Link-Sulzbach Corp. v. Robinson

15 Pa. D. & C.4th 365, 1992 Pa. Dist. & Cnty. Dec. LEXIS 245
CourtPennsylvania Court of Common Pleas, Montgomery County
DecidedMarch 25, 1992
Docketno. 89-02339
StatusPublished
Cited by1 cases

This text of 15 Pa. D. & C.4th 365 (Link-Sulzbach Corp. v. Robinson) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Montgomery County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Link-Sulzbach Corp. v. Robinson, 15 Pa. D. & C.4th 365, 1992 Pa. Dist. & Cnty. Dec. LEXIS 245 (Pa. Super. Ct. 1992).

Opinion

BROWN, J.,

In July of 1985 defendant, Fred I. Robinson, invited Dennis Link, the president of plaintiff Link-Sulzbach Corp., to submit a bid for electrical work in a building Robinson was renovating [366]*366at 614 Hollywood Avenue in Cherry Hill, New Jersey.1 On August 8,1985, Link received a set of electrical plans, E-l, E-2, from the project’s architect, Ivan Blitz (Blitz Group plans) and, after discussing those plans with Robinson and Steve Metzler, Robinson’s office manager, Link submitted a proposal for $66,000.

Robinson informed Link that this figure was high and that he’d “appreciate it if [Link] could do something to get that [bid] down.” Link consequently redesigned some of the lighting on the Blitz Group plans and lowered his bid to $60,000. When they agreed to the price Robinson and Link shook hands and Robinson said, “Fine, begin.”2

On August 16, 1985, at Robinson’s request, Link submitted a letter outlining the scope of the bid; it states:

“We are pleased to confirm our arrangement to perform the electrical work specified at subject location. This work will include all electrical work specified on drawings from the Blitz Group E-l, E-2, dated August 1, 1985, as amended in subsequent discussions.
“Specifically, our work will include the following:...
“Our estimate to complete this work as discussed with you is $60,000.”

[367]*367On the same day that Link mailed this confirmation letter to Robinson, Steven Shore, an electrical engineer hired by Blitz, mailed Link-Sulzbach a second set of electrical plans (Shore plans). Although Link received the Shore plans sometime after the project started in late August 1985, Link-Sulzbach electricians used the Blitz Group plans as the basis of their work. This second set was similar to the first set but not identical; e.g. it required additional electrical circuitry and panels for a computer room.

Link-Sulzbach finished the electrical work in December 1985 and a certificate of completion was signed in January 1986. At the request of Robinson’s representatives, Blitz and Stewart Krevolin, the construction coordinator, Link was asked to perform some of the “extra” work detailed by the Shore plans and he complied. All extras, however, were submitted first via change orders for Blitz and Krevolin to approve and these requests were initialed as “okay, not on print.” “Not on print” meant not on the Blitz Group plans.

On August 26th, September 25th, October 7th, October 24th and November 21st Link-Sulzbach submitted invoices approved for payment totaling $67,754.23. (Each job order listed on these invoices was initialed by Blitz and/or Krevolin after they determined that the work had been done.) On October 24, 1985, and revised on November 6,1985, the Blitz Group sent the plaintiff a “final punch list,” a list of work which needed to be corrected or finished before the job could be considered complete. On December 5, 1985, Link, Krevolin and Blitz made a site inspection.

On December 26, 1985, after a meeting with Link, Blitz and Krevolin, the Blitz Group sent Link-Sulzbach [368]*368a letter detailing which invoices for additional work were approved for payment and which were not. The plaintiff, however, was not paid for any of the approved additional work. As of December 31, 1985, and continuing to the present, the defendants have paid only $50,000 of the total of $67,754.23 due.

On February 13, 1989, plaintiff filed suit against the defendants for breach of contract and demanded judgment in the amount of $17,754.23, together with costs, and interest from the date of demand, the date the invoices were mailed. The defendants responded with an amended answer with new matter and counterclaim filed September 8, 1989, alleging that plaintiff’s work was incomplete, defective and in violation of the electrical code and demanded judgment “estimated not to be in excess of $20,000.”

A bench trial was held on January 9, 10 and 11, 1991. On January 22nd, we found for the plaintiff and against the defendants in the sum of $23,302.43 plus costs. As part of costs, the plaintiff was also awarded $4,991 in counsel fees against all defendants for conduct in defense of this claim within the meaning of section 2503(7) and (9) of Title 42 Pa.C.S.

Post trial the defendants moved for judgment notwithstanding the verdict and/or a modification of the verdict and/or a new trial.

A trial court may enter judgment n.o.v. only in a clear case where, after reviewing the evidence in the light most favorable to the plaintiff, no reasonable minds could fail to agree that the verdict was improper. Solomon v. Baum, 126 Pa. Commw. 646, 650, 560 A.2d 878, 880, appeal denied, 578 A.2d 930 (1989).

[369]*369A trial court’s denial of a new trial motion is within its sound discretion and will not be reversed in the absence of a manifest abuse of that discretion or a clear error of law. Id. An appellate court’s role is to determine whether the trial court committed an error of law which controlled the outcome of the case and led to an incorrect result. Nacarati v. Garrett, 352 Pa. Super. 437, 443, 506 A.2d 428, 430 (1986).

The defendants’ first argument, that the weight of the evidence proves that the scope of the contract was defined by the Shore plans, not the Blitz Group plans, is patently false and unsupported by the evidence.

The scope of the work to be performed by LinkSulzbach was set forth cleárly in Link’s letter to Robinson dated August 16,1985, a letter which Robinson conceded he received but did not fully read. That letter states that “the work will include all electrical work specified on drawings from the Blitz Group E-l, E-2 dated August 1, 1985, as amended in subsequent discussions.”

The uncontradicted evidence further demonstrates that the Shore plans were not issued or sent out until August 16,1985, on or after the date of Link’s letter to Robinson confirming their contractual relationship. Therefore, both parties knew or should have known that the Shore plans did not control the terms of the agreement. Logic demands that a bid based on the Blitz plans would not set a dollar cap for work called for in a second set never seen by Link.

Contrary to the defendants’ contentions, Link was not told at the time he entered into the contract with Robinson that his bid was to include the work specified on the Shore plans or that Robinson mistakenly believed that the $60,000 bid was based on the Shore plans. Robinson [370]*370left the matter of plans and payment to his architect Blitz and paid no attention to the plans or to Link’s August 16th letter. In fact, he stated he never reviewed any plans with Link and that he “didn’t even know there were two sets of plans” until several days before the trial.

Moreover, Robinson and Link were the only witnesses who had any direct knowledge of the parties’ contractual relationship; Blitz was told of the contract after he returned from vacation and was not involved in any negotiations.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cummins v. Atlas Railroad Construction Co.
814 A.2d 742 (Superior Court of Pennsylvania, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
15 Pa. D. & C.4th 365, 1992 Pa. Dist. & Cnty. Dec. LEXIS 245, Counsel Stack Legal Research, https://law.counselstack.com/opinion/link-sulzbach-corp-v-robinson-pactcomplmontgo-1992.