware, 2003)
Emmett S. Hickman Co. v. Emilio Capaldi Developer, Inc.
251 A.2d 571 (Superior Court of Delaware, 1969)
BioLife Solutions, Inc. v. Endocare, Inc.
838 A.2d 268 (Court of Chancery of Delaware, 2003)
Beard Research, Inc. v. Kates
8 A.3d 573 (Court of Chancery of Delaware, 2010)
Bye v. Mc-Caulley & Son Co.
76 A. 621 (Superior Court of Delaware, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
Lisa Sinclair v. CMI Solar & Electric, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/lisa-sinclair-v-cmi-solar-electric-inc-delctcompl-2024.