Lipinsky v. Hufft

533 P.2d 328, 271 Or. 572, 1975 Ore. LEXIS 538
CourtOregon Supreme Court
DecidedApril 1, 1975
StatusPublished
Cited by5 cases

This text of 533 P.2d 328 (Lipinsky v. Hufft) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lipinsky v. Hufft, 533 P.2d 328, 271 Or. 572, 1975 Ore. LEXIS 538 (Or. 1975).

Opinion

*573 BRYSON, J.

Plaintiff brought this action to recover the balance due under the terms of a contract to remodel a building. Defendant’s motions for a nonsuit and a directed verdict were denied, and the jury returned a verdict in favor of plaintiff. On defendant’s motion the court set aside the judgment and entered judgment in favor of the defendant n.o.v. Plaintiff appeals, contending the trial court erred in granting the judgment notwithstanding the verdict.

We view the evidence in the light most favorable to the plaintiff. The plaintiff is entitled to the benefit of all favorable evidence and all favorable inferences which may be reasonably drawn from the evidence. Austin v. Sisters of Charity, 256 Or 179, 183, 470 P2d 939 (1970); Krause v. Eugene Dodge, Inc., 265 Or 486, 490, 509 P2d 1199 (1973).

On October 7, 1968, plaintiff, as contractor, and defendant, as owner, entered into the following contract :

“WITNESSETH:
“That in consideration of the mutual promises and conditions herein contained to be performed by the parties,
“1. CONTBACTOB agrees to_construct according to plans and specs, addition and remodel Pleasant Valley Nursing Home according to Architect, James W. Keefe’s plans dated 5/28/68_ ON THE PBEMISES of SECOND PARTY located at_395 W. 29th Eugene, Lane County, Oregon, for the sum of Sixty-thousand three hundred seven Dollars ($60,307) including plus *574 cost of materials, which SECOND PARTY agrees to pay as follows_as work progresses.
Interest shall be charged on any late payments at the rate of eight per cent per annum. It is understood that the cost of the contracted job herein provided shall be a first and prior lien on said premises and that CONTRACTOR may take all steps necessary to protect his rights as such.
“2. Costs of any changes from original plans and design requested by owner shall be agreed upon and endorsed hereon before work is started.
“3. CONTRACTOR agrees to complete said job in a first-class manner and in accordance with the best practices of the trade unless otherwise specified. Said job to be completed in 90 work days_working days. * * *.
U# * & * *
“4. * * * The party’s [sic] further agree that the unsuccessful party in any litigation shall pay such sum as the court may adjudge reasonable as attorney’s fees for the prevailing party.
“IN WITNESS WHEREOF, the parties have hereunto set their hands and seals the day and year first hereinabove written.
/s/ Jimmy L. Hufft (SEAL)
/s/ A. B. Lipinsky (SEAL)”
Plaintiff’s complaint alleged:
“I
“That the parties entered into a written agreement on October 7, 1968 in which Plaintiff agreed to construct according to plans and specifications an addition, and to remodel the Pleasant Valley Nursing Plome located at 395 West 29th Street, Eugene, Oregon, the plans and specifications to be submitted by an architect, James W. Keefe.
“II
“That the Defendant agreed to pay to the Plain *575 tiff, tlie sum of $60,307.00, which said sum was to be paid as work progressed.
“HI
“That the parties further agreed orally that the Defendant would pay to the Plaintiff the additional sum of $2,500.00 to be evidenced by a promissory note to be payable one-year following the completion of the project. That the Defendant has never provided the Plaintiff with the said promissory note.
“IV
“That the parties further agreed that any late payments should bear 8% interest per annum.
“V
“That the parties further agreed that the Defendant should bear the additional costs of any extra work which constituted changes from the original plan and design * * *.
ÍÍ # # # * *
“VII
“That the Defendant has only paid the sum of $58,807.00 in connection with the said agreement,
“VIII
“That it was further agreed that should the Plaintiff be successful in any litigation, the Defendant shall pay such sum as the Court may judge reasonable as attorney’s fees to the Plaintiff. * * *

Defendant’s answer admits each of the allegations in plaintiff’s complaint above set forth and counterclaimed against plaintiff for damages for plaintiff’s failure to complete performance of the contract within 90 days, for failure to perform the contract in a good and workmanlike manner, and for reimbursement because of overpayment of the contract, together with attorney’s fees.

*576 Plaintiff’s amended complaint sets forth three requests for relief: (1) the balance of the written contract of $1,500; (2) an additional sum of $2,500 which the defendant would pay to the plaintiff after completion of the contract; and (3) extra work performed by plaintiff outside of the original contract in the amount of $3,563.74. The court instructed the jury as follows:

“Putting this case very simple, Ladies and Gentlemen, along with a couple of other issues that I shall tell you about, you are to determine whether Jimmy Hufft owes Mr. Lipinsky any money because of this transaction they were involved in, whatever you find the transaction to be, or does Tony Lipinsky owe Jimmy Hufft because of this transaction that they have entered into, or is the situation such that neither one of them owe each other anything.
“In other words, is it a push and neither one of them owe each other anything?”

The evidence shows that the parties originally entered into a contract for the sum of $65,807, but defendant could not secure a loan in excess of $60,000. Thereafter the two parties conferred with the architect ; certain changes were made in an attempt to reduce the amount of the contract and defendant agreed to perform part of the labor and further agreed, as admitted, thát he would pay the plaintiff an additional $2,500 following the completion of the project. This accounts for the execution of the new contract involved in this litigation in the amount of $60,307.

Mr. Keefe, defendant’s architect and the supervisor of the project, testified that by May of 1969, but for certain minor details, plaintiff had substantially completed all of the work required under the architect’s plans and specifications. He further testified *577

Free access — add to your briefcase to read the full text and ask questions with AI

Related

King v. All Pro Services, Inc.
852 P.2d 943 (Court of Appeals of Oregon, 1993)
Gardner v. First Escrow Corp.
696 P.2d 1172 (Court of Appeals of Oregon, 1985)
Blank v. Far West Federal Savings
575 P.2d 148 (Oregon Supreme Court, 1978)
Green v. Uncle Don's Mobile City
568 P.2d 1375 (Oregon Supreme Court, 1977)
Jacobs v. Tidewater Barge Lines, Inc.
562 P.2d 545 (Oregon Supreme Court, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
533 P.2d 328, 271 Or. 572, 1975 Ore. LEXIS 538, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lipinsky-v-hufft-or-1975.