Lilly Investments v. City of Rochester

674 F. App'x 523
CourtCourt of Appeals for the Sixth Circuit
DecidedJanuary 5, 2017
Docket15-2289
StatusUnpublished
Cited by10 cases

This text of 674 F. App'x 523 (Lilly Investments v. City of Rochester) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lilly Investments v. City of Rochester, 674 F. App'x 523 (6th Cir. 2017).

Opinion

*524 COOK, Circuit Judge.

This case concerns Louis Leonor’s efforts to open a dental clinic in Rochester, Michigan. The clinic stands nearly com: píete, but in May 2013 Rochester issued a stop-work order preventing Leonor from finishing and operating the clinic, pi’ompt-ed by an expert’s finding that the clinic does not comply with the conditions of a city permit. That same expert found compliance a few months later after Leonor made corrective changes. Nonetheless, Rochester refused to lift the stop-work order or take an up-down vote on the project unless Leonor waived any legal claims and paid a $40,000 fee. Unwilling to comply with those conditions, Leonor filed a complaint asserting a regulatory taking, which the district court dismissed on ripeness grounds, citing the lack of a “final decision.” We now REVERSE.

I.

Louis Leonor, a dentist turned real-estate developer, purchased property in Rochester to build a modern dental facility. In September 2011, Leonor sought approval from the Rochester Planning Commission (“Commission”) to begin construction. The initial site-plan-approval application called for demolishing the existing structure, a house built in 1878.

At its September meeting, the Commission took issue with demolishing the house in light of its perceived historical significance. Leonor’s architect, Peter Stuhlreyer,' responded that renovating the house would cost twenty-five percent more than tearing it down and starting anew. The parties also discussed parking. City regulations require that commercial developments either provide parking or pay into a parking fund. According to Rochester, Leonor would owe almost a half million dollars if he could not provide onsite parking. Stuhlreyer told the Commission that the planned renovation was financially infeasible without a parking-fee waiver.

After several months of back and forth, the parties reached an agreement in February 2012. In exchange for a full parking-fee waiver, Leonor agreed to demonstrate “reasonable compliance” with the Secretary of the Interior’s Standards for property rehabilitation and save a purported Chinese Elm tree on the property. The Secretary of the Interior’s Standards for the Treatment of Historic Properties (“SOI standards”) set forth different building guidelines depending on the developer’s goal: preservation, rehabilitation, restoration, or reconstruction. Preservation requires the greatest retention of historic features, reconstruction the least. The parties settled on “rehabilitation”—the middle ground that seeks to minimize the alteration of historic features while permitting the removal of materials when necessary. To address interpretive disagreements over “reasonable compliance,” they stipulated that “an outside expert will be selected by the City Administration and paid for by [Leonor].”

The project faced problems soon after construction began in May 2012. Rochester condemned the property in October 2012 after excavation work undermined an adjacent property’s wall and Leonor’s construction crew removed the purported Chinese Elm tree in violation of the approved site plan. Over the next few months, it also became apparent that the parties disagreed over whether construction to date “reasonably complied” with the SOI standards for rehabilitation. To help resolve the brewing dispute, the Commission hired Ed Francis, an architect and “preservation expert,” to evaluate the building’s compliance with the SOI standards. Francis presented his report to the Commission in February 2013, concluding that the project “meets only in part” the SOI standards for *525 rehabilitation. At its April 2013 meeting, the Commission made a finding of noncompliance “as demonstrated by [Fran-cises report.”

The parties worked to resolve their disagreements in the succeeding months. Leonor submitted an amended landscape plan in March, and the Commission told Leonor he could donate to a “tree fund” to remedy the tree removal. The Commission toured the clinic in April and invited Leonor to address the issues highlighted in Francis’s report. To that end, Stuhlreyer met with the City Manager and two historic architects to discuss how Leonor could cure those deficiencies. Their meeting produced an April 25 letter from one of the architects recommending 16 remedial measures. Stuhlreyer made many of those changes, believing that the City Manager authorized him to perform the modifications before receiving Commission approval, a fact that Rochester disputes.

The Commission met on May 6, 2013 to discuss how Leonor could regain approval. Stuhlreyer presented the remedial changes outlined in the April 25 letter to the Commission and explained that many were already complete. ' The Commission expressed its willingness to approve an amended site plan reflecting the current state of the property on the condition that Leonor both make a $5,040 payment to ' offset the tree removal, and work with Rochester to develop a formula to “justify a payment [into] the parking fund less than $480,000.”

Thereafter, Rochester imposed a stop-work order on May 28 after negotiations between the Commission and Leonor broke down. The Commission voted in June to continue the stop-work order until it approved an amended site plan. In July, Leonor submitted to the City Planner a site plan reflecting many of the remedial changes outlined in the April 25 letter. The City Planner reviewed the plan and recommended that the Commission accept it if the Commission was satisfied with those modifications. At its next meeting in August, the Commission took no action on the City Planner’s recommendation. Instead, it instructed the City Attorney to negotiate the removal of the stop-work order, contingent on Leonor waiving “certain rights and claims against the City.” Leonor maintains that he met with city officials in September but refused to agree to any hold harmless condition.

Soon after, the Commission hired Ed Francis to reevaluate the property. This time around, Francis found Leonor’s development “reasonably compliant” based on the changes Leonor made following Francis’s first report. The Commission, however, did not disclose that second report or its favorable findings until Leonor later obtained it in discovery.

Unaware that Francis had now found the clinic “reasonably compliant,” Stuhl-reyer met with the Commission on October 23 to discuss the project. During the meeting, it was suggested that a $40,000 payment into a historic preservation fund would lift the stop-work order. And around this same time, the City Attorney advised Leonor that the stop-work order would remain in place until Leonor submitted yet another amended site plan, though the Commission had not taken up the earlier-submitted plan.

Negotiations stalled over the next three months. Stuhlreyer gave a presentation at the November Commission meeting that covered much of the information that the Commission had previously requested, yet consideration of lifting the stop-work order was tabled until December. In the meantime, the Commission instructed Leonor to submit a complete package consisting of the project as originally approved and a revised site plan. Leonor submitted this *526 information the day of the next Commission meeting in December.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
674 F. App'x 523, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lilly-investments-v-city-of-rochester-ca6-2017.