Liles v. Wedding

733 P.2d 952, 84 Or. App. 350
CourtCourt of Appeals of Oregon
DecidedMarch 11, 1987
DocketC847108; CA A35937
StatusPublished
Cited by8 cases

This text of 733 P.2d 952 (Liles v. Wedding) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Liles v. Wedding, 733 P.2d 952, 84 Or. App. 350 (Or. Ct. App. 1987).

Opinion

*352 DEITS, J.

Defendant appeals from a judgment granting plaintiffs an implied easement across defendant’s property. We modify the judgment.

In 1956, plaintiffs and defendant and her now deceased husband jointly purchased 400 acres of land in Curry County. 1 Plaintiffs moved into an existing house on the property, and defendant built a home. Both houses are on the north side of the Winchuck River, which cuts through the property. The property north of the river has direct access to a county road. In 1956, the property on the south side of the river could be reached either by fording the Winchuck River or over a private road on adjacent property which intersected an old logging road which crossed the southern portion of the parties’ land.

In 1961, the parties divided the property. By warranty deed, defendant conveyed approximately 100 acres to plaintiffs, including the land north of the river on which plain - . tiffs’ house was located and the adjacent land on the south side of the river. Defendant reserved an easement so that she could use an orchard on the land conveyed to plaintiffs.

At the same time, plaintiffs conveyed approximately 300 acres to defendant by warranty deed. The property included the house defendant had built north of the river and the rest of the property south of the river. Plaintiffs granted an easement across their property to defendant, allowing her access to the county road from defendant’s house.

Plaintiffs did not reserve an easement allowing access to and use of the logging road which crossed the southern portion of defendant’s property. Before 1961, the parties both used the road for hunting, tending cattle and maintaining a gravity flow water system that provided water for them. The water system, which was located on the south side of defendant’s property, required a lot of service, part of .which was done by Mr. Liles. After the 1961 conveyance, plaintiffs continued to use the road for two years to maintain the system. In 1971 they used the road for logging.

*353 In 1975, Mr. Wedding and Mr. Liles granted a “Right-Of-Way Easement Deed” to the United States for the Forest Service to construct a logging road across defendant’s property. 2 The road was built in 1977. It crossed defendant’s property, intersecting with the old logging road. The Forest Service road gave defendant direct access from the southern portion of her property to a public road.

In 1984, plaintiffs brought this declaratory judgment action, alleging they were entitled to an easement across defendant’s property. They argued that without the easement their access to the southern portion of their property was by crossing the Winchuck River, which would require the construction of a “substantial bridge.” The trial court held that plaintiffs were entitled to an easement.

Implied easements are not favored, and the claimant has the burden of establishing such an easement. Cheney v. Mueller, 259 Or 108, 485 P2d 1218 (1971). In determining whether an easement should be implied, the circumstances at the time of the conveyance of the disputed property are crucial. 3 Jack v. Hunt et ux, 200 Or 263, 264 P2d 461, 265 P2d 251 (1953). In Rose et ux v. Denn et ux, 188 Or 1, 19, 212 P 1077, 213 P 810 (1949), the court cited a number of factors from Restatement, Property § 476 to consider in deciding if an easement should be implied. The factors in their entirety are:

“(a) [W]hether the claimant is the conveyor or the conveyee,
“(b) the terms of the conveyance,
“(c) the consideration given for it,
“(d) whether the claim is made against a simultaneous conveyee,
“(e) the extent of necessity of the easement to the claimant,
*354 “(f) whether reciprocal benefits result to the conveyor and the conveyee,
“(g) the manner in which the land was used prior to its conveyance, and
“(h) the extent to which the manner of prior use was or might have been known to the parties.”

However, those factors do not have fixed values, see Cheney v. Mueller, supra, 259 Or at 113, but merely aid in determining the intention of the parties. Dressler et al v. Isaacs et al, 217 Or 586, 598, 343 P2d 714 (1959). The purpose in considering the factors, as stated in Dressler, 217 Or at 597, is to determine whether

“had the grantor put his mind to the matter he would have intended the servitude to be created.”

We conclude that the trial court’s holding that an easement should be implied was correct. There are factors in this case which weigh against the implication: the express language of the conveyance warranting against encumbrances and the execution of other easements at the time of the conveyance. In addition, defendant argues that plaintiffs have not shown the requisite degree of necessity at the time of the conveyance. Defendant points out that, during the period preceding the conveyance, “at least half the time” plaintiffs reached the southern portion of their property by fording the river; but it is also clear that at times fording the river was impossible because of flooding. At those times access across the river was not possible, even by boat. Defendant argues, however, that in the past plaintiffs had constructed a temporary bridge and that they could now construct a permanent bridge. However, plaintiffs are not required to show an absolute necessity for an implied easement. As the court held in Jack v. Hunt et ux, supra, 200 Or at 269:

“We are of the opinion that in matters of this kind the rule should be less strict than that of absolute and indispensable necessity. However, such a rule of reasonable necessity should not be grounded in mere convenience, but rather in the necessity appearing from the apparent purpose, the adaptability, and the known use to which the property is to be put. This so that the court may say that the parties as reasonable men contemplated and duly considered the continued use of the quasi easement claimed as necessary to a reasonable enjoyment of the dominant estate at the time of conveyance.”

*355 We believe that plaintiffs had a reasonable necessity for the easement at the time of the conveyance and that, had plaintiffs put their minds to this matter at the time of the conveyance, they would have intended the easement to be created.

We do agree with defendant that the court erred in failing to limit the use of the easement. It is assumed that the parties contemplated not only the present uses, but a normal development of the use of the property. Adams v. Crook, 43 Or App 427, 432, 602 P2d 1143 (1979). As explained in Restatement, Property, § 484,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dayton v. Jordan
381 P.3d 1041 (Court of Appeals of Oregon, 2016)
Gosney v. Glenn
163 S.W.3d 894 (Court of Appeals of Kentucky, 2005)
Bloomfield v. Weakland
92 P.3d 749 (Court of Appeals of Oregon, 2004)
Carroll v. Meredith
59 S.W.3d 484 (Court of Appeals of Kentucky, 2001)
Daniel v. Fox
917 S.W.2d 106 (Court of Appeals of Texas, 1996)
Thompson v. Whinnery
895 P.2d 537 (Supreme Court of Colorado, 1995)
Wayt v. Buerkel
875 P.2d 499 (Court of Appeals of Oregon, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
733 P.2d 952, 84 Or. App. 350, Counsel Stack Legal Research, https://law.counselstack.com/opinion/liles-v-wedding-orctapp-1987.